Project Review Comments

Back to List


Project Name
7376 McLaughlin Road - Change of Use
Description
Location
Parcels
4307202022 4307202022
Applicant
ENM General Contractor
Richard Deras ( rderas@atei97.com )
(210) 725-9323
Richard Deras ( rderas@atei97.com )
(210) 725-9323
File Number
COM2121
Project Manager
Matthew Fitzsimmons
Status
Closed
Created
4/9/2021 4:48:27 PM

View: Project Documents



Review Comments (8)

Link Agency Comment
PCD Engineering Division
5/11/2022 1:36:08 PM
Comments resolved.

Reviewed by:
Gilbert LaForce, P.E.
gilbertlaforce@elpasoco.com
5/11/2022 1:36:08 PM
View PCD Project Manager
5/20/2021 1:07:11 PM
Redlines 5/20/2021 1:07:11 PM
View PCD Project Manager
5/20/2021 1:06:56 PM
Redlines 5/20/2021 1:06:56 PM
PCD Engineering Division
5/20/2021 11:50:52 AM
Review 2: Previous comments are unresolved.

1. Update the letter of intent to provide information regarding the change of use being proposed.
2. Add a section in the letter of intent discussing the traffic impact. Is the change of use an increase or decrease in vehicular trips? See the Engineering Criteria Manual Appendix B Section B.1.2.C and B.1.2.D for criteria for when a traffic study memorandum is required and when no traffic study is required. Provide justification if no TIS is required.

There does not appear to be any drainage impact since no site improvements or ground disturbance are proposed.

Reviewed by:
Gilbert LaForce
gilbertlaforce@elpasoco.com
Reviewed by:
Gilbert LaForce
gilbertlaforce@elpasoco.com
5/20/2021 11:50:52 AM
View PCD Project Manager
4/20/2021 7:42:05 AM
Letter of Intent_V1 redlines 4/20/2021 7:42:05 AM
View PCD Project Manager
4/20/2021 7:17:10 AM
Site Plan Drawing_V1 redlines 4/20/2021 7:17:10 AM
PCD Engineering Division
4/19/2021 11:32:00 AM
Review 1:
1. Update the letter of intent to provide information regarding the change of use being proposed.
2. Add a section in the letter of intent discussing the traffic impact. Is the change of use an increase or decrease in vehicular trips? See the Engineering Criteria Manual Appendix B Section B.1.2.C and B.1.2.D for criteria for when a traffic study memorandum is required and when no traffic study is required. Provide justification if no TIS is required.

There does not appear to be any drainage impact since no site improvements or ground disturbance are proposed.

Reviewed by:
Gilbert LaForce
gilbertlaforce@elpasoco.com
4/19/2021 11:32:00 AM
View PCD Project Manager
4/13/2021 4:34:54 PM
Site Plan Drawing redlines 4/13/2021 4:34:54 PM