View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Administrative Notice
11/18/2021 3:38:22 PM |
Adjacent property notifications have been mailed indicating the anticipated decision date and how to provide comment. | 11/18/2021 3:38:22 PM | |
Pikes Peak Regional Building Department
11/16/2021 2:45:22 PM |
1. Enumerations has no issue with using the address of 35 Wuthering Heights Drive for the newly realigned lot/lots as long as the driveway access is from Wuthering Heights Drive. 2. No further comments. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
11/16/2021 2:45:22 PM | |
PCD Project Manager
11/16/2021 8:12:47 AM |
Prepping project for approval. Mailout being prepped. | 11/16/2021 8:12:47 AM | |
View |
PCD Project Manager
11/15/2021 9:36:09 AM |
Vacation drawing_v3 | 11/15/2021 9:36:09 AM |
View |
PCD Project Manager
9/9/2021 5:06:46 PM |
Vacation drawing_v2 redlines | 9/9/2021 5:06:46 PM |
PCD Engineering Division
9/9/2021 9:48:06 AM |
There are no further comments relating to drainage or transportation. The project manager will upload any approved documents. Please note: a condition will be required for approval. Only one access point will be allowed to this lot. The applicant will be allowed to choose which road the access will be on, but there shall only be one access. One of the access permits will become voided. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
9/9/2021 9:48:06 AM | |
View |
PCD Project Manager
7/22/2021 4:55:37 PM |
Letter of Intent_v1redlines | 7/22/2021 4:55:37 PM |
View |
PCD Project Manager
7/22/2021 4:55:24 PM |
Vacation drawing_v1redlines | 7/22/2021 4:55:24 PM |
View |
PCD Project Manager
7/22/2021 4:55:10 PM |
Adjacent Property Owner Notification_v1redlines | 7/22/2021 4:55:10 PM |
PCD Engineering Division
7/22/2021 2:51:52 PM |
Review1 comments will be uploaded by the project engineer. Please address comments on the following documents: -Vacation plan -Letter of intent Please note: a condition will be required for approval. Only one access point will be allowed to this lot. The applicant will be allowed to choose which road the access will be on, but there shall only be one access. One of the access permits will become voided. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
7/22/2021 2:51:52 PM | |
Colorado Springs Public Works
7/21/2021 10:27:53 AM |
Engineering Development Review Division has no comments. Patrick V. Morris Civil Engineer II Public Works/Engineering Development Review City of Colorado Springs Phone: 719-385-5075 Patrick.morris@coloradosprings.gov |
7/21/2021 10:27:53 AM | |
Mountain View Electric Association, Inc.
7/21/2021 2:15:09 PM |
Mountain View Electric Association has no objections to the lot line vacation as well as the vacation of the easement adjacent to the lot line. | 7/21/2021 2:15:09 PM | |
County Attorney - Development Review
7/15/2021 11:35:28 AM |
No comments from County Attorney - Development Review at this time. | 7/15/2021 11:35:28 AM | |
Colorado Springs Public Works
7/15/2021 7:43:55 AM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
7/15/2021 7:43:55 AM | |
Monument
7/12/2021 8:26:22 AM |
Town of Monument has no comments. Thank you for the opportunity to review the plans. | 7/12/2021 8:26:22 AM | |
Academy SD 20 Building Fund
7/12/2021 7:01:02 AM |
Academy District 20 is in receipt of File #V212 for the vacation to the lot line between 35 Wuthering Height and 5 Rangely Drive. The District is requesting fees versus land dedication per the existing El Paso County Code if any additional residential units are constructed on this parcel. No other comments. Please contact me if you need additional information. Don Smith Planning Consultant |
7/12/2021 7:01:02 AM |