Project Review Comments

Back to List


Project Name
Paint Brush Hills Equipment Storage Facility
Description
Applicant wishes to construct a new maintenance facility for infrastructure within a tract of land that serves as drainage, and utilities to be owned and maintained by the District.
Location
Parcels
5225305053 5225305053
Applicant
Kimley-Horn and Associates, Inc.
Rachael Rodgers ( Rachael.Rodgers@kimley-horn.com )
(720) 826-4389
Rachael Rodgers ( Rachael.Rodgers@kimley-horn.com )
(720) 826-4389
File Number
PPR2327
Project Manager
Christian Haas
Status
Closed
Created
2/26/2021 9:02:12 AM

View: Project Documents



Review Comments (11)

Link Agency Comment
PCD Engineering Division
11/29/2023 9:18:05 AM
Engineering Review Ver.3

No further engineer comments.
Deviation Request has been approved.
- A driveway access permit will be required. Applicant to submit via EDARP for approval.
- Road Impact fees are applicable for Warehouse type use.
2,520sqft BLDG Warehouse $1,865 /1,000sqft

Thank you

Edward Schoenheit, Engineer I
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
https://planningdevelopment.elpasoco.com/
11/29/2023 9:18:05 AM
PCD Project Manager
11/13/2023 9:37:19 AM
No Additional Comments 11/13/2023 9:37:19 AM
View PCD Engineering Division
11/8/2023 7:21:08 PM
Engineering Review Ver.2

Please see comments on the following review documents.

- Deviation Request Form
- A driveway access permit will be required. Applicant to submit via EDARP and provide copy.
- Road Impact fees are applicable for Warehouse type use.
2,520sqft BLDG Warehouse $1,865 /1,000sqft

Thank you

Edward Schoenheit, Engineer I
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
https://planningdevelopment.elpasoco.com/
11/8/2023 7:21:08 PM
Upper Black Squirrel Creek GWMD
9/6/2023 3:18:31 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. 9/6/2023 3:18:31 PM
View Mountain View Electric Association, Inc.
9/6/2023 11:02:50 AM
See attached comments 9/6/2023 11:02:50 AM
View PCD Project Manager
9/5/2023 7:56:51 AM
Planning Review Ver.1

Please see the review comments on the following documents:

- Letter of Intent
- Site Plan


Subsequent review may have additional comments and require updates to additional documents.
.
9/5/2023 7:56:51 AM
Pikes Peak Regional Building Department
8/25/2023 10:39:28 AM
1. The address for the new maintenance garage/office will be 10815 Londonderry Drive. The existing pump house building (10028 Jagger Way) is accessed off of Jaggar Way but this building will be accessed off of Londonderry Drive.
2. Please update all development plan pages to show the newly assigned address. Also, please be sure to submit the plans for permit under this new address.
3. No further comments.

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
8/25/2023 10:39:28 AM
PCD Engineering Division
8/24/2023 12:48:38 PM
Engineering Review Ver.1

Please see comments on the following review documents.

- Letter of Intent
- Site Plan
- A driveway access permit will be required
- A deviation for access to a Collector Road is needed.
- Road Impact fees are applicable for Warehouse type use.

Thank you.

Edward Schoenheit, Engineer I
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
https://planningdevelopment.elpasoco.com/
8/24/2023 12:48:38 PM
EPC Stormwater Review
8/21/2023 12:57:37 PM
EPC Stormwater has no comments.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
ChristinaPrete@elpasoco.com
8/21/2023 12:57:37 PM
View Falcon Fire Protection District
8/17/2023 7:26:30 AM
8/17/2023 7:26:30 AM
911 Authority - El Paso/Teller County
8/15/2023 11:41:59 AM
No action for E911 on this submittal.
Thank you.
Justin
8/15/2023 11:41:59 AM