Project Review Comments
- Project Name
- Venetucci Farms Business Event Center
- Description
- Special Use request to allow a wedding venue in the A-35 District
- Location
- Parcels
- 6511300008 6511300008
- Applicant
-
N.E.S.
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073 Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073 - EA Number
- EA212
- File Number
- AL2115
- Project Manager
- Ryan Howser
- Status
- Closed
- Created
- 1/20/2021 1:20:20 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
9/19/2022 8:26:11 AM |
Engineer Review Version 4 No further Engineer Comments Traffic Impact Study Ver.4 accepted for file. Thank you Edward Schoenheit, Engineer I E.P.C. Planning & Community Development 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
9/19/2022 8:26:11 AM | |
View |
PCD Project Manager
9/7/2022 2:26:31 PM |
SpecialUseVarianceUse_Markup Please review and clarify item #13 on checklist in regards to wells and septic on the site plan. Please also see comments from Engineering and latest comment letter from CDOT uploaded on 8/31/22. |
9/7/2022 2:26:31 PM |
PCD Engineering Division
9/6/2022 5:05:55 PM |
Engineer Review Version 3 Please complete owner signature on Traffic Impact Study Ver.3 (signature missing) so TIS can be approved and filed. Please contact Engineer Reviewer when the final signed copy has been uploaded. No further engineer comments on Site Plan, TIS or LOI Version 3 submittal. Thank you Edward Schoenheit, Engineer I E.P.C. Planning & Community Development 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
9/6/2022 5:05:55 PM | |
View |
Colorado Department of Transportation - Pueblo Office
8/31/2022 2:29:03 PM |
8/31/2022 2:29:03 PM | |
View |
PCD Project Manager
7/11/2022 11:44:29 AM |
Traffic Impact Study_V2 redlines | 7/11/2022 11:44:29 AM |
View |
PCD Project Manager
7/11/2022 11:44:02 AM |
Site Plan Drawing_V2 redlines | 7/11/2022 11:44:02 AM |
View |
PCD Project Manager
7/11/2022 11:43:27 AM |
LOI_V2 redlines | 7/11/2022 11:43:27 AM |
PCD Engineering Division
6/30/2022 2:41:19 PM |
Engineer Review Version 2 Please address redline comments on the following documents -Traffic Impact Study -Letter of Intent - Road Impact fees are applicable and should be addressed in LOI or TIS. Site Plan was reviewed under PCD File # PPR2153 and comments were addressed. Thank you Edward Schoenheit, Engineer I E.P.C. Planning & Community Development 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
6/30/2022 2:41:19 PM | |
View |
PCD Administrative Notice
6/20/2022 3:17:23 PM |
Neighbor notification letter, mailing labels, and vicinity map | 6/20/2022 3:17:23 PM |
View |
EPC Health Department
12/13/2021 9:41:40 PM |
12/13/2021 9:41:40 PM | |
View |
Colorado Department of Transportation - Pueblo Office
12/2/2021 2:38:20 PM |
12/2/2021 2:38:20 PM | |
PCD Project Manager
11/30/2021 3:50:25 PM |
Redline comments on plan sets from PPR review uploaded for both AL and PPR projects. | 11/30/2021 3:50:25 PM | |
View |
PCD Project Manager
11/30/2021 3:48:52 PM |
Please see redline comments on Traffic Memo | 11/30/2021 3:48:52 PM |
View |
PCD Project Manager
11/30/2021 3:48:21 PM |
Please see redline comments on LOI | 11/30/2021 3:48:21 PM |
View |
PCD Project Manager
11/30/2021 3:49:29 PM |
Please see redline comments on Vicinity Map | 11/30/2021 3:49:29 PM |
View |
PCD Project Manager
11/30/2021 3:41:17 PM |
Please see redline comments on Title Commitment | 11/30/2021 3:41:17 PM |
View |
PCD Project Manager
11/30/2021 3:40:54 PM |
Please see redline comments on Site Development Plan | 11/30/2021 3:40:54 PM |
View |
PCD Project Manager
11/30/2021 3:40:29 PM |
Please see redline comments on sign plan | 11/30/2021 3:40:29 PM |
View |
PCD Project Manager
11/30/2021 3:40:10 PM |
Please see redline comments on Landscape Plans | 11/30/2021 3:40:10 PM |
View |
PCD Project Manager
11/30/2021 3:39:42 PM |
Please see redline comments on floor plans | 11/30/2021 3:39:42 PM |
View |
PCD Project Manager
11/30/2021 3:39:15 PM |
Please see redline comments on application form | 11/30/2021 3:39:15 PM |
Pikes Peak Regional Building Department
11/23/2021 1:40:01 PM |
Enumerations has no comments regarding the special use permit. Please see our comments on the plot plan review entry for more information. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
11/23/2021 1:40:01 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
11/17/2021 1:56:01 PM |
I have no review comments 11/17/2021 AJ | 11/17/2021 1:56:01 PM | |
PCD Engineering Division
11/17/2021 5:18:34 PM |
Review #1: Redline comments on the following documents will be uploaded by the project manager: - Letter of Intent - Traffic Impact Study NOTE: Redline comments to the site development plan set is provided with the site development plan application (PCD File No. PPR-21-053). Thank you Reviewed by: Edward B. Schoenheit Engineer I Reviewer El Paso County Planning & Community Development EdwardSchoenheit@elpasoco.com 719-520-6813 (O) 719-502-9659 (C) |
11/17/2021 5:18:34 PM | |
View |
Widefield SD 3
11/8/2021 12:04:38 PM |
11/8/2021 12:04:38 PM | |
View |
EPC Environmental Services
11/4/2021 2:11:13 PM |
11/4/2021 2:11:13 PM | |
County Attorney - Development Review
11/2/2021 7:43:04 PM |
No comments from County Attorney - Development Review at this time. | 11/2/2021 7:43:04 PM | |
View |
EPC Parks Department
11/2/2021 3:29:48 PM |
See administrative Parks comments attached. Greg |
11/2/2021 3:29:48 PM |
View |
El Paso County Conservation Dist
10/28/2021 8:59:56 AM |
10/28/2021 8:59:56 AM | |
View |
El Paso County Conservation Dist
10/28/2021 8:59:23 AM |
10/28/2021 8:59:23 AM |