Project Review Comments

Back to List


Project Name
A-1 Chip Seal Additional Parking Lot Paved
Description
Site Plan for contractor's equipment and storage yard in CS to add additional impervious surface (15,570 SF) to the lot adjacent to corner lot (37,500 SF) with building. Aerial imagery appears to depict concrete surfacing on corner lot greater than 27K.....Total proposed area appears to be greater than acre.
Location
Parcels
5408102040 5408102040 5408102052 5408102052
Applicant
A-1 Chipseal Co.
John Fornander ( john@tnesinc.com )
(719) 635-6422
John Fornander ( john@tnesinc.com )
(719) 635-6422
EA Number
EA20118
File Number
COM2214
Project Manager
Lekishia Bellamy
Status
Closed
Created
3/24/2021 1:53:00 PM

View: Project Documents



Review Comments (40)

Link Agency Comment
View County Attorney - Development Review
7/11/2023 2:34:41 PM
Signature attached. 7/11/2023 2:34:41 PM
County Attorney - Development Review
7/6/2023 12:18:12 PM
No further comments to Detention Maintenance Agreement. Please have the property owner sign and I will then sign. 7/6/2023 12:18:12 PM
County Attorney - Development Review
6/22/2023 2:30:48 PM
There is one edit to paragraph 4 of the detention maintenance agreement from the 6/13/23 review that was not incorporated. Please include that additional language in that paragraph. 6/22/2023 2:30:48 PM
View County Attorney - Development Review
6/13/2023 2:19:32 PM
Comments and proposed edits to Detention Maintenance Agreement attached. 6/13/2023 2:19:32 PM
EPC Stormwater Review
5/31/2023 9:53:11 AM
All Stormwater comments have been addressed.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
5/31/2023 9:53:11 AM
Pikes Peak Regional Building Department
5/22/2023 9:48:05 AM
Retaining wall has been removed from scope. No address needed. No further comment.

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
5/22/2023 9:48:05 AM
PCD Engineering Division
5/16/2023 5:21:54 PM
Engineering has no further comments. Previous comments have been resolved. Any approved documents will be uploaded by the project manager.

Reviewed by:
Carlos Hernandez
Review Engineer I
carloshernandez@elpasoco.com
5/16/2023 5:21:54 PM
View EPC Stormwater Review
5/16/2023 2:04:29 PM
FAE_v3 5/16/2023 2:04:29 PM
EPC Stormwater Review
5/16/2023 2:03:53 PM
Review 4: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- FAE (review 3 comments)

Please sign and resubmit the following documents for approval:
- GEC Checklist
- SWMP Checklist

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
5/16/2023 2:03:53 PM
PCD Engineering Division
4/6/2023 3:30:45 PM
Review 3: See engineering comments on the following documents uploaded by the project manager

- Grading and Erosion Control Plan (minor comment)

Please note additional comments were made due to the design change in water quality BMP.

Reviewed by:
Carlos Hernandez
Review Engineer I
carloshernandez@elpasoco.com
4/6/2023 3:30:45 PM
View EPC Stormwater Review
4/6/2023 3:05:25 PM
ESQCP_v3 4/6/2023 3:05:25 PM
View EPC Stormwater Review
4/6/2023 3:04:42 PM
PBMP_v3 4/6/2023 3:04:42 PM
View EPC Stormwater Review
4/6/2023 3:04:27 PM
SDP_v3 4/6/2023 3:04:27 PM
View EPC Stormwater Review
4/6/2023 3:04:09 PM
FAE_v3 4/6/2023 3:04:09 PM
View EPC Stormwater Review
4/6/2023 3:03:50 PM
O&M_v3 4/6/2023 3:03:50 PM
View EPC Stormwater Review
4/6/2023 3:03:30 PM
GEC_v3 4/6/2023 3:03:30 PM
View EPC Stormwater Review
4/6/2023 3:03:09 PM
Drainage Letter_v3 4/6/2023 3:03:09 PM
EPC Stormwater Review
4/6/2023 3:02:40 PM
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Letter
- GEC Plan
- O&M Manual
- FAE
- Site Development Plan
- PBMP Applicability Form
- ESQCP

Please provide the following document with resubmittal (Planner: Please open a slot and request a review from Lori):
- Easement Agreement
- Maintenance Agreement

Please sign and resubmit the following documents for approval:
- GEC Checklist
- SWMP Checklist

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
4/6/2023 3:02:40 PM
Pikes Peak Regional Building Department
4/4/2023 12:18:23 PM
Per conversation with the Department of Public Works Stormwater department, the retaining wall will require a separate permit based on the possible surcharge which might affect its structural stability.

Please send Becky Allen (beckya@pprbd.org) a site plan showing the location of the retaining wall. I was unable to find a location on the site plan to address the retaining wall.

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
4/4/2023 12:18:23 PM
Pikes Peak Regional Building Department
8/10/2022 9:19:23 AM
Hello,
Thank you for contacting us regarding the retaining wall. Please see my comments below:

• How tall is the retaining wall? Walls over 4’ in height will require a separate address and permit, I can be contacted directly if an address is needed for the wall.
• Is this the wall on the north side of the building?
• Plans will need to be submitted to Regional Building Department for permit if over 4’ in height.

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
8/10/2022 9:19:23 AM
View EPC Stormwater Review
8/5/2022 9:31:18 AM
FAE_v2 8/5/2022 9:31:18 AM
View EPC Stormwater Review
8/5/2022 9:30:56 AM
O&M_v2 8/5/2022 9:30:56 AM
View EPC Stormwater Review
8/5/2022 9:30:31 AM
SWMP_v2 8/5/2022 9:30:31 AM
View EPC Stormwater Review
8/5/2022 9:28:50 AM
GEC_v2 8/5/2022 9:28:50 AM
View EPC Stormwater Review
8/5/2022 9:16:56 AM
Drainage Letter_v2 8/5/2022 9:16:56 AM
View PCD Project Manager
8/4/2022 3:53:23 PM
Site Plan Drawing Redlines 8/4/2022 3:53:23 PM
View PCD Project Manager
8/4/2022 3:53:03 PM
PBMP Applicability Form Redlines 8/4/2022 3:53:03 PM
EPC Stormwater Review
8/5/2022 9:10:09 AM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Letter
- GEC Plan
- SWMP
- O&M Manual
- FAE

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
8/5/2022 9:10:09 AM
PCD Engineering Division
7/12/2022 2:10:54 PM
Review 2 comments will be uploaded by the project manager. Review comments on the following documents:

- PBMP Applicability Form (Minor Comment)
- Site Development Plan (Minor Comment)

Please upload the following documents requested by EPC Stormwater for next review:
- 2022 Financial Assurance Estimate Form
- MS4 Post Construction Form
- O&M Manual
- Private Detention Basin / Stormwater Quality BMP Maintenance Agreement

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
7/12/2022 2:10:54 PM
View PCD Project Manager
6/1/2022 2:52:00 PM
Drainage Letter Redlines 6/1/2022 2:52:00 PM
View PCD Project Manager
6/1/2022 2:49:24 PM
Site Plan Redlines 6/1/2022 2:49:24 PM
View PCD Project Manager
6/1/2022 2:47:53 PM
Grading & Erosion Control Plan Redlines 6/1/2022 2:47:53 PM
View PCD Project Manager
6/1/2022 2:47:28 PM
Landscape Plan drawings redlines 6/1/2022 2:47:28 PM
View EPC Stormwater Review
6/1/2022 2:23:01 PM
ESQCP_v1 6/1/2022 2:23:01 PM
View EPC Stormwater Review
6/1/2022 2:22:34 PM
PBMP_v1 6/1/2022 2:22:34 PM
View EPC Stormwater Review
6/1/2022 2:22:17 PM
SWMP Checklist_v1 6/1/2022 2:22:17 PM
View EPC Stormwater Review
6/1/2022 2:21:35 PM
SWMP_v1 6/1/2022 2:21:35 PM
View EPC Stormwater Review
6/1/2022 2:21:06 PM
GEC Checklist_v1 6/1/2022 2:21:06 PM
EPC Stormwater Review
6/1/2022 2:21:52 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Letter......(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP
- SWMP Checklist
- PBMP Applicability Form
- ESQCP

Please provide the following documents on resubmittal:
- FAE
- MS4 Post Construction Form
- O&M Manual
- Private Detention Basin / Stormwater Quality BMP Maintenance Agreement

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
6/1/2022 2:21:52 PM
PCD Engineering Division
5/26/2022 3:01:11 PM
Review 1 comments will be uploaded by the project manager. Review comments on the following documents:

- Drainage Letter
- PBMP Applicability Form (Minor Comment)
- Site Development Plan (Minor Comments)
- SWMP (Minor Comment)
- Grading & Erosion Control Plan (Minor Comments)


Note:
- Please submit a Financial Assurance Estimate Form next submittal.
- There is no Driveway Access Waiver on file for existing driveway. Please apply for a driveway access waiver through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online.

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
5/26/2022 3:01:11 PM