Project Review Comments
- Project Name
- Villages at WaterView North Early Grading
- Description
- 100 acres Pre-development Grading Stand Alone BoCC required
- Location
- Applicant
-
Dakota Springs Engineering
PA Koscielski ( dse.pak7@gmail.com )
(719) 377-0244 PA Koscielski ( dse.pak7@gmail.com )
(719) 377-0244 - EA Number
- EA2149
- File Number
- EGP214
- Project Manager
- Justin Kilgore
- Status
- Closed
- Created
- 3/17/2021 2:33:44 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
Colorado Department of Transportation - Pueblo Office
12/16/2022 10:02:23 AM |
12/16/2022 10:02:23 AM | |
View |
EPC Stormwater Review
3/22/2022 5:10:37 PM |
ESQCP_v2 | 3/22/2022 5:10:37 PM |
View |
EPC Stormwater Review
3/22/2022 5:10:13 PM |
GEC Checklist_v2 | 3/22/2022 5:10:13 PM |
Colorado Department of Transportation - Pueblo Office
3/21/2022 11:29:18 AM |
Comments will be forthcoming. Arthur Gonzales - Access Manager | 3/21/2022 11:29:18 AM | |
EPC Stormwater Review
3/22/2022 5:09:34 PM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - GEC (to be uploaded by PM with PCD comments) - ESQCP - GEC Checklist The SWMP does not meet EPC criteria and will be reviewed with the SWMP checklist upon resubmittal. Please reach out prior to resubmittal if you have any questions regarding SWMP requirements. Due to the volume or complexity of the comments provided, these comments are cursory in nature and EPC Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review. Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
3/22/2022 5:09:34 PM | |
View |
PCD Project Manager
3/15/2022 8:06:36 AM |
Please see redline comments on SWMP | 3/15/2022 8:06:36 AM |
View |
PCD Project Manager
3/15/2022 8:06:14 AM |
Please see redline comments on Grading Narrative | 3/15/2022 8:06:14 AM |
View |
PCD Project Manager
3/15/2022 8:05:51 AM |
Please see redline comments on GEC Plan | 3/15/2022 8:05:51 AM |
View |
PCD Project Manager
3/15/2022 8:05:30 AM |
Please see redline comments on Drainage Report | 3/15/2022 8:05:30 AM |
PCD Engineering Division
3/10/2022 3:15:40 PM |
NOTICE: The resubmittal will be treated as a first review due to the nature of the review comments. Additional comments will be provided on the resubmittal. Staff recommends scheduling a meeting to discuss any comments the applicant requires clarification to ensure they are addressed appropriately. Review #2 redline comments to the following documents will be uploaded individually: - Drainage Report - Grading and Erosion Control Plans - Grading and Erosion Control and Stormwater Management Narrative. - Financial Assurance Estimate - SWMP Unresolved. The document uploaded for Stormwater Management Plan (SWMP) is not correct. See the SWMP checklist posted on the County website for contents that needs to be included in the SWMP report. Contact the stormwater team for guidance. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
3/10/2022 3:15:40 PM | |
911 Authority - El Paso/Teller County
2/14/2022 8:13:13 AM |
No new street names requested with this submittal. No action for E911 until development plans include streetnames and layouts. Thank you. Justin |
2/14/2022 8:13:13 AM | |
Colorado Springs Public Works
2/10/2022 9:03:55 AM |
Engineering Development Review has the following comments: No comments on this application request. Informational comments: Engineering Development Review will require all public ROW improvements to be built to City Engineering and Traffic Engineering standards if this site is chosen for pre-annexation. In addition, if the development is annex into the City, it will need to follow the City's Stormwater Enterprise Division policies and design criteria. Patrick V. Morris Civil Engineer II Public Works/Engineering Development Review City of Colorado Springs Phone: 719-385-5075 Patrick.morris@coloradosprings.gov |
2/10/2022 9:03:55 AM | |
Colorado Springs Public Works
2/8/2022 3:21:36 PM |
Traffic Engineering has the following comments: 1- Traffic Engineering will require all public improvements to be built to full City Standards if this site is chosen for pre-annexation. 2- Future comment(s) might be given when city traffic review the furfure development plan. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
2/8/2022 3:21:36 PM | |
View |
Colorado Department of Transportation - Pueblo Office
11/19/2021 10:23:18 AM |
11/19/2021 10:23:18 AM | |
View |
PCD Project Manager
11/16/2021 2:30:24 PM |
Please see redline comments on Vicinity Map | 11/16/2021 2:30:24 PM |
View |
PCD Project Manager
11/16/2021 2:30:07 PM |
Please see redline comments on GEC Plan | 11/16/2021 2:30:07 PM |
View |
PCD Project Manager
11/16/2021 2:29:51 PM |
Please see redline comments on FAE | 11/16/2021 2:29:51 PM |
View |
PCD Project Manager
11/16/2021 2:29:32 PM |
Please see redline comments on ESQCP | 11/16/2021 2:29:32 PM |
View |
PCD Project Manager
11/16/2021 2:29:02 PM |
Please see redline comments on Drainage Report | 11/16/2021 2:29:02 PM |
Colorado Department of Transportation - Pueblo Office
11/16/2021 11:50:39 AM |
Comments will be forthcoming. - Arthur Gonzales, Access Manager | 11/16/2021 11:50:39 AM | |
View |
PCD Engineering Division
11/10/2021 1:27:32 PM |
Review #1: Financial Assurance Estimate Form redlines. | 11/10/2021 1:27:32 PM |
View |
PCD Engineering Division
11/10/2021 1:25:00 PM |
Review #1: Grading and Erosion Control Plan redlines. Markup summary is located at the end of the document. |
11/10/2021 1:25:00 PM |
View |
PCD Engineering Division
11/10/2021 1:19:49 PM |
Review #1: Drainage Report redlines. Markup summary is located at the end of the document. |
11/10/2021 1:19:49 PM |
View |
EPC Stormwater Review
11/10/2021 12:10:36 PM |
ESQCP_v1 | 11/10/2021 12:10:36 PM |
EPC Stormwater Review
11/10/2021 12:10:07 PM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - GEC (to be uploaded by PM with PCD comments) - ESQCP Please provide the following documents on resubmittal: - SWMP (see ECM Section I.4.1 for SWMP requirements) - Updated GEC Checklist and SWMP Checklist (Checklists can be found at: https://publicworks.elpasoco.com/stormwater/) The following documents were not reviewed by EPC Stormwater. These are not required with the EGP application and will be reviewed under subsequent filing: - MS4 Post Construction Detention Form - PBMP Applicability Form Due to the volume or complexity of the comments provided, these comments are cursory in nature and EPC Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review. Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
11/10/2021 12:10:07 PM | |
PCD Engineering Division
11/10/2021 1:36:23 PM |
NOTICE: The resubmittal will be treated as a first review due to the nature of the review comments. Additional comments will be provided on the resubmittal. Review #1 redline comments to the following documents will be uploaded individually: - Drainage Report - Grading and Erosion Control Plans - Financial Assurance Estimate The document uploaded for Stormwater Management Plan (SWMP) is not correct. See the SWMP checklist posted on the County website for contents that needs to be included in the SWMP report. Contact the stormwater team for guidance. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
11/10/2021 1:36:23 PM | |
Colorado Springs Airport Advisory Commission
11/8/2021 4:02:25 PM |
Airport staff has no comments to provide on the grading and erosion control permit. | 11/8/2021 4:02:25 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
11/8/2021 10:03:49 AM |
I have no review comments for the above name project Al | 11/8/2021 10:03:49 AM | |
911 Authority - El Paso/Teller County
10/21/2021 9:08:43 AM |
No action for E911 on this submittal. Thank you. Justin. |
10/21/2021 9:08:43 AM | |
Mountain View Electric Association, Inc.
10/21/2021 8:49:56 AM |
Mountain View Electric Association has no objection to the current plan. | 10/21/2021 8:49:56 AM |