Agency | Comment | ||
---|---|---|---|
PCD Project Manager
5/13/2022 7:47:59 AM |
Additional comments are minor, project can be scheduled for June 16 Planning Commission | 5/13/2022 7:47:59 AM | |
View |
PCD Project Manager
5/13/2022 7:42:40 AM |
Letter of Intent Redlines | 5/13/2022 7:42:40 AM |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/11/2022 11:00:04 AM |
Kylie, I am done with my review comments Al | 5/11/2022 11:00:04 AM |
PCD Engineering Division
5/10/2022 2:17:43 PM |
Engineer Review Ver.2 Please correct PCD File # on the Letter of Intent. Incorrect File # listed. Site Plan should have VA-22-002 as File # not PPR-21-043. Same Site plan was used for both project submittals. Road Impact fees are applicable at time of building permit. No further engineer comments or concerns. Issues addressed. Edward B. Schoenheit Engineer I Reviewer El Paso County Planning & Community Development EdwardSchoenheit@elpasoco.com 719-520-6813 (O) 719-502-9659 (C) |
5/10/2022 2:17:43 PM | |
View |
EPC Health Department
4/1/2022 4:59:23 PM |
4/1/2022 4:59:23 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/14/2022 1:43:56 PM |
CSU does not have water or wastewater in this area please, however you will need to reach out to Mary Hoaglund at CSU for any questions are concerns on the gas and electric for this site. She can be reached at 719-668-4083 | 3/14/2022 1:43:56 PM | |
View |
PCD Project Manager
3/10/2022 7:21:04 AM |
Please see redline comments on Site Plan | 3/10/2022 7:21:04 AM |
View |
PCD Project Manager
3/10/2022 7:20:45 AM |
Please see redline comments on LOI | 3/10/2022 7:20:45 AM |
EPC Stormwater Review
3/9/2022 2:40:14 PM |
Stormwater has no comments at this time. | 3/9/2022 2:40:14 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/9/2022 10:42:13 AM |
John, the customer only submitted a site plan for the new proposed building, however I will need a Preliminary Utility and Public Facility plan submitted in place to review prior to first review comments going out. Al |
3/9/2022 10:42:13 AM | |
View |
Colorado Parks and Wildlife
3/9/2022 7:21:59 AM |
3/9/2022 7:21:59 AM | |
Pikes Peak Regional Building Department
3/8/2022 2:48:10 PM |
1. Will there be a trash enclosure over 7’ in height associated with this project? If so, a separate address and permit will be required. 2. Plans show the retaining wall is under 3’ in height and the fencing will be under 7’ in height. No separate address or permit will be required for these items. 3. Building will use the address shown on the exhibit. Please submit plans under 1875 Main Street for the proposed project Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
3/8/2022 2:48:10 PM | |
PCD Engineering Division
3/8/2022 1:45:47 PM |
Engineer Review Ver.1 Please see engineer comments on the following documents for correction. Review documents will be uploaded by the PCD Project Manager. Letter of Intent Site Development Plan Thank you Edward B. Schoenheit Engineer Reviewer El Paso County Planning & Community Development EdwardSchoenheit@elpasoco.com 719-520-6813 (O) 719-502-9659 (C) |
3/8/2022 1:45:47 PM | |
View |
Widefield SD 3
3/1/2022 8:02:30 AM |
3/1/2022 8:02:30 AM | |
County Attorney - Development Review
2/17/2022 3:51:14 PM |
No comments from County Attorney's Office at this time. | 2/17/2022 3:51:14 PM | |
View |
EPC Environmental Services
2/17/2022 12:21:17 PM |
2/17/2022 12:21:17 PM | |
Mountain View Electric Association, Inc.
2/16/2022 12:14:20 PM |
This property is not within the Mountain View Electric Association territory | 2/16/2022 12:14:20 PM | |
View |
El Paso County Conservation Dist
2/16/2022 11:46:07 AM |
2/16/2022 11:46:07 AM | |
View |
El Paso County Conservation Dist
2/16/2022 11:20:25 AM |
2/16/2022 11:20:25 AM |