Project Review Comments
- Project Name
- Peaceful Ridge CDR and SIA Amendment to SF05044
- Description
- Ref SF05044 - application to update construction drawings and SIA to meet current standards. EDARP will not allow SIA to be added to SF file so it is in CDR file.
- Location
- Parcels
- 5515400002 5515400002
- Applicant
-
Widefield Investment Group
Ryan Watson ( ryan@widefieldinvestmentgroup.com )
(719) 392-0194 Ryan Watson ( ryan@widefieldinvestmentgroup.com )
(719) 392-0194 - File Number
- CDR2215
- Project Manager
- Ryan Howser
- Status
- Closed
- Created
- 5/25/2021 9:52:49 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
County Attorney - Development Review
3/21/2024 5:18:48 PM |
Signature provided to County Project Manager. | 3/21/2024 5:18:48 PM | |
View |
County Attorney - Development Review
2/20/2024 9:42:18 AM |
Made a couple of additional changes to the SIA based on the determination that the lots will need to be identified by address in Exhibits D and E. | 2/20/2024 9:42:18 AM |
View |
County Attorney - Development Review
1/18/2024 4:01:42 PM |
Proposed amended SIA attached. | 1/18/2024 4:01:42 PM |
PCD Engineering Division
11/13/2023 8:17:34 AM |
Comments have been resolved. The project manager will upload any approved documents. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
11/13/2023 8:17:34 AM | |
EPC Stormwater Review
10/25/2023 4:42:18 PM |
All EPC Stormwater comments have been addressed. Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
10/25/2023 4:42:18 PM | |
PCD Engineering Division
10/25/2023 7:58:04 AM |
Comments have been resolved. The project manager will upload any approved documents. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
10/25/2023 7:58:04 AM | |
View |
PCD Engineering Division
10/18/2023 8:59:34 AM |
Construction Drawings Redlines | 10/18/2023 8:59:34 AM |
PCD Engineering Division
10/18/2023 8:25:57 AM |
Review 4 comments are attached for the following document: -CDs: sidewalk grade comments have not been addressed. Note to planner: set review cycle to 7 days. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
10/18/2023 8:25:57 AM | |
EPC Stormwater Review
10/18/2023 7:54:58 AM |
Review 4: EPC Stormwater reviewed the following documents submitted to EPC on 10.17.23 via email. Please address EPC Stormwater comments from Review 3: - Construction Drawings Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
10/18/2023 7:54:58 AM | |
View |
PCD Engineering Division
8/24/2023 10:17:52 PM |
Deviation Request comments | 8/24/2023 10:17:52 PM |
View |
PCD Engineering Division
8/24/2023 10:15:11 PM |
CD's comments | 8/24/2023 10:15:11 PM |
PCD Engineering Division
8/24/2023 10:07:59 PM |
Review 3 comment on the following documents will be uploaded: -CD's -Deviation Request Ryan: a 7-day turnaround is sufficient for the re-review. reviewed by: Carlos Hernandez & Daniel Torres carloshernandez@elpasoco.com & danieltorres@elpasoco.com |
8/24/2023 10:07:59 PM | |
PCD Project Manager
8/24/2023 5:12:58 PM |
Planning Division has no comments at this time. | 8/24/2023 5:12:58 PM | |
View |
County Attorney - Development Review
8/24/2023 2:09:39 PM |
Signature to Detention Maintenance Agreement attached. | 8/24/2023 2:09:39 PM |
View |
County Attorney - Development Review
8/24/2023 2:09:06 PM |
Please make sure name of bank issuing letter of credit is filled out in paragraph 1 of SIA. Signature attached. | 8/24/2023 2:09:06 PM |
EPC Stormwater Review
8/22/2023 12:30:55 PM |
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following documents (to be uploaded by the Planner): - Construction Drawings Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
8/22/2023 12:30:55 PM | |
View |
PCD Engineering Division
6/8/2023 4:54:38 PM |
GEC Plan | 6/8/2023 4:54:38 PM |
View |
PCD Engineering Division
6/8/2023 4:51:34 PM |
FAE | 6/8/2023 4:51:34 PM |
View |
PCD Engineering Division
6/8/2023 4:51:17 PM |
Construction Drawings | 6/8/2023 4:51:17 PM |
View |
PCD Engineering Division
6/8/2023 4:50:07 PM |
Drainage Report | 6/8/2023 4:50:07 PM |
PCD Engineering Division
6/8/2023 4:54:54 PM |
Comments were resolved for the following documents: -TIS Comments for the following documents are attached: -Drainage report -CDs: staff is waiting for correspondence about inner radius for knuckles. -FAE -GEC Plan Reviewed By: Lupe Packman lupepackman@elpasoco.com |
6/8/2023 4:54:54 PM | |
PCD Project Manager
6/7/2023 1:23:18 PM |
Please either update the signature block on the detention maintenance agreement (DMA) to replace Kevin Mastin with Meggan Herington, or update both agreements' signature blocks to replace PCD Director with BoCC signature blocks. Please also provide justification for the administrative approval of these agreements. I believe these will require BoCC approval. | 6/7/2023 1:23:18 PM | |
EPC Stormwater Review
6/6/2023 7:50:39 PM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following documents (uploaded by the Planner): - CDs - FAE - Drainage Report Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
6/6/2023 7:50:39 PM | |
County Attorney - Development Review
6/2/2023 5:13:07 PM |
No further comments. | 6/2/2023 5:13:07 PM | |
View |
County Attorney - Development Review
11/7/2022 11:17:30 AM |
Proposed edits to SIA attached. | 11/7/2022 11:17:30 AM |
Colorado Springs Public Works
10/19/2022 3:54:12 PM |
Engineering Development Review will require all public improvements to be built to full City Standards if this is chosen for pre-annexation per the IGA. Joel Dagnillo, P.E. Engineer III Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
10/19/2022 3:54:12 PM | |
PCD Project Manager
10/12/2022 4:18:48 PM |
Planning Division has no comments at this time. Please note that comments from the County Attorney's Office may be forthcoming. | 10/12/2022 4:18:48 PM | |
Colorado Springs Public Works
10/6/2022 1:52:19 PM |
Traffic Engineering will require all public improvements to be built to full City Standards if the El-Paso county section of Marksheffel Road is chosen for pre-annexation. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
10/6/2022 1:52:19 PM | |
View |
EPC Stormwater Review
10/5/2022 4:50:59 PM |
Traffic Impact Study_v1 | 10/5/2022 4:50:59 PM |
View |
EPC Stormwater Review
10/5/2022 4:49:43 PM |
GEC Checklist_v1 | 10/5/2022 4:49:43 PM |
View |
EPC Stormwater Review
10/5/2022 4:47:20 PM |
Drainage Report_v1 | 10/5/2022 4:47:20 PM |
View |
EPC Stormwater Review
10/5/2022 4:45:01 PM |
GEC_v1 | 10/5/2022 4:45:01 PM |
View |
EPC Stormwater Review
10/5/2022 4:42:48 PM |
FAE_v1 | 10/5/2022 4:42:48 PM |
View |
EPC Stormwater Review
10/5/2022 4:41:55 PM |
CDs_v1 | 10/5/2022 4:41:55 PM |
EPC Stormwater Review
10/5/2022 4:40:33 PM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CDs........................(uploaded with PCD comments) - FAE........................(uploaded with PCD comments) - GEC Plan...............(uploaded with PCD comments) - Drainage Report.....(uploaded with PCD comments) - GEC Checklist Submit the following approved documents from EGP-21-003: - PBMP Applicability Form - ESQCP Due to the volume or complexity of the comments provided, these comments are cursory in nature and EPC Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review. Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
10/5/2022 4:40:33 PM | |
PCD Engineering Division
10/3/2022 12:54:01 PM |
Review 1 comments will be uploaded by the EPC Stormwater staff for the following documents: -Drainage report -Traffic study -GEC plan -FAE -Construction drawings -SIA: update letter of credit amount described in SIA to match FAE. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
10/3/2022 12:54:01 PM | |
Mountain View Electric Association, Inc.
9/26/2022 3:55:39 PM |
The Association has existing facilities near and within this parcel of land. If there is any damage, removal or relocation of facilities it will be at the expense of the applicant. | 9/26/2022 3:55:39 PM |