Project Review Comments
- Project Name
- CDR Vollmer Road (Marksheffel to Poco)
- Description
- interim plan approved phase 1 New segment review 7/32/2023 2cd phase in review final plans segmented
- Location
- Applicant
-
JR Engineering
Mike Bramlett ( mbramlett@jrengineering.com )
(303) 267-6240 Mike Bramlett ( mbramlett@jrengineering.com )
(303) 267-6240 - File Number
- CDR2110
- Project Manager
- Kari Parsons
- Status
- Closed
- Created
- 7/21/2021 12:46:28 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
10/23/2023 5:00:49 PM |
Engineering has no further comments on Barbarick-Interim plans. Note: A condition of approval will be added to the CDs and GEC Plan addressing the need for temporary and permanent easements previously discussed. Documents have been forwarded to the ECM Administrator for approval/acceptance and approved plans will be uploaded to EDARP when available. Jeff Rice 719-520-7877 |
10/23/2023 5:00:49 PM | |
EPC Stormwater Review
10/23/2023 2:48:25 PM |
Review 10: EPC DPW Stormwater has no further comments. Planner: no re-review necessary. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
10/23/2023 2:48:25 PM | |
PCD Project Manager
10/18/2023 1:45:59 PM |
Road credit program in process. | 10/18/2023 1:45:59 PM | |
Mountain View Electric Association, Inc.
8/28/2023 10:14:34 AM |
MVEA has existing facilities near and within this parcel of land. If there is any damage, removal or relocation of facilities it will be at the expense of the applicant. | 8/28/2023 10:14:34 AM | |
View |
EPC Stormwater Review
8/23/2023 7:34:18 AM |
SWMP | 8/23/2023 7:34:18 AM |
View |
EPC Stormwater Review
8/23/2023 7:32:50 AM |
GEC Checklist | 8/23/2023 7:32:50 AM |
View |
EPC Stormwater Review
8/23/2023 7:32:15 AM |
GEC Plan | 8/23/2023 7:32:15 AM |
View |
EPC Stormwater Review
8/23/2023 7:30:23 AM |
CDs | 8/23/2023 7:30:23 AM |
PCD Engineering Division
8/22/2023 5:11:04 PM |
Engineering has no further comments on Barbarick-Interim plans. Note: If any ditch grading falls outside of the road Right-of-way, permanent easements will need to be provided for maintenance of roadside ditches. Permanent offsite drainage easements will need to be provided prior to preliminary acceptance. Charlene Durham, PE charlenedurham@elpasoco.com |
8/22/2023 5:11:04 PM | |
PCD Project Manager
8/21/2023 4:38:52 PM |
Engineering and Stormwater will upload comments. Planning has no comments. | 8/21/2023 4:38:52 PM | |
Colorado Springs Public Works
8/18/2023 11:00:32 AM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
8/18/2023 11:00:32 AM | |
EPC Stormwater Review
8/23/2023 7:31:06 AM |
Review 9: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CDs (Vollmer Road - Barbarick Interim Condition) - GEC Plan (Vollmer Road - Barbarick Interim Condition) - GEC Checklist (Vollmer Road - Barbarick Interim Condition) - SWMP (Vollmer Road - Barbarick Interim Condition) EPC DPW Stormwater comments have been resolved on the following documents: - ESQCP (Vollmer Road - Barbarick Interim Condition) - PBMP (Vollmer Road - Barbarick Interim Condition) - SWMP Checklist (Vollmer Road - Barbarick Interim Condition) Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
8/23/2023 7:31:06 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
8/11/2023 9:12:35 AM |
On Construction drawings both interim and final provide profiles showing gas line that runs down Vollmer Road, to ensure minimum bury depth of 3 feet | 8/11/2023 9:12:35 AM | |
Colorado Springs Public Works
8/7/2023 10:33:33 AM |
Traffic Engineering has no further comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
8/7/2023 10:33:33 AM | |
PCD Project Manager
6/5/2023 4:11:21 PM |
Please provide the easements, and update the Chair to Ms. Cami Bremmer | 6/5/2023 4:11:21 PM | |
PCD Engineering Division
6/5/2023 1:59:46 PM |
Engineering has the following comments: See previous memo regarding final checklist items. Note: this review was for the Vollmer North segment; if anything changes on the interim Barbarick segment let us know to complete that review. The following items need to be revised and resubmitted for Vollmer North: - Signed easement documents. - Revise Stan VanderWerf to Cami Bremer on the two temporary easements to the County. Note: comments on the SWMP, CDs and GEC Plans and checklist have been resolved with notes added by Staff. -- Jeff Rice - 719-520-7877 |
6/5/2023 1:59:46 PM | |
EPC Stormwater Review
6/5/2023 2:15:53 PM |
Review 8: EPC DPW Stormwater comments have been resolved on the following documents: - CDs (Vollmer North) - ESQCP (Vollmer North) - GEC Plan (Vollmer North) - GEC Checklist (Vollmer North) - PBMP (Vollmer North) - SWMP Checklist (Vollmer North) - SWMP (Vollmer North) EPC DPW Stormwater has no further comments. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
6/5/2023 2:15:53 PM | |
View |
PCD Engineering Division
4/27/2023 2:44:35 PM |
(Vollmer Barbarick Interim GEC redlines) | 4/27/2023 2:44:35 PM |
View |
PCD Engineering Division
4/27/2023 2:43:41 PM |
(Vollmer North GEC redlines) | 4/27/2023 2:43:41 PM |
View |
PCD Engineering Division
4/27/2023 2:43:06 PM |
(Vollmer North CD redlines) | 4/27/2023 2:43:06 PM |
View |
EPC Stormwater Review
4/27/2023 1:41:23 PM |
SWMP Checklist (Barbarick Interim) | 4/27/2023 1:41:23 PM |
View |
EPC Stormwater Review
4/27/2023 1:40:55 PM |
SWMP (Barbarick Interim) | 4/27/2023 1:40:55 PM |
View |
EPC Stormwater Review
4/27/2023 1:40:10 PM |
PBMP (Barbarick Interim) | 4/27/2023 1:40:10 PM |
View |
EPC Stormwater Review
4/27/2023 1:39:39 PM |
GEC Checklist (Barbarick Interim) | 4/27/2023 1:39:39 PM |
View |
EPC Stormwater Review
4/27/2023 1:39:11 PM |
GEC (Barbarick Interim) | 4/27/2023 1:39:11 PM |
View |
EPC Stormwater Review
4/27/2023 1:37:29 PM |
ESQCP (Barbarick Interim) | 4/27/2023 1:37:29 PM |
View |
EPC Stormwater Review
4/27/2023 1:36:41 PM |
SWMP Checklist (Vollmer North) | 4/27/2023 1:36:41 PM |
View |
EPC Stormwater Review
4/27/2023 1:36:10 PM |
SWMP (Vollmer North) | 4/27/2023 1:36:10 PM |
View |
EPC Stormwater Review
4/27/2023 1:35:11 PM |
PBMP (Vollmer North) | 4/27/2023 1:35:11 PM |
View |
EPC Stormwater Review
4/27/2023 1:34:35 PM |
GEC Checklist (Vollmer North) | 4/27/2023 1:34:35 PM |
View |
EPC Stormwater Review
4/27/2023 1:33:28 PM |
GEC (Vollmer North) | 4/27/2023 1:33:28 PM |
View |
EPC Stormwater Review
4/27/2023 1:32:56 PM |
ESQCP (Vollmer North) | 4/27/2023 1:32:56 PM |
View |
EPC Stormwater Review
4/27/2023 1:31:52 PM |
CDs (Vollmer North) | 4/27/2023 1:31:52 PM |
View |
PCD Engineering Division
4/27/2023 2:41:57 PM |
See the attached comment memo (link at left) and checklist for reference. The following items need to be revised and resubmitted for Vollmer North and Barbarick Interim: - CDs - GEC Plans (2) - Documents with Stormwater comments -- Jeff Rice - 719-520-7877 |
4/27/2023 2:41:57 PM |
Colorado Springs Public Works
4/21/2023 8:33:34 AM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
4/21/2023 8:33:34 AM | |
EPC Stormwater Review
4/27/2023 1:21:57 PM |
Review 7: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CDs - Vollmer North.......(uploaded with PCD comments) - SWMP (Vollmer North) - SWMP Checklist (Vollmer North) - PBMP (Vollmer North) - ESQCP (Vollmer North) - GEC Plan (Vollmer North).......(uploaded with PCD comments) - GEC Checklist (Vollmer North) - SWMP (Vollmer Road - Barbarick Interim Condition) - SWMP Checklist (Vollmer Road - Barbarick Interim Condition) - PBMP (Vollmer Road - Barbarick Interim Condition) - ESQCP (Vollmer Road - Barbarick Interim Condition) - GEC Plan (Vollmer Road - Barbarick Interim Condition).......(uploaded with PCD comments) - GEC Checklist (Vollmer Road - Barbarick Interim Condition) EPC DPW Stormwater has reviewed the FAE for Barbarick Interim, but not Barbarick Ult. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
4/27/2023 1:21:57 PM | |
Colorado Springs Public Works
4/6/2023 8:30:04 AM |
Traffic Engineering has no further comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
4/6/2023 8:30:04 AM | |
View |
EPC Stormwater Review
2/6/2023 12:10:22 PM |
SWMP_v6 | 2/6/2023 12:10:22 PM |
View |
PCD Engineering Division
2/6/2023 12:06:16 PM |
(Vollmer Barbarick FAE redlines) | 2/6/2023 12:06:16 PM |
View |
EPC Stormwater Review
2/6/2023 12:06:09 PM |
PBMP_v6 | 2/6/2023 12:06:09 PM |
View |
PCD Engineering Division
2/6/2023 12:05:27 PM |
(Vollmer North FAE redlines) | 2/6/2023 12:05:27 PM |
View |
EPC Stormwater Review
2/6/2023 12:04:58 PM |
CDs_v6 | 2/6/2023 12:04:58 PM |
EPC Stormwater Review
2/6/2023 12:03:33 PM |
Review 6: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CDs - Vollmer North.......(uploaded with PCD comments) - PBMP Applicability Form - SWMP Please submit the following Stormwater documents necessary for construction: - Approved drainage report under Homestead North Filing 1 - GEC Checklist (Vollmer North) - ESQCP (for Homestead North or separate) - SWMP Checklist - GEC Plan (Vollmer Road - Barbarick Interim Condition) - GEC Checklist (Vollmer Road - Barbarick Interim Condition) Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
2/6/2023 12:03:33 PM | |
Colorado Springs Public Works
2/1/2023 10:48:44 AM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
2/1/2023 10:48:44 AM | |
View |
PCD Engineering Division
2/6/2023 12:03:37 PM |
See the attached comment memo (link at left) and checklist for reference. The following items need to be revised and resubmitted for Vollmer North: - CDs/GEC (Vollmer North) - FAE All documents necessary for construction: - PBMP Applicability Form - GEC Checklist - ESQCP (for Homestead North or separate) - SWMP - SWMP Checklist If approvals are desired on the Vollmer-Barbarick Interim CDs, see FAE redlines and comment letter. These can be resubmitted with the appropriate project when construction is necessary. -- Jeff Rice - 719-520-7877 |
2/6/2023 12:03:37 PM |
Colorado Springs Public Works
1/5/2023 8:26:03 AM |
Traffic Engineering has no further comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
1/5/2023 8:26:03 AM | |
EPC Stormwater Review
9/26/2022 1:47:33 PM |
Please submit the following Stormwater documents necessary for construction: - Approved drainage report under Homestead North Filing 1 - PBMP Applicability Form - GEC Checklist - ESQCP (for Homestead North or separate) - SWMP - SWMP Checklist Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
9/26/2022 1:47:33 PM | |
View |
PCD Engineering Division
9/23/2022 1:05:44 PM |
(Vollmer-Barbarick Interim CDs redlines) | 9/23/2022 1:05:44 PM |
View |
PCD Engineering Division
9/23/2022 1:04:51 PM |
(Vollmer-Barbarick Ultimate CDs redlines) | 9/23/2022 1:04:51 PM |
View |
PCD Engineering Division
9/23/2022 1:04:02 PM |
(Vollmer-Barbarick FAE redlines) | 9/23/2022 1:04:02 PM |
View |
PCD Engineering Division
9/23/2022 1:03:28 PM |
(Vollmer North FAE redlines) (question on note) | 9/23/2022 1:03:28 PM |
View |
PCD Engineering Division
9/23/2022 1:02:48 PM |
(Utility CDs redlines summary) | 9/23/2022 1:02:48 PM |
View |
PCD Engineering Division
9/23/2022 1:02:18 PM |
(Utility CDs redlines) | 9/23/2022 1:02:18 PM |
View |
PCD Engineering Division
9/23/2022 1:01:03 PM |
(Vollmer North CDs redlines summary) | 9/23/2022 1:01:03 PM |
View |
PCD Engineering Division
9/23/2022 1:00:20 PM |
(Vollmer North CDs redlines) | 9/23/2022 1:00:20 PM |
View |
PCD Engineering Division
9/23/2022 12:57:50 PM |
See the attached comment memo (link at left) and checklist for reference. The following items need to be revised and resubmitted for Vollmer North: - CDs (Vollmer North) - CDs (Utility) All documents necessary for construction: - Approved drainage report under Homestead North Filing 1 - Approved traffic study under Homestead North - PBMP Applicability Form - GEC Checklist - ESQCP (for Homestead North or separate) - SWMP - SWMP Checklist If approvals are desired on the Vollmer-Barbarick CDs, see redlines and comment letter. These can be resubmitted with the appropriate project when construction is necessary. -- Jeff Rice - 719-520-7877 |
9/23/2022 12:57:50 PM |
PCD Project Manager
9/22/2022 10:55:08 AM |
Please see engineering comments | 9/22/2022 10:55:08 AM | |
Colorado Springs Public Works
9/14/2022 9:52:11 AM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
9/14/2022 9:52:11 AM | |
Upper Black Squirrel Creek GWMD
9/6/2022 2:39:51 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. | 9/6/2022 2:39:51 PM | |
Mountain View Electric Association, Inc.
9/6/2022 9:09:59 AM |
See comment letter dated October 7, 2021. No additional comments at this time. | 9/6/2022 9:09:59 AM | |
Colorado Springs Public Works
9/1/2022 9:00:26 AM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
9/1/2022 9:00:26 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
8/31/2022 4:15:02 PM |
If the engineer of record or the contractor believes or sees that development will interfere with the infrastructure of Springs Utilities, we must be notified immediately. Corey Masoumi - Cmasoumi@csu.org |
8/31/2022 4:15:02 PM | |
EPC Stormwater Review
7/8/2022 9:45:43 AM |
Stormwater review completed by PCD Engineer for this submittal, revise documents per their comments. Stormwater review will be provided with the complete submittal, whether in this CDR project or with Homestead North Filing No. 1. Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
7/8/2022 9:45:43 AM | |
Colorado Springs Public Works
6/30/2022 8:09:45 AM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
6/30/2022 8:09:45 AM | |
View |
PCD Engineering Division
6/23/2022 4:54:22 PM |
(FAE redlines) | 6/23/2022 4:54:22 PM |
View |
PCD Engineering Division
6/23/2022 4:53:52 PM |
(GEC redlines summary) | 6/23/2022 4:53:52 PM |
View |
PCD Engineering Division
6/23/2022 4:53:28 PM |
(GEC redlines) | 6/23/2022 4:53:28 PM |
View |
PCD Engineering Division
6/23/2022 4:52:45 PM |
(CDs redlines - Utilities) | 6/23/2022 4:52:45 PM |
View |
PCD Engineering Division
6/23/2022 4:52:23 PM |
(CDs redlines - Barbarick Ultimate) | 6/23/2022 4:52:23 PM |
View |
PCD Engineering Division
6/23/2022 4:51:47 PM |
(CDs redlines - Barbarick Interim) | 6/23/2022 4:51:47 PM |
View |
PCD Engineering Division
6/23/2022 4:51:07 PM |
(CD redlines summary - Vollmer North) | 6/23/2022 4:51:07 PM |
View |
PCD Engineering Division
6/23/2022 4:50:37 PM |
(CD redlines - Vollmer North) | 6/23/2022 4:50:37 PM |
View |
PCD Engineering Division
6/23/2022 4:49:54 PM |
See the attached comment memo (link at left) and checklist for reference. The following items need to be revised and resubmitted: - CDs (Vollmer North) - GEC plans - FAE When available: - All documents necessary for construction (see comment memo). -- Jeff Rice - 719-520-7877 |
6/23/2022 4:49:54 PM |
Colorado Springs Public Works
6/16/2022 12:16:03 PM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
6/16/2022 12:16:03 PM | |
View |
EPC Stormwater Review
4/18/2022 1:48:58 PM |
EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - GEC Plan Please submit all ESQCP/Stormwater documents for review. Please note, comments are cursory and will be reviewed in detail in conjunction with all required Stormwater documents. Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
4/18/2022 1:48:58 PM |
View |
PCD Engineering Division
4/11/2022 2:07:55 PM |
(Vollmer North FAE redlines) | 4/11/2022 2:07:55 PM |
View |
PCD Engineering Division
4/11/2022 2:07:24 PM |
(Vollmer North GEC redlines summary) | 4/11/2022 2:07:24 PM |
View |
PCD Engineering Division
4/11/2022 2:06:50 PM |
(Vollmer North GEC redlines) | 4/11/2022 2:06:50 PM |
View |
PCD Engineering Division
4/11/2022 2:05:31 PM |
(Vollmer North Ultimate CDs redlines summary) | 4/11/2022 2:05:31 PM |
View |
PCD Engineering Division
4/11/2022 2:05:01 PM |
(Vollmer North Ultimate CDs redlines) | 4/11/2022 2:05:01 PM |
View |
PCD Engineering Division
4/11/2022 2:04:12 PM |
(Barbarick Ultimate CDs redlines summary) | 4/11/2022 2:04:12 PM |
View |
PCD Engineering Division
4/11/2022 2:03:24 PM |
(Barbarick Ultimate CDs redlines) | 4/11/2022 2:03:24 PM |
View |
PCD Engineering Division
4/11/2022 2:02:39 PM |
(Barbarick Interim CDs redlines summary) | 4/11/2022 2:02:39 PM |
View |
PCD Engineering Division
4/11/2022 2:02:12 PM |
(Barbarick Interim CDs redlines) | 4/11/2022 2:02:12 PM |
View |
PCD Engineering Division
4/11/2022 2:01:20 PM |
See the attached comment memo (link at left) and checklist for reference. The following items need to be revised and resubmitted: - CDs - GEC plans - FAE When available: - Any easements necessary for construction. - All documents necessary for construction. -- Jeff Rice - 719-520-7877 |
4/11/2022 2:01:20 PM |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/14/2022 3:46:26 PM |
Please disregard this action item if you have already talked to CSU regarding this matter. Please call 719-668-7662 and speak with the CSU field engineer about the CSU gas requirement for this project. Existing CSU high-pressure gas lines in the area that must be discussed with CSU gas field engineering & CSU gas planning & design, and update me. ____________________________________________________ Corey Masoumi | Engineering Support Coordinator Utilities Development Services | Colorado Springs Utilities 1521 S Hancock Expy Colorado Springs, CO 80903 O: 719-668-1856 | Main: 719-668-8259 cmasoumi@csu.org | www.csu.org |
3/14/2022 3:46:26 PM | |
PCD Project Manager
12/29/2021 9:27:27 AM |
See engineering comments | 12/29/2021 9:27:27 AM | |
View |
PCD Engineering Division
12/28/2021 1:15:32 PM |
(Vollmer North GEC redlines) | 12/28/2021 1:15:32 PM |
View |
PCD Engineering Division
12/28/2021 1:14:54 PM |
(Vollmer North CDs redlines) | 12/28/2021 1:14:54 PM |
View |
PCD Engineering Division
12/28/2021 1:14:24 PM |
(Vollmer Barbarick-ultimate redlines) | 12/28/2021 1:14:24 PM |
View |
PCD Engineering Division
12/28/2021 1:14:00 PM |
(Vollmer Barbarick-MS redlines) | 12/28/2021 1:14:00 PM |
View |
PCD Engineering Division
12/28/2021 1:13:37 PM |
(Vollmer Barbarick-interim redlines) | 12/28/2021 1:13:37 PM |
View |
PCD Engineering Division
12/28/2021 1:12:46 PM |
See the attached comment memo (link at left) and checklist for reference. The following items need to be revised and resubmitted: - CDs - GEC plans When available: - FAE - Any easements necessary for construction. -- Jeff Rice - 719-520-7877 |
12/28/2021 1:12:46 PM |
EPC Stormwater Review
12/22/2021 4:41:48 PM |
Stormwater has no comments at this time. | 12/22/2021 4:41:48 PM | |
Colorado Springs Public Works
12/22/2021 12:20:31 PM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
12/22/2021 12:20:31 PM | |
Upper Black Squirrel Creek GWMD
12/21/2021 2:49:45 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. | 12/21/2021 2:49:45 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
12/17/2021 3:35:23 PM |
Please call 719-668-7662 and speak with the CSU field engineer about the CSU gas requirement for this project. Existing CSU high-pressure gas lines in the area that must be discussed with CSU gas field engineering & CSU gas planning & design, and update me. ____________________________________________________ Corey Masoumi | Engineering Support Coordinator Utilities Development Services | Colorado Springs Utilities 1521 S Hancock Expy Colorado Springs, CO 80903 O: 719-668-1856 | Main: 719-668-8259 cmasoumi@csu.org | www.csu.org |
12/17/2021 3:35:23 PM | |
Colorado Springs Public Works
12/9/2021 7:07:15 AM |
Traffic Engineering has no further comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/ Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
12/9/2021 7:07:15 AM | |
Mountain View Electric Association, Inc.
11/29/2021 12:16:54 PM |
See comment letter dated October 7, 2021. No additional comments at this time. | 11/29/2021 12:16:54 PM | |
View |
PCD Engineering Division
10/19/2021 5:48:52 PM |
(Vollmer Barbarick Interim CD redlines) | 10/19/2021 5:48:52 PM |
View |
PCD Engineering Division
10/19/2021 5:48:21 PM |
(Vollmer Barbarick Ultimate CD redlines) | 10/19/2021 5:48:21 PM |
View |
PCD Engineering Division
10/19/2021 5:47:47 PM |
(Vollmer Barbarick-BGP CD redlines) | 10/19/2021 5:47:47 PM |
View |
PCD Engineering Division
10/19/2021 5:47:12 PM |
(Vollmer North CD redlines) | 10/19/2021 5:47:12 PM |
View |
PCD Engineering Division
10/19/2021 5:46:31 PM |
See the attached comment memo (link at left) and checklist for reference. The following items need to be revised and resubmitted: - CDs (4) - GEC (discuss with Staff) Submit later: Any easements necessary for construction. -- Jeff Rice - 719-520-7877 |
10/19/2021 5:46:31 PM |
EPC Stormwater Review
10/18/2021 10:23:16 AM |
EPC Stormwater has no comments at this time. When the applicant is ready to submit for construction review, required documents should be revised to include the proposed work on Vollmer Road. In addition, the proposed expansion of Vollmer Road will need to account for water quality. Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
10/18/2021 10:23:16 AM | |
Colorado Springs Public Works
10/8/2021 1:32:22 PM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
10/8/2021 1:32:22 PM | |
View |
Mountain View Electric Association, Inc.
10/7/2021 2:16:24 PM |
10/7/2021 2:16:24 PM | |
Upper Black Squirrel Creek GWMD
10/6/2021 3:44:13 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on any future submittals. | 10/6/2021 3:44:13 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/30/2021 9:23:30 AM |
CSU does not usually review EPC "CDR" projects. Was there a specific reason it was sent to us? BML | 9/30/2021 9:23:30 AM | |
Colorado Springs Public Works
9/28/2021 11:15:29 AM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
9/28/2021 11:15:29 AM |