Project Review Comments

Back to List


Project Name
Mikey's Total Car Care Site Development Plan
Description
Special Use Permit for existing car repair garage in I-2 district.
Location
Parcels
5406204040 5406204040
Applicant
CMG Corporation
Tim McConnell ( tmcconnell@drexelbarrell.com )
(719) 491-5170
Tim McConnell ( tmcconnell@drexelbarrell.com )
(719) 491-5170
EA Number
EA2078
File Number
PPR2139
Project Manager
Ryan Howser
Status
Active
Created
4/2/2021 3:59:18 PM

View: Project Documents



Review Comments (17)

Link Agency Comment
PCD Engineering Division
11/29/2021 8:40:06 AM
PCD Engineering has no further comments regarding drainage or transportation. Any approved documents will be uploaded by the project manager.


Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
11/29/2021 8:40:06 AM
PCD Project Manager
11/17/2021 4:59:06 PM
Planning Division has no comments at this time. 11/17/2021 4:59:06 PM
PCD Engineering Division
11/17/2021 12:47:17 PM
PCD Engineering has no further comments relating to drainage or transportation. Please provide signed copies of engineering documents:

- Drainage Letter

As a reminder:
- Please note the engineer's signature and date of signature shall appear through the seal.
- Owner/Developer's signature is required on engineering documents as well.

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
11/17/2021 12:47:17 PM
View PCD Project Manager
11/16/2021 8:41:20 AM
Planning Division has no further comments at this time. Please see attached for PCD Engineering Division comments on the site plan. 11/16/2021 8:41:20 AM
EPC Stormwater Review
10/28/2021 7:19:21 AM
Review 2: EPC Stormwater comments have been resolved on the following documents:
- Drainage Letter
- PBMP Applicability Form

EPC Stormwater has no further comments at this time. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
10/28/2021 7:19:21 AM
PCD Engineering Division
10/25/2021 12:46:03 PM
Review 2 comments will be uploaded by the project manager. Review comments on the following documents:

- Site Development Plan

Please note per the "Easement" statement on the property's plat, public utility easements are platted on the property. Before resubmitting please contact me at (719)-520-6314 or through email to discuss any questions or concerns.

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
10/25/2021 12:46:03 PM
View PCD Project Manager
10/7/2021 8:40:12 AM
PCD Planning & PCD Engineering - site development plan comments 10/7/2021 8:40:12 AM
View PCD Project Manager
10/7/2021 8:39:39 AM
PCD Planning & PCD Engineering - letter of intent comments 10/7/2021 8:39:39 AM
View PCD Project Manager
10/7/2021 8:39:18 AM
PCD Planning - landscape plan comments 10/7/2021 8:39:18 AM
View PCD Project Manager
10/7/2021 8:37:59 AM
PCD Engineering - drainage letter comments 10/7/2021 8:37:59 AM
PCD Project Manager
10/7/2021 8:27:59 AM
Lighting plan was not provided. If there is no lighting on site, please include in the letter of intent. If there is existing lighting, we still need a lighting plan with full photometrics for the site and details for light fixtures. 10/7/2021 8:27:59 AM
PCD Engineering Division
10/6/2021 1:54:05 PM
Review 1 comments will be uploaded by the project manager. Review comments on the following documents:

- Letter of Intent
- Drainage Letter
- Site Development Plan

There is no driveway permit on file. Please apply for a driveway permit by contacting Petra Rangel at petrarangel@elpasoco.com.

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com

Lupe Packman
Review Engineer
lupepackman@elpasoco.com
10/6/2021 1:54:05 PM
View EPC Stormwater Review
9/20/2021 10:47:06 AM
PBMP Applicability Form_V1 9/20/2021 10:47:06 AM
EPC Stormwater Review
9/20/2021 10:46:47 AM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Letter...(to be uploaded by PM with PCD comments)
- PBMP Applicability Form

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
9/20/2021 10:46:47 AM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/15/2021 1:39:56 PM
I have no review comments for this project Al 9/15/2021 1:39:56 PM
Pikes Peak Regional Building Department
9/8/2021 10:58:16 AM
Enumerations has no comment.


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
9/8/2021 10:58:16 AM
Cimarron Hills Fire
9/2/2021 7:43:58 AM
CHFD has reviewed the plot plan review for this project and it is approved. Construction drawings for the interior have been approved as well. JT McLeod, Division Chief-Fire Inspector III. 9/2/2021 7:43:58 AM