Project Review Comments

Back to List


Project Name
Palmer Ridge High School Renovation
Description
Renovations to include GEC only and no exterior structural modifications
Location
Applicant
Tolin Mechanical
tbejarano@tolin.com ( tbejarano@tolin.com ) tbejarano@tolin.com ( tbejarano@tolin.com )
File Number
CDR219
Project Manager
Kylie Bagley
Status
Active
Created
7/22/2021 4:24:22 PM

View: Project Documents



Review Comments (19)

Link Agency Comment
View EPC Stormwater Review
9/27/2021 8:54:00 AM
GEC Checklist_v2 9/27/2021 8:54:00 AM
View EPC Stormwater Review
9/27/2021 8:53:25 AM
GEC_v2 9/27/2021 8:53:25 AM
View EPC Stormwater Review
9/27/2021 8:52:05 AM
SWMP_v2 9/27/2021 8:52:05 AM
View EPC Stormwater Review
9/27/2021 8:51:31 AM
ESQCP_v2 9/27/2021 8:51:31 AM
EPC Stormwater Review
9/27/2021 8:51:07 AM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- FAE (to be uploaded by PM with PCD comments)
- ESQCP
- SWMP
- GEC Plan
- GEC Checklist

Please provide the following documents on resubmittal:
- SWMP Checklist (FAE was uploaded in its place)
- PBMP Applicability Form

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
9/27/2021 8:51:07 AM
View PCD Engineering Division
9/23/2021 7:49:47 AM
Financial Assurance Estimate Redlines_v2 9/23/2021 7:49:47 AM
PCD Engineering Division
9/23/2021 7:45:25 AM
Please address unresolved comments on the following documents:

-FAE

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
9/23/2021 7:45:25 AM
PCD Project Manager
9/17/2021 10:21:37 AM
No Planning comments at this time. Comments will be uploaded once PCD Engineering and Stormwater have completed their reviews. 9/17/2021 10:21:37 AM
View PCD Project Manager
8/26/2021 1:22:08 PM
Please see redline comments on SWMP 8/26/2021 1:22:08 PM
View PCD Project Manager
8/26/2021 1:21:39 PM
Please see redline comments on SWMP Checklist 8/26/2021 1:21:39 PM
View PCD Project Manager
8/26/2021 1:21:08 PM
Please see redline comments on GEC Plan 8/26/2021 1:21:08 PM
View PCD Project Manager
8/26/2021 1:20:40 PM
Please see redline comments on FAE 8/26/2021 1:20:40 PM
View PCD Project Manager
8/26/2021 1:20:10 PM
Please see redline comments on ESQCP 8/26/2021 1:20:10 PM
View EPC Stormwater Review
8/25/2021 6:03:17 PM
SWMP Checklist_v1 8/25/2021 6:03:17 PM
View EPC Stormwater Review
8/25/2021 6:02:57 PM
SWMP_v1 8/25/2021 6:02:57 PM
View EPC Stormwater Review
8/25/2021 6:02:35 PM
ESQCP_v1 8/25/2021 6:02:35 PM
View EPC Stormwater Review
8/25/2021 6:02:14 PM
GEC_v1 8/25/2021 6:02:14 PM
EPC Stormwater Review
8/25/2021 6:03:28 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- FAE (to be uploaded by PM with PCD comments)
- GEC Plan
- ESQCP
- SWMP
- SWMP Checklist

Please provide the following documents:
- GEC Checklist
- PBMP Applicability Form

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
8/25/2021 6:03:28 PM
PCD Engineering Division
8/25/2021 3:46:35 PM
Review 1 comments will be uploaded by the project manager. Please address the comments on the following documents:

-Financial Assurance Form

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
8/25/2021 3:46:35 PM