View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
5/11/2022 1:36:08 PM |
Comments resolved. Reviewed by: Gilbert LaForce, P.E. gilbertlaforce@elpasoco.com |
5/11/2022 1:36:08 PM | |
View |
PCD Project Manager
5/20/2021 1:07:11 PM |
Redlines | 5/20/2021 1:07:11 PM |
View |
PCD Project Manager
5/20/2021 1:06:56 PM |
Redlines | 5/20/2021 1:06:56 PM |
PCD Engineering Division
5/20/2021 11:50:52 AM |
Review 2: Previous comments are unresolved. 1. Update the letter of intent to provide information regarding the change of use being proposed. 2. Add a section in the letter of intent discussing the traffic impact. Is the change of use an increase or decrease in vehicular trips? See the Engineering Criteria Manual Appendix B Section B.1.2.C and B.1.2.D for criteria for when a traffic study memorandum is required and when no traffic study is required. Provide justification if no TIS is required. There does not appear to be any drainage impact since no site improvements or ground disturbance are proposed. Reviewed by: Gilbert LaForce gilbertlaforce@elpasoco.com Reviewed by: Gilbert LaForce gilbertlaforce@elpasoco.com |
5/20/2021 11:50:52 AM | |
View |
PCD Project Manager
4/20/2021 7:42:05 AM |
Letter of Intent_V1 redlines | 4/20/2021 7:42:05 AM |
View |
PCD Project Manager
4/20/2021 7:17:10 AM |
Site Plan Drawing_V1 redlines | 4/20/2021 7:17:10 AM |
PCD Engineering Division
4/19/2021 11:32:00 AM |
Review 1: 1. Update the letter of intent to provide information regarding the change of use being proposed. 2. Add a section in the letter of intent discussing the traffic impact. Is the change of use an increase or decrease in vehicular trips? See the Engineering Criteria Manual Appendix B Section B.1.2.C and B.1.2.D for criteria for when a traffic study memorandum is required and when no traffic study is required. Provide justification if no TIS is required. There does not appear to be any drainage impact since no site improvements or ground disturbance are proposed. Reviewed by: Gilbert LaForce gilbertlaforce@elpasoco.com |
4/19/2021 11:32:00 AM | |
View |
PCD Project Manager
4/13/2021 4:34:54 PM |
Site Plan Drawing redlines | 4/13/2021 4:34:54 PM |