Project Name
Aura at Crossroads
Description
300 unit multi-family single lot, detention tract, private road tract, sign tract, and future development tract
Location
Parcels
5408007005 5408007005
Applicant
Kimley-Horn
Jim Houk ( jhouk@ttplan.net )
(719) 284-7830
Jim Houk ( jhouk@ttplan.net )
(719) 284-7830
EA Number
EA2055
File Number
PPR2141
Project Manager
Ryan Howser
Status
Active
Created
7/1/2021 11:13:04 AM

View: Project Documents



Review Comments (33)

Link Agency Comment
PCD Project Manager
12/1/2021 11:10:38 AM
Please note that additional comments from EPC Stormwater may be forthcoming. 12/1/2021 11:10:38 AM
View PCD Project Manager
12/1/2021 11:09:50 AM
PCD Engineering comments - grading & erosion control plan 12/1/2021 11:09:50 AM
View PCD Project Manager
12/1/2021 11:06:14 AM
PCD Engineering comments - construction drawings 12/1/2021 11:06:14 AM
View PCD Project Manager
12/1/2021 11:06:30 AM
PCD Engineering comments - drainage report 12/1/2021 11:06:30 AM
View PCD Project Manager
12/1/2021 10:58:45 AM
Minor comments on the site development plan attached 12/1/2021 10:58:45 AM
View PCD Project Manager
12/1/2021 10:58:26 AM
Minor comments on letter of intent attached 12/1/2021 10:58:26 AM
PCD Project Manager
12/1/2021 10:10:11 AM
Planning Division has no further comments on the lighting plan. However, Project Manager is requesting a resubmittal of the lighting plan without the redline comment copy appended. Just the revised plan set will suffice. Thank you! 12/1/2021 10:10:11 AM
View Cherokee Metro Dist
11/30/2021 9:37:45 AM
Sheet 3 of 29 Overall Utility Plan - See attached comments

Sheet 23 of 29 - Provide area of ground cover types (sod, mulch, etc.)
11/30/2021 9:37:45 AM
PCD Engineering Division
11/30/2021 1:58:08 PM
Review 2 comments will be uploaded by the project manager. Please address comments on the following documents:

-Drainage report
-Construction drawings
-GEC plans

Comments have been resolved on the following documents:
-FAE
-Site development plans

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
11/30/2021 1:58:08 PM
Pikes Peak Regional Building Department
11/24/2021 8:21:56 AM
1. El Paso/Teller E911 has approved the two street names, Crossbuck Point and Highball View. Please add the streets to the Development Plan.
2. Once the Secondary addressing on the floor plans for both building types are finalized . Please send to Becky Allen, prior to plan submittal for review. Beckya@pprbd.org. Link to guide https://www.pprbd.org/File/Resources/Downloads/Addressing/SECONDARY_ADDRESS_REQUEST_FORM.pdf
3. Clarification was received, the name of the subdivision is Aura at Crossroads.

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
11/24/2021 8:21:56 AM
911 Authority - El Paso/Teller County
11/17/2021 8:50:18 AM
Streetnames have been reserved for this development, but are not depicted on the plan drawings.
Final approval reserved until streetname layout is submitted.
Thank you.
Justin
11/17/2021 8:50:18 AM
View PCD Project Manager
10/12/2021 5:00:15 PM
PCD Engineering - traffic memo comments 10/12/2021 5:00:15 PM
View PCD Project Manager
10/12/2021 4:59:54 PM
PCD Planning and PCD Engineering - site development plan comments 10/12/2021 4:59:54 PM
View PCD Project Manager
10/12/2021 4:59:29 PM
PCD Planning - lighting plan comments 10/12/2021 4:59:29 PM
View PCD Project Manager
10/12/2021 4:59:10 PM
PCD Planning - letter of intent comments 10/12/2021 4:59:10 PM
View PCD Project Manager
10/12/2021 4:58:54 PM
PCD Planning - landscape plan comments 10/12/2021 4:58:54 PM
View PCD Project Manager
10/12/2021 4:56:58 PM
PCD Engineering and EPC Stormwater - grading and erosion control plan comments 10/12/2021 4:56:58 PM
View PCD Project Manager
10/12/2021 4:56:22 PM
PCD Engineering and EPC Stormwater - financial assurance form comments 10/12/2021 4:56:22 PM
View PCD Project Manager
10/12/2021 4:56:02 PM
PCD Engineering - drainage report comments 10/12/2021 4:56:02 PM
View PCD Project Manager
10/12/2021 4:55:37 PM
PCD Planning - application comment 10/12/2021 4:55:37 PM
PCD Engineering Division
10/11/2021 4:50:12 PM
Project manager will upload comments. Please address comments in the following documents:

-Drainage report
-Site development plan
-Grading and Erosion Control plan
-Traffic memo
-Financial Assurance Estimate

Please note: due to the concurrent application, SF-2129, comments are precursory.

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
10/11/2021 4:50:12 PM
View EPC Stormwater Review
10/6/2021 12:55:35 PM
SWMP Checklist_v1 10/6/2021 12:55:35 PM
View EPC Stormwater Review
10/6/2021 12:55:02 PM
SWMP_v1 10/6/2021 12:55:02 PM
View EPC Stormwater Review
10/6/2021 12:54:12 PM
GEC Checklist_v1 10/6/2021 12:54:12 PM
EPC Stormwater Review
10/6/2021 12:50:48 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- FAE.......................(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP
- SWMP Checklist

Please provide the following documents upon resubmittal:
- ESQCP

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
10/6/2021 12:50:48 PM
Cherokee Metro Dist
10/4/2021 5:04:28 PM
Review is preliminary only. Final Plan on water and wastewater utilities is required before final approval.
Information still needed includes:
Water main details, crossings, material, valve locations. Exterior meters are not allowed except for landscape service - meters to located inside mechanical room per Cherokee standards.
Sanitary sewer plan and profile sheets, details, notes.
10/4/2021 5:04:28 PM
Pikes Peak Regional Building Department
10/4/2021 3:04:25 PM
1. Due to the large number of carports and buildings, at least two internal streets will be needed. Provide a list of proposed street names to Justin Annan jannan@elpasoteller911.org, and Glenn West gwest@elpasoteller911.org with El Paso/Teller County 911 Authority. An email from E-911 approving street names is required for Enumeration approval. Email Becky Allen when street names are approved. Beckya@pprbd.org.
2. Trash enclosure is over 7’ in height and will also require a separate address and permit.
3. Secondary addressing on the floor plans for both building types is missing. Please refer to our Secondary Addressing guidelines when submitting the plans for RBD review. Please send to Becky Allen, prior to plan submittal for review. Beckya@pprbd.org. Link to guide https://www.pprbd.org/File/Resources/Downloads/Addressing/SECONDARY_ADDRESS_REQUEST_FORM.pdf
4. Per Colorado Springs Utilities, there is an address for an illuminated sign, 7315 E Hwy 24 is an old address and is not currently active.
5. When submitting the plans for RBD/Enumerations review, we will need each secondary structure location highlighted/clouded. Be sure to label each building with assigned address.
6. What is the exact use of the Amenities building, building 10 (dog wash?)
7. What is the rectangular structure/area south of the Clubhouse building? If it is a building or structure, a separate address and permit will be needed. Please clarify.
8. Clarify the name of the subdivision, plan title on EDARP shows Crossroads at Meadowbrook and the Site Development Plan shows Aura at Crossroads.


Development Plan Standard Comments:

1. For assignment of addressing for lots and tracts, place addressing marker (xxx) where they are intended to be utilized. Addressing marker for lots should be front door.
2. Provide a 100 scale copy or larger of the entire APPROVED development plan (d.p.) to this department so that addressing can be assigned. Once received, the development plan will be placed on a list to be addressed. Development plans that are not yet approved may be addressed, however additional plan review fees will accrue if changes are made to the D.P. after initial addressing.
3. If underground service is needed prior to plat, submit a Utilities Addressing Plan (UAP), to Colorado Springs Utilities via the related link at https://www.csu.org/Pages/mapping.aspx For more information contact: Karen Carlton KCARLTON@CSU.ORG

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
10/4/2021 3:04:25 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/29/2021 8:46:42 AM
For gas and electric designs for your project you will need to reach out to CSU gas and electric Field Engineering. Please give Ginny Halvorson a call at 719-668-5567 for gas and Aaron Cassio a call at 668-5573 for Joint Trench, and if you have any further questions you can reach out to me at 719-668-8769 thanks Al 9/29/2021 8:46:42 AM
View EPC Environmental Services
9/20/2021 2:21:59 PM
9/20/2021 2:21:59 PM
View Parks Advisory Board
9/17/2021 11:28:32 AM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (Administrative Comments Only - No PAB Endorsement Necessary) 9/17/2021 11:28:32 AM
View EPC Parks Department
9/17/2021 11:25:51 AM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (Administrative Comments Only - No PAB Endorsement Necessary) 9/17/2021 11:25:51 AM
911 Authority - El Paso/Teller County
9/15/2021 8:21:29 AM
No new street names requested on this submittal.
No action for E911.
Thank you.
Justin.
9/15/2021 8:21:29 AM
Cimarron Hills Fire
9/13/2021 11:52:01 AM
CHFD has reviewed the plot plan for this project. We have had several planning meetings regarding the access and overall site plans. These are approved. JT McLeod, Division Chief-Fire Inspector III. 9/13/2021 11:52:01 AM