Project Review Comments

Back to List


Project Name
Northcrest Flex Space PPR
Description
PPR for flex office space and outdoor storage areas. Plat must be recorded prior to approval. V222
Location
Parcels
5332309004 5332309004 5332309005 5332309005 5332309006 5332309006
Applicant
RMG-Rocky Mountain Group
Jennifer Zezlina ( jzezlina@rmg-engineers.com ) Jennifer Zezlina ( jzezlina@rmg-engineers.com )
File Number
PPR2136
Project Manager
Ashlyn Mathy
Status
Closed
Created
3/15/2021 2:36:48 PM

View: Project Documents



Review Comments (75)

Link Agency Comment
EPC Stormwater Review
2/21/2023 9:38:13 AM
All Stormwater comments have been addressed. 2/21/2023 9:38:13 AM
PCD Engineering Division
2/15/2023 12:09:07 PM
Engineering Review Version 7

No further engineer comments. Project routed for final approval.

Thank you

Edward B. Schoenheit
Engineer I Reviewer
El Paso County Planning & Community Development
EdwardSchoenheit@elpasoco.com
719-520-6813 (O)
719-502-9659 (C)
2/15/2023 12:09:07 PM
PCD Project Manager
2/2/2023 8:38:47 AM
stormwater has comment for the pond document and drainage report 2/2/2023 8:38:47 AM
View EPC Stormwater Review
2/1/2023 1:52:37 PM
Drainage Report_v6 2/1/2023 1:52:37 PM
View EPC Stormwater Review
2/1/2023 1:51:39 PM
Pond Plans_v6 2/1/2023 1:51:39 PM
EPC Stormwater Review
2/1/2023 1:59:05 PM
Review 6: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Pond Plans
- Drainage Report

Please submit the following signed documents with the next resubmittal:
- Drainage Report
- GEC Plans
- GEC Checklist
- PBMP Applicability Form
- FAE

Planner: Please put the next resubmittal on a 2-week review period.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
2/1/2023 1:59:05 PM
View PCD Engineering Division
1/24/2023 11:17:54 AM
CD Standard Signature blocks 1/24/2023 11:17:54 AM
View PCD Engineering Division
1/24/2023 11:17:19 AM
Std EPC CD notes 1/24/2023 11:17:19 AM
PCD Engineering Division
1/24/2023 11:19:05 AM
Engineering Review Version 6

The following documents were reviewed. No further engineer comments. Pending Stormwater review and final signatures on open documents. Engineer will coordinate for signatures.

1. Pond Design V6. Pedestrian railing was added to pond design plans.
2. GEC Plan V6 Will need Owner signature statement added (missing).
3. Drainage Report-Final V6 dated 01/11/2023

The FAE V5 will require signatures.
Detention Maintenance Agreement will require signature.
Construction Drawings: Please add title page, sheet index, Std EPC CDs notes and signature blocks. Signature block and Std notes examples attached.

Thank you

Edward B. Schoenheit
Engineer I Reviewer
El Paso County Planning & Community Development
EdwardSchoenheit@elpasoco.com
719-520-6813 (O)
719-502-9659 (C)
1/24/2023 11:19:05 AM
PCD Project Manager
12/21/2022 11:11:31 AM
project manager stated on 9/2/22 that planning does not have any further comments. At this time engineering and storm water have comments to be revised for version 5.

Thank you!
12/21/2022 11:11:31 AM
View EPC Stormwater Review
12/20/2022 11:54:06 AM
Drainage Report_v5 12/20/2022 11:54:06 AM
View EPC Stormwater Review
12/20/2022 11:52:34 AM
Pond Plans_v5 12/20/2022 11:52:34 AM
View EPC Stormwater Review
12/20/2022 11:29:31 AM
GEC_v5 12/20/2022 11:29:31 AM
PCD Engineering Division
12/20/2022 6:02:03 PM
Engineering Review Version 5

Please see comments on the following documents.

-Pond Design Detail CDs V5. Version 5 was reviewed. Pending submission of Pond Design Ver.6 with corrections per applicant.
-GEC Plan V5. Please address pedestrian railing
-SDP V5. Please address pedestrian railing
Please note. The pedestrian safety railing design details may be added to either the SDP, GEC Plan or the Pond Design CDs with a design detail call out showing the type of railing to meet ECM 2.6.7.E

The Deviation for the southern access driveway along Canada Drive was approved with conditions.

Updated & corrected FAE V5 was received by the applicant on 12/14/22. Corrections made. Will require signature.

Updated signed Final Drainage Report Ver.6 dated 12/16/22 was received by the applicant on 12/19/22. An updated FDR and GEC Plan are needed to ensure all comments are addressed and match the Pond Design.

Thank you

Edward B. Schoenheit
Engineer I Reviewer
El Paso County Planning & Community Development
EdwardSchoenheit@elpasoco.com
719-520-6813 (O)
719-502-9659 (C)
12/20/2022 6:02:03 PM
EPC Stormwater Review
12/20/2022 11:19:33 AM
Review 5: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- GEC Plan...............(uploaded with PCD comments)
- Pond Plans.............(uploaded with PCD comments)
- Drainage Report

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
12/20/2022 11:19:33 AM
View PCD Project Manager
9/8/2022 10:43:19 AM
Site Development Plan Redlines 9/8/2022 10:43:19 AM
View PCD Project Manager
9/8/2022 10:42:52 AM
GEC Plan Redlines 9/8/2022 10:42:52 AM
View PCD Project Manager
9/8/2022 10:42:29 AM
Financial Assurance Forms Redlines 9/8/2022 10:42:29 AM
View PCD Project Manager
9/8/2022 10:39:24 AM
Drainage Report Final Redlines 9/8/2022 10:39:24 AM
PCD Engineering Division
9/8/2022 7:53:44 AM
Review 4 comments will be uploaded by the project manager. Review comments on the following documents:

- Financial Assurance Forms
- Final Drainage Report
- Grading and Erosion Control Plan
- Site Development Plan (Minor Comment)
- Please submit a revised SDI sheet using the updated values from the final drainage report.

A deviation request will be needed for the two proposed access points on Canada Drive. The proposed access locations do not meet the ECM Chapter 2.4.1(B) Access Spacing requirements. A revised traffic memo will be required as well.

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
9/8/2022 7:53:44 AM
EPC Stormwater Review
9/8/2022 9:32:35 AM
Review 4: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- FAE........................(to be uploaded by PM with PCD comments)
- Drainage Report....(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
9/8/2022 9:32:35 AM
PCD Project Manager
9/2/2022 10:27:49 AM
Planning department has no further comments at this time 9/2/2022 10:27:49 AM
County Attorney - Development Review
8/25/2022 12:21:23 PM
No further comments from County Attorney - Development Review. 8/25/2022 12:21:23 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/11/2022 3:16:23 PM
Detention pond conflicts with existing electrical infrastructure in utility easement. Requires reroute of 600 amp structure, switch, and electric lines. Coordinate with field engineering for estimated cost and design of any reroutes:

Ginny Halvorson | Engineering Support Coordinator
Colorado Springs Utilities | System Planning & Projects |Engineering Design
O (719) 668-5567 | C (719) 491-8420
ghalvorson@csu.org

and/or

Rudy Duran | Engineering Support Coordinator
Colorado Springs Utilities | System Planning & Projects |Engineering Design
O 719-668-8762 | C 719-464-7961
rduran@csu.org

Reviewer:
Caleb Savage | Engineer III
Utilities Development Services | Colorado Springs Utilities
O: 719-668-1855 | Main: 719-668-8259
cjsavage@csu.org
5/11/2022 3:16:23 PM
View PCD Project Manager
2/18/2022 9:20:07 AM
Drainage Report - EPC Stormwater Redlines 2/18/2022 9:20:07 AM
PCD Project Manager
2/17/2022 1:52:42 PM
PCD Planning has no further comments 2/17/2022 1:52:42 PM
View PCD Project Manager
2/17/2022 1:52:17 PM
Site Development Plan - PCD Engineering Redlines 2/17/2022 1:52:17 PM
View PCD Project Manager
2/18/2022 9:19:24 AM
Grading and Erosion Control Plan - PCD Engineering and ECM Stormwater Redlines 2/18/2022 9:19:24 AM
View PCD Project Manager
2/18/2022 9:17:36 AM
Financial Assurance Forms - PCD Engineering and ECM Stormwater Redlines 2/18/2022 9:17:36 AM
PCD Engineering Division
2/16/2022 4:29:27 PM
Review 3 comments will be uploaded by the project manager. Review comments on the following documents:

- Grading and Erosion Control Plan
- Financial Assurance Estimate Form
- Site Development Plan

FYI:
A Work in the Right-of-Way Permit is required from the El Paso County Department of Public Works for all work in the county right-of-way.

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
2/16/2022 4:29:27 PM
PCD Project Manager
2/16/2022 4:28:41 PM
Comments will be uploaded 2/17/2022 2/16/2022 4:28:41 PM
EPC Stormwater Review
2/17/2022 3:36:37 PM
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- FAE........................(to be uploaded by PM with PCD comments)
- Drainage Report....(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)


Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
2/17/2022 3:36:37 PM
View County Attorney - Development Review
2/8/2022 12:22:22 PM
Proposed changes to Detention Maintenance Agreement attached. 2/8/2022 12:22:22 PM
View Cherokee Metro Dist
2/8/2022 10:14:05 AM
See comments on attached Sheet DP.05 2/8/2022 10:14:05 AM
View PCD Project Manager
12/14/2021 7:23:25 AM
Please see redline comments on Traffic Memo 12/14/2021 7:23:25 AM
View PCD Project Manager
12/14/2021 7:23:04 AM
Please see redline comments on SDP 12/14/2021 7:23:04 AM
View PCD Project Manager
12/14/2021 7:22:35 AM
Please see redline comments on GEC Plan 12/14/2021 7:22:35 AM
View PCD Project Manager
12/14/2021 7:22:11 AM
Please see redline comments on GEC Checklist 12/14/2021 7:22:11 AM
View PCD Project Manager
12/14/2021 7:21:45 AM
Please see redline comments on FAE 12/14/2021 7:21:45 AM
View PCD Project Manager
12/14/2021 7:21:23 AM
Please see redline comments on ESQCP 12/14/2021 7:21:23 AM
View PCD Project Manager
12/14/2021 7:20:46 AM
Please see redline comments on Drainage Report 12/14/2021 7:20:46 AM
PCD Project Manager
12/9/2021 7:16:38 AM
Comments to be uploaded 12-9 12/9/2021 7:16:38 AM
View EPC Stormwater Review
12/8/2021 10:37:26 AM
PBMP_v2 12/8/2021 10:37:26 AM
View EPC Stormwater Review
12/8/2021 10:37:02 AM
ESQCP_v2 12/8/2021 10:37:02 AM
View EPC Stormwater Review
12/8/2021 10:36:36 AM
GEC Checklist_v2 12/8/2021 10:36:36 AM
EPC Stormwater Review
12/8/2021 10:35:54 AM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- FAE........................(to be uploaded by PM with PCD comments)
- Drainage Report....(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- ESQCP
- PBMP Applicability Form

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
12/8/2021 10:35:54 AM
PCD Engineering Division
12/6/2021 10:24:17 AM
Review 2 comments will be uploaded by the project manager. Please address comments on the following documents:

-Traffic memo
-Site development plan
-GEC plan
-FAE
- Construction Drawings (Plans-Profiles): Please remove this submittal requirement from EDARP.

FYI:
- A Work in Right-of-Way Permit is required for all work within county right of way. Please apply for a permit through El Paso County Department of Public Works.
- Per LDC 1.13 any retaining wall above 4ft in height is required to have a building permit. Building permits can be obtained through the Pike Peak Regional Building Department.
- Please provide a public improvement easement and show exhibit on the site development plan for the highlighted sections of proposed sidewalk on the site development plan.


Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
12/6/2021 10:24:17 AM
County Attorney - Development Review
12/3/2021 2:31:29 PM
Please provide the Detention Maintenance Agreement in Word for ease of editing. 12/3/2021 2:31:29 PM
View Cherokee Metro Dist
11/22/2021 4:52:08 PM
See review comments on Sheet DP.05 11/22/2021 4:52:08 PM
View Cherokee Metro Dist
9/15/2021 4:43:15 PM
The Northcrest development is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer.

See attached Drawing DP.08 for comments on Utility Plan
9/15/2021 4:43:15 PM
View PCD Project Manager
9/9/2021 11:14:43 AM
Please see redline comments on Traffic Memo 9/9/2021 11:14:43 AM
View PCD Project Manager
9/9/2021 11:13:50 AM
Please see redline comments on Title Commitment 9/9/2021 11:13:50 AM
View PCD Project Manager
9/9/2021 11:12:34 AM
Please see redline comments on SWMP Checklist 9/9/2021 11:12:34 AM
View PCD Project Manager
9/9/2021 11:12:03 AM
Please see redline comments on SWMP 9/9/2021 11:12:03 AM
View PCD Project Manager
9/9/2021 11:11:22 AM
Please see redline comments on Site Development Plan 9/9/2021 11:11:22 AM
View PCD Project Manager
9/9/2021 11:10:35 AM
Please see redline comments on LOI 9/9/2021 11:10:35 AM
View PCD Project Manager
9/9/2021 11:08:59 AM
Please see redline comments on Landscape Plans 9/9/2021 11:08:59 AM
View PCD Project Manager
9/9/2021 11:08:27 AM
Please see redline comments on GEC Plan 9/9/2021 11:08:27 AM
View PCD Project Manager
9/9/2021 11:07:51 AM
Please see redline comments on Floor Plans 9/9/2021 11:07:51 AM
View PCD Project Manager
9/9/2021 11:07:23 AM
Please see redline comments on FAE 9/9/2021 11:07:23 AM
View PCD Project Manager
9/9/2021 11:07:01 AM
Please see redline comments on ESQCP 9/9/2021 11:07:01 AM
View PCD Project Manager
9/9/2021 11:06:37 AM
Please see redline comments on Drainage Report 9/9/2021 11:06:37 AM
View PCD Project Manager
9/9/2021 11:06:04 AM
Please see redline comments on Application Form 9/9/2021 11:06:04 AM
PCD Engineering Division
9/7/2021 4:04:45 PM
Review 1 comments will be uploaded by the project manager. Please address comments on the following documents:

-Drainage report: comments are precursory because of missing sections of report.
-Traffic memo
-Site development plan
-GEC plan
-FAE

Note: next review will be considered as the first because of missing sections in drainage report and is subject to new comments.

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
9/7/2021 4:04:45 PM
View EPC Stormwater Review
9/7/2021 2:10:24 PM
ESQCP_v1 9/7/2021 2:10:24 PM
View EPC Stormwater Review
9/7/2021 2:10:03 PM
SWMP Checklist_v1 9/7/2021 2:10:03 PM
View EPC Stormwater Review
9/7/2021 2:09:38 PM
SWMP_V1 9/7/2021 2:09:38 PM
EPC Stormwater Review
9/7/2021 2:10:52 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- FAE........................(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- Drainage Report....(to be uploaded by PM with PCD comments)
- SWMP
- SWMP Checklist
- ESQCP

EPC Stormwater will review the following documents on resubmittal:
- MS4 Post Construction Form
- SDI

Please provide the following documents:
- GEC Checklist
- PBMP Applicability Form
- O&M Manual
- Private Detention Basin / Stormwater Quality BMP Maintenance Agreement

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
9/7/2021 2:10:52 PM
Pikes Peak Regional Building Department
9/7/2021 8:54:24 AM
1. Secondary addressing is incorrectly shown on the floor plans and site development plan. Please change the secondary addressing per the addressing plan sent to Jennifer Zezlina on 8/26/21. One separate address has been assigned for the storage space 2522 Canada Drive and the office/warehouse building is 2510 Canada Drive, and the suites will start with 100, 108, 116 etc. (jumping by 8)
2. Will any of the trash receptacles be over 7’ in height? An address will need to be assigned and a permit issued if any trash receptacle is over 7’.


Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
9/7/2021 8:54:24 AM
EPC Code Enforcement
9/7/2021 8:54:00 AM
No comment from Code Enforcement. 9/7/2021 8:54:00 AM
View County Attorney - Development Review
9/2/2021 1:46:51 PM
The Detention Maintenance Agreement was not completed and was not in an editable version. Attached is the document in Word. Applicant must fill in all needed information and resubmit in Word for review. 9/2/2021 1:46:51 PM
View EPC Parks Department
9/1/2021 9:36:03 AM
Please see final administrative Parks comments attached.

Thanks, Greg
9/1/2021 9:36:03 AM
View EPC Environmental Services
8/31/2021 11:35:29 AM
8/31/2021 11:35:29 AM
Cimarron Hills Fire
8/26/2021 7:27:28 AM
CHFD has reviewed the Plot Plan Review and site reviews for the above project. We have no comments or issues. A fire commitment letter has been uploaded from a previous review. J.T. McLeod, Division Chief CHFD. 8/26/2021 7:27:28 AM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
8/19/2021 5:22:59 PM
Please coordinate with the CSU field engineer for final location of the gas meter and service line.
Field engineer:
Ginny Halvorson, 719-668-5567, ghalvorson@csu.org

Reviewer:
Caleb Savage, 719-668-1855, cjsavage@csu.org
Utilities Development Services
8/19/2021 5:22:59 PM