10/4/2021 7:27:06 AM |
The project manager will upload any approved documents. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
10/4/2021 7:27:06 AM | |
PCD Engineering Division
9/22/2021 11:12:09 AM |
Please submit the grading and erosion control plan with signed signature blocks and engineer stamps on every sheet of the grading control plan. Please feel free to contact me if you have any questions. Review engineer Lupe Packman lupepackman@elpasoco.com |
9/22/2021 11:12:09 AM | |
PCD Project Manager
9/9/2021 12:50:34 PM |
Prepping item for approval. Site plan sent to supervisor for approval. | 9/9/2021 12:50:34 PM | |
PCD Engineering Division
9/9/2021 9:19:24 AM |
There are no further comments relating to drainage or transportation. The project manager will upload any approved documents. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
9/9/2021 9:19:24 AM | |
PCD Project Manager
8/16/2021 9:14:12 AM |
PCD Planning comments have been resolved. Per Lupe's previous comment, please submit the following documents with the appropriate stamps/signatures for approval: -Financial Assurance -ESQCP After these are provided, I will start prepping this PPR for approval. |
8/16/2021 9:14:12 AM | |
Cherokee Metro Dist
8/3/2021 11:32:14 AM |
No further comments | 8/3/2021 11:32:14 AM | |
View |
Cherokee Metro Dist
7/27/2021 4:29:31 PM |
See comments on Site Development Plan Utility Plan - attached. | 7/27/2021 4:29:31 PM |
PCD Project Manager
7/27/2021 2:58:36 PM |
-Letter of intent needs to reference "alterative landscaping plan" and you need to justify your need for one. -The site plan and letter of intent need to reference the parking agreement and recording information. Both documents need to have a description of what the parking agreement means for parking for this property. |
7/27/2021 2:58:36 PM | |
View |
PCD Project Manager
7/13/2021 4:40:26 PM |
Letter of intent redlines | 7/13/2021 4:40:26 PM |
PCD Engineering Division
7/13/2021 11:36:32 AM |
PCD Engineering comments have been resolved. Please submit the following documents with the appropriate stamps/signatures for approval: -Financial Assurance -ESQCP Note to planner: Place a 1 week due date on the resubmittal for final for final approval. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
7/13/2021 11:36:32 AM | |
EPC Stormwater Review
7/6/2021 12:36:34 PM |
Review 3: EPC Stormwater comments have been resolved on the following documents: - ESQCP - SWMP - SWMP Checklist EPC Stormwater has no further comments at this time. Thanks. Reviewed by: Glenn Reese, P.E. Stormwater Engineer I glennreese@elpasoco.com |
7/6/2021 12:36:34 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/1/2021 2:48:13 PM |
No comments, recommend approval. | 7/1/2021 2:48:13 PM | |
Cherokee Metro Dist
6/29/2021 10:28:24 AM |
Water Meter is to be located inside building. Meters in exterior meter box not allowed. Add curb box at property line. Show cleanout on sanitary lateral Add note that water and sanitary sewer are to be installed per CSU Standards with Cherokee Metro District Exceptions as provided on the Cherokee website https://www.cherokeemetro.org/ |
6/29/2021 10:28:24 AM | |
View |
PCD Project Manager
6/8/2021 12:44:53 PM |
Please see attached planning comments to the site development plan. Please note both comments are outstanding from previous review; please reach out to PM Planner Sophie Kiepe at sophiekiepe@elpasoco.com | 6/8/2021 12:44:53 PM |
View |
PCD Engineering Division
6/7/2021 3:11:24 PM |
Review 2 redline comments on the following document is attached: - Drainage Letter Address all remaining engineering and stormwater team comments and resubmit the following documents with signatures/stamp for final approval: - Drainage Letter - Grading and Erosion Control Plan (all sheets must have PE stamp/signature) - ESQCP - Financial Assurance Estimate Form Note to planner: Place a 1 week due date on the resubmittal for final for final approval. Comments resolved on the following documents: - Grading & Erosion Control Plans - Site Development Plan - Financial Assurance Estimate Reviewed by: Gilbert LaForce gilbertlaforce@elpasoco.com |
6/7/2021 3:11:24 PM |
View |
EPC Stormwater Review
6/1/2021 8:03:58 AM |
ESQCP_V2 | 6/1/2021 8:03:58 AM |
View |
EPC Stormwater Review
6/1/2021 8:03:08 AM |
SWMP_V2 | 6/1/2021 8:03:08 AM |
View |
EPC Stormwater Review
6/1/2021 8:01:03 AM |
SWMP checklist_V2 | 6/1/2021 8:01:03 AM |
EPC Stormwater Review
5/27/2021 1:23:32 PM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - ESQCP - SWMP - SWMP Checklist EPC Stormwater comments have been resolved on the following documents: - Drainage Report - FAE - GEC Plan - GEC Checklist - PBMP Applicability Form Reviewed by: Glenn Reese, P.E. Stormwater Engineer I glennreese@elpasoco.com |
5/27/2021 1:23:32 PM | |
Cherokee Metro Dist
5/26/2021 10:13:22 AM |
Site Development Plan: Key Note 4 - Grease Interceptor - minimum size 1500 gallons capacity reference CSU standard C4-2 Key Note 7 - Copper not allowed for service line except for meter set inside building. Acceptable material HDPE (blue) or PVC The Brakes Plus development located at 2467 Marksheffel Road is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer. |
5/26/2021 10:13:22 AM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/25/2021 2:16:58 PM |
Hey Sophie, Attached is the review memo for the subject application. The same comment applies, however, it is because of my confusing comment. I apologize to the client and yourself for not making sure the comment made sense. Please let me know if you have any further questions. Thanks, Ryne Solberg rsolberg@csu.org |
5/25/2021 2:16:58 PM |
View |
PCD Project Manager
4/29/2021 3:43:13 PM |
Please see attached PCD comments to GEC plan. | 4/29/2021 3:43:13 PM |
View |
PCD Project Manager
4/29/2021 3:41:00 PM |
Please see attached PCD comments to GEC checklist. | 4/29/2021 3:41:00 PM |
View |
PCD Project Manager
4/29/2021 3:40:12 PM |
Please see attached PCD comments to SWMP Checklist. | 4/29/2021 3:40:12 PM |
View |
PCD Project Manager
4/29/2021 3:39:36 PM |
Please see attached PCD comments to site development plan. Planning comments are in green; engineering comments are in blue. | 4/29/2021 3:39:36 PM |
View |
PCD Project Manager
4/29/2021 3:37:13 PM |
Please see attached PCD comments to sign plan. | 4/29/2021 3:37:13 PM |
View |
PCD Project Manager
4/29/2021 3:36:27 PM |
Please see attached PCD comments to letter of intent. | 4/29/2021 3:36:27 PM |
View |
PCD Project Manager
4/29/2021 3:35:43 PM |
Please see attached PCD comments to landscape plans. | 4/29/2021 3:35:43 PM |
View |
PCD Project Manager
4/29/2021 3:35:08 PM |
Please see attached PCD comments to Financial Assurance Forms. | 4/29/2021 3:35:08 PM |
View |
PCD Project Manager
4/29/2021 3:29:47 PM |
Please see attached PCD comments to drainage report. | 4/29/2021 3:29:47 PM |
PCD Engineering Division
4/28/2021 4:17:10 PM |
Review 1 redline comments on the following documents will be uploaded by the project manager: - Grading & Erosion Control Plans - Site Development Plan - Drainage Letter - Financial Assurance Estimate - Submit the traffic memo with the Traffic Engineer's Statement and Developer's Statement. See the Memo submitted with Claremont Ranch Filing No. 9C for an example (PCD File No. VR1811). Reviewed by: Gilbert LaForce gilbertlaforce@elpasoco.com |
4/28/2021 4:17:10 PM | |
PCD Project Manager
4/19/2021 4:41:23 PM |
Planning comments will be issued pending completion of Engineering review. | 4/19/2021 4:41:23 PM | |
View |
Mountain View Electric Association, Inc.
4/15/2021 5:02:01 PM |
See attached comments | 4/15/2021 5:02:01 PM |
View |
EPC Stormwater Review
4/14/2021 9:10:19 AM |
PBMP Applicability Form_V1 | 4/14/2021 9:10:19 AM |
View |
EPC Stormwater Review
4/14/2021 9:10:04 AM |
GEC Checklist_V1 | 4/14/2021 9:10:04 AM |
View |
Falcon Fire Protection District
4/13/2021 2:11:45 PM |
4/13/2021 2:11:45 PM | |
EPC Stormwater Review
4/14/2021 9:11:04 AM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded by PM with PCD comments) - FAE........................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - PBMP Applicability Form Please complete and upload an ESQCP and SWMP with the next review submittal. Reviewed by: Glenn Reese, P.E. Stormwater Engineer I glennreese@elpasoco.com |
4/14/2021 9:11:04 AM | |
Cherokee Metro Dist
4/12/2021 4:40:33 PM |
The Brakes Plus development is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer. Drawing Comments: Utility Plan Sheet 3 of 10 - Note 4 - Change to Oil Sand Separator, Min. 1,500 Gal., CSU Std. C4-5 - Note 7 - Change from Type K Copper to HDPE DR9 CTS Blue - Note 8 - Locate meter inside building accessible to Cherokee inspector, Install per Cherokee B1-7 (see Cherokee website) Floor Plan Sheet 9 of 11 - show floor drain piping route to sand/oil separator |
4/12/2021 4:40:33 PM | |
Pikes Peak Regional Building Department
4/12/2021 11:52:22 AM |
2467 Marksheffell Road is the address to the Brakes Plus building. What is the height of the proposed trash enclosure? If over 7’ an address and separate permit will be required. No further comment. You are welcome to respond to me directly in an email. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
4/12/2021 11:52:22 AM | |
Central Marksheffel Metro
4/7/2021 11:23:20 AM |
This property is located within the Central Marksheffel Metropolitan District The District assess’ building permit fees for new development in the District, the District also assess’ a mill levy on property within the District Boundaries. The Fees for 2020 are: Building Permit Fees: Commercial: Industrial/ Agricultural - $1.50/ square foot Lodging/ Land - $200/ Room Recreational/ institutional/ medical/ Office/ Retail - $2.00/ square foot Residential: Single Family - $$1,914/ Unit Multi Family - $1,172/ Unit Pronghorn Meadows Filings 2 & 3 - $246.70/ Unit |
4/7/2021 11:23:20 AM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/31/2021 11:45:53 AM |
Hey Sophie, Attached is the review memo for the subject application. CSU has one action item. Let me know if you need anything else from me. Thanks, Ryne Solberg rsolberg@csu.org |
3/31/2021 11:45:53 AM |