Project Review Comments

Back to List


Project Name
Smith Plumbing, Heating & Cooling Site Development Plan
Description
Site Development Plan - Variance of use approved to allow contractor's equipment yard in CC district
Location
Parcels
6501312002 6501312002
Applicant
Hammers Construction
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
EA Number
EA2173
File Number
PPR2143
Project Manager
Kylie Bagley
Status
Closed
Created
5/5/2021 7:48:37 AM

View: Project Documents



Review Comments (41)

Link Agency Comment
View County Attorney - Development Review
7/14/2022 10:15:13 AM
Signature to Detention Maintenance Agreement attached. 7/14/2022 10:15:13 AM
View County Attorney - Development Review
6/28/2022 4:03:28 PM
Edits to Detention Maintenance Agreement attached. 6/28/2022 4:03:28 PM
PCD Project Manager
6/27/2022 1:37:33 PM
Planning has no further comments 6/27/2022 1:37:33 PM
PCD Engineering Division
6/27/2022 12:45:05 PM
Review #5: Comment Resolved.
The approved engineering documents will be uploaded by the Project Manager.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
6/27/2022 12:45:05 PM
PCD Project Manager
5/20/2022 3:38:56 PM
Planning has no additional comments. 5/20/2022 3:38:56 PM
EPC Stormwater Review
5/17/2022 3:50:53 PM
Review 4: EPC Stormwater comments have been resolved on the following documents:
- Drainage Report
- SDI Worksheet

EPC Stormwater has no further comments at this time. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
5/17/2022 3:50:53 PM
PCD Engineering Division
5/18/2022 9:36:49 AM
Review #4: Upload a signed version (pdf) of the pond maintenance agreement.
The approved engineering documents will be uploaded by the Project Manager.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
5/18/2022 9:36:49 AM
View EPC Stormwater Review
3/8/2022 9:38:35 AM
SDI Worksheet 3/8/2022 9:38:35 AM
EPC Stormwater Review
3/8/2022 9:38:50 AM
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report....(to be uploaded by PM with PCD comments)
- SDI Worksheet

EPC Stormwater comments have been resolved on the following documents:
- GEC Plan
- PBMP Applicability Form

Please sign, date, and resubmit the following docs:
- GEC Checklist
- SWMP Checklist

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
3/8/2022 9:38:50 AM
View PCD Project Manager
3/10/2022 9:22:11 AM
Drainage Report Redlines 3/10/2022 9:22:11 AM
PCD Project Manager
3/3/2022 4:31:04 PM
Planning has no additional comments. 3/3/2022 4:31:04 PM
PCD Engineering Division
3/8/2022 2:58:28 PM
Review #3: Engineering documents will be processed for final signature approval once Stormwater Team comments are resolved.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
3/8/2022 2:58:28 PM
View PCD Project Manager
1/31/2022 4:17:22 PM
Grading & Erosion Control Plan Redlines 1/31/2022 4:17:22 PM
View PCD Project Manager
1/31/2022 4:16:52 PM
Financial Assurance Forms Redlines 1/31/2022 4:16:52 PM
View PCD Project Manager
1/31/2022 4:16:28 PM
Drainage Report Redlines 1/31/2022 4:16:28 PM
View PCD Project Manager
1/31/2022 4:16:03 PM
PBMP revision responses 1/31/2022 4:16:03 PM
PCD Project Manager
1/31/2022 4:10:45 PM
Planning has no additional comments 1/31/2022 4:10:45 PM
View EPC Stormwater Review
1/27/2022 4:57:35 PM
PBMP Applicability Form 1/27/2022 4:57:35 PM
PCD Engineering Division
1/19/2022 11:20:37 AM
Review #2
Minor comment remains. Submit signed/stamped engineering documents for final approval once all of Stormwater Teams' comments are resolved.

A. Redline comments on the following documents will be uploaded by the project manager:
* Drainage Report

B. [UNRESOLVED] Submit the following documents:
- Pond Operations and Maintenance Manual
- SDI Worksheet (required since the WQ only facility is an EDB)
- MS4 Post Construction Form

C. Comments resolved on the following document:
- Grading and Erosion Control Plan
- Financial Assurance Estimate Form

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
1/19/2022 11:20:37 AM
EPC Stormwater Review
1/25/2022 10:04:10 PM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report....(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- PBMP Applicability Form

Please provide the following documents upon resubmittal for the water quality pond (these were also requested with Review 1, but were not uploaded for submittal 2):
- O&M Manual
- MS4 Post Construction Form
- SDI

EPC Stormwater comments have been resolved on the following documents:
- ESQCP (sign, date, and resubmit)
- GEC Checklist (sign, date, and resubmit)
- Private Detention Basin / Stormwater Quality BMP Maintenance Agreement
- SWMP
- SWMP Checklist (sign, date, and resubmit)

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
1/25/2022 10:04:10 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/5/2022 2:33:57 PM
All the comments have been addressed. Approval can be recommended.
_________________________________________
Corey Masoumi | Engineering Support Coordinator
Utilities Development Services | Colorado Springs Utilities
1521 S Hancock Expy Colorado Springs, CO 80903
O: 719-668-1856 | Main: 719-668-8259
cmasoumi@csu.org | www.csu.org
1/5/2022 2:33:57 PM
View PCD Project Manager
10/12/2021 1:20:15 PM
PCD Planning - site development plan comments 10/12/2021 1:20:15 PM
View PCD Project Manager
10/12/2021 1:19:58 PM
PCD Planning - lighting plan comments 10/12/2021 1:19:58 PM
View PCD Project Manager
10/12/2021 1:19:41 PM
PCD Planning - letter of intent comments 10/12/2021 1:19:41 PM
View PCD Project Manager
10/12/2021 1:19:23 PM
PCD Planning - landscape plan comments 10/12/2021 1:19:23 PM
View PCD Project Manager
10/12/2021 1:19:05 PM
PCD Engineering and EPC Stormwater - grading & erosion control plan comments 10/12/2021 1:19:05 PM
View PCD Project Manager
10/12/2021 1:18:41 PM
PCD Engineering - financial assurance form comments 10/12/2021 1:18:41 PM
View PCD Project Manager
10/12/2021 1:18:20 PM
EPC Stormwater - ESQCP comments 10/12/2021 1:18:20 PM
View PCD Project Manager
10/12/2021 1:18:00 PM
PCD Engineering and EPC Stormwater - drainage report comments 10/12/2021 1:18:00 PM
PCD Engineering Division
10/11/2021 10:57:42 AM
Review 1 redline comments on the following documents will be uploaded by the project manager:
- Drainage Report
- Financial Assurance Estimate Form
- Grading and Erosion Control Plan

Submit the following documents:
- Pond Operations and Maintenance Manual
- SDI Worksheet (required since the WQ only facility is an EDB)
- MS4 Post Construction Form

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
10/11/2021 10:57:42 AM
View EPC Stormwater Review
10/5/2021 2:15:10 PM
SWMP Checklist_v1 10/5/2021 2:15:10 PM
View EPC Stormwater Review
10/5/2021 2:14:52 PM
SWMP_v1 10/5/2021 2:14:52 PM
View EPC Stormwater Review
10/5/2021 2:14:21 PM
Detention Maintenance Agreement_v1 10/5/2021 2:14:21 PM
View EPC Stormwater Review
10/5/2021 2:13:59 PM
PBMP Applicability Form_v1 10/5/2021 2:13:59 PM
View EPC Stormwater Review
10/5/2021 2:13:41 PM
GEC Checklist_v1 10/5/2021 2:13:41 PM
EPC Stormwater Review
10/5/2021 2:12:51 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report...(to be uploaded by PM with PCD comments)
- ESQCP...................(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- PBMP Applicability Form
- Private Detention Basin / Stormwater Quality BMP Maintenance Agreement
- SWMP
- SWMP Checklist

Please provide the following documents on resubmittal for the water quality pond:
- O&M Manual
- MS4 Post Construction Form
- SDI
10/5/2021 2:12:51 PM
Pikes Peak Regional Building Department
10/4/2021 8:36:04 AM
Regarding a request for approval of a site development plan for Smith Plumbing and Heating, Enumerations has the following comments:

1. The address of 1875 Main St. shown on the development plan is the correct address for this site and should be used when submitting building plans for review/permit.


Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
10/4/2021 8:36:04 AM
View El Paso County Conservation Dist
9/30/2021 12:15:56 PM
9/30/2021 12:15:56 PM
View El Paso County Conservation Dist
9/30/2021 12:14:58 PM
9/30/2021 12:14:58 PM
View Widefield SD 3
9/23/2021 12:43:25 PM
9/23/2021 12:43:25 PM
View Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/16/2021 3:53:26 PM
Good afternoon,

Please see attached for my comments on Smith Plumbing, Heating & Cooling Site Development Plan. Please let me know if you have any questions or need additional information. After the requested information has been given, additional review will be required.

-The current utility easements must be shown, as well as the reception number or book and page number.
-The proposed locations for gas and electric meters must be shown.
-A layout of the proposed transformer location is required.
-The existing OH electric lines must be indicated within the existing utilities' easement.
-The existing gas main must be indicated within the existing utilities' easement.
-The planned water quality basin appears to be depicted in the current utilities easement. In any public utility easement, water quality basins (including any retaining walls) are prohibited.

Thanks,
____________________________________________
Corey Masoumi | Engineering Support Coordinator
Colorado Springs Utilities | Utilities Development Services
PHYSICAL: 1521 S Hancock Expressway, Colorado Springs, CO 80903
MAILING: PO BOX 1103, MC 1812, Colorado Springs, CO 80947-0010
Direct (719) 668-1856 | Main (719) 668-8259
www.csu.org • www.csu.org/Pages/BuildingDevelopment.aspx
9/16/2021 3:53:26 PM