Project Review Comments

Back to List


Project Name
Sunset Village, Filing 4 Road Maintenance Phase 1
Description
Location
Parcels
3512102016 3512102016 3512102017 3512102017 3512103017 3512103017 3512103018 3512103018 3512105007 3512105007 3512108007 3512108007 3512108008 3512108008 3512108009 3512108009 3512108010 3512108010 3512108011 3512108011 3512108012 3512108012 3512108013 3512108013 3512108014 3512108014 3512108015 3512108015 3512108016 3512108016 3512108017 3512108017 3512108018 3512108018 3512108019 3512108019 3512108020 3512108020 3512108021 3512108021 3512108022 3512108022 3512108023 3512108023 3512108024 3512108024 3512108025 3512108025 3512108026 3512108026 3512108027 3512108027 3512110001 3512110001 3512110002 3512110002 3512110003 3512110003 3512110004 3512110004 3512110005 3512110005 3512110006 3512110006 3512110007 3512110007 3512110008 3512110008 3512110009 3512110009 3512110010 3512110010 3512110011 3512110011 3512111001 3512111001 3512111002 3512111002 3512111003 3512111003 3512111004 3512111004 3512111005 3512111005 3512111006 3512111006 3512111007 3512111007
Applicant
PunchList Connection
Scott Van Wyhe ( scott@punchlistconnection.com )
(303) 519-5200
Scott Van Wyhe ( scott@punchlistconnection.com )
(303) 519-5200
EA Number
EA20177
File Number
CDR218
Project Manager
Ryan Howser
Status
Closed
Created
12/18/2020 2:30:28 PM

View: Project Documents



Review Comments (42)

Link Agency Comment
View County Attorney - Development Review
3/29/2022 11:28:12 AM
County Attorney's signature on SIA attached. 3/29/2022 11:28:12 AM
PCD Engineering Division
2/24/2022 9:15:52 AM
The approved engineering documents will be uploaded by the project manager.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
2/24/2022 9:15:52 AM
County Attorney - Development Review
2/19/2022 6:40:29 PM
No further comments from County Attorney - Development Review. 2/19/2022 6:40:29 PM
PCD Project Manager
2/18/2022 2:34:26 PM
No comments from Planning Division at this time. 2/18/2022 2:34:26 PM
View County Attorney - Development Review
2/17/2022 3:49:03 PM
Attached is a draft SIA that would cover both Phases of construction. The amounts of the two FAEs need to be filled in, and then they would be attached as Exhibits A-1 and A-2. 2/17/2022 3:49:03 PM
View PCD Engineering Division
2/15/2022 4:50:44 PM
Review #5:
Redline comments to the following document is attached:
* Construction Drawings (see sheets 1 & 18)

Remaining comments are minor. Upload the following document with the owner signature:
- ESQCP

Per ECM 5.9.4 upload the CAD files of the construction drawings and final plat base drawings with the final approval.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
2/15/2022 4:50:44 PM
EPC Stormwater Review
2/16/2022 8:28:34 PM
Review 5: EPC Stormwater comments have been resolved on the following documents:
- CD
- PBMP Applicability Form
- SDI Form

EPC Stormwater has no further comments at this time. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
2/16/2022 8:28:34 PM
View EPC Stormwater Review
2/3/2022 9:10:38 AM
PBMP Applicability Form 2/3/2022 9:10:38 AM
View EPC Stormwater Review
2/3/2022 9:10:25 AM
Construction Drawings 2/3/2022 9:10:25 AM
EPC Stormwater Review
2/3/2022 8:37:22 AM
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CD
- PBMP Applicability Form

Something happened between the V2 and V3 SDI Form such that the V3 one is missing data on the table at the bottom. Please re-upload a complete SDI Form.

EPC Stormwater comments have been resolved on the following documents:
- Drainage Letter
- GEC Checklist
- SWMP
- SWMP Checklist

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
2/3/2022 8:37:22 AM
PCD Project Manager
2/1/2022 4:30:01 PM
It is likely that this is going to be approved with a condition that indicates that the approval only constitutes Phase 1 and the SIA and collateral posted will only reflect Phase 1. We cannot approve construction drawings for improvements that are not collateralized. So please make sure that all documentation reflects Phase 1 only. Please review County Attorney comments and PCD Engineering comments and contact me if you have any questions. We may need to have another meeting to make sure we are all on the same page.

Thanks

Ryan
2/1/2022 4:30:01 PM
View County Attorney - Development Review
2/1/2022 2:35:31 PM
Proposed changes to SIA attached. 2/1/2022 2:35:31 PM
View PCD Engineering Division
1/31/2022 9:19:34 AM
Review #4: Redline comments to the following documents is attached:
* Construction Drawings

Comments resolved on the following:
* Drainage Letter
* Financial Assurance Estimate

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
1/31/2022 9:19:34 AM
PCD Project Manager
1/6/2022 9:18:06 AM
Planning Division does not have comments at this time. Comments have been uploaded by PCD Engineering Division. It is likely that County Attorney comments on the SIA will be forthcoming. 1/6/2022 9:18:06 AM
View PCD Engineering Division
1/3/2022 12:56:58 PM
Review #3: Drainage Letter 1/3/2022 12:56:58 PM
View PCD Engineering Division
1/3/2022 12:56:35 PM
Review #3: Construction Drawings 1/3/2022 12:56:35 PM
View PCD Engineering Division
1/3/2022 12:55:44 PM
Review #3: Financial Assurance Estimate 1/3/2022 12:55:44 PM
View EPC Stormwater Review
12/27/2021 7:02:41 PM
SWMP Checklist 12/27/2021 7:02:41 PM
View EPC Stormwater Review
12/27/2021 7:02:21 PM
SWMP 12/27/2021 7:02:21 PM
View EPC Stormwater Review
12/27/2021 7:02:01 PM
PBMP Applicability Form 12/27/2021 7:02:01 PM
View EPC Stormwater Review
12/27/2021 7:01:46 PM
GEC Checklist 12/27/2021 7:01:46 PM
EPC Stormwater Review
12/27/2021 7:01:22 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CD.........................(to be uploaded by PM with PCD comments)
- Drainage Letter.....(to be uploaded by PM with PCD comments)
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist

EPC Stormwater comments have been resolved on the following documents:
- FAE
- MS4 Post Construction Form

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
12/27/2021 7:01:22 PM
PCD Engineering Division
1/3/2022 12:54:14 PM
Review #3: Redline comments to the following documents will be uploaded as separate comments:
* Financial Assurance Estimate
* Construction Drawings
* Drainage Letter


Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
1/3/2022 12:54:14 PM
View EPC Health Department
12/3/2021 3:59:35 PM
12/3/2021 3:59:35 PM
View PCD Project Manager
11/4/2021 10:47:29 AM
PCD Engineering and EPC Stormwater comments - financial assurance form 11/4/2021 10:47:29 AM
View PCD Project Manager
11/4/2021 10:47:17 AM
PCD Engineering and EPC Stormwater comments - drainage letter 11/4/2021 10:47:17 AM
View PCD Project Manager
11/4/2021 10:47:04 AM
PCD Engineering and EPC Stormwater comments - construction drawings 11/4/2021 10:47:04 AM
Upper Black Squirrel Creek GWMD
11/3/2021 11:08:46 AM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment at a later date if necessary. 11/3/2021 11:08:46 AM
View County Attorney - Development Review
11/2/2021 7:41:14 PM
Comments to the SIA are attached. 11/2/2021 7:41:14 PM
View EPC Stormwater Review
11/2/2021 5:31:25 PM
MS4 Post Construction Form_V2 11/2/2021 5:31:25 PM
View EPC Stormwater Review
11/2/2021 5:31:13 PM
GEC-Checklist 11/2/2021 5:31:13 PM
PCD Engineering Division
11/2/2021 1:33:40 PM
Review #2: Redline comments to the following documents will be uploaded as separate comments:
- Financial Assurance Estimate
- Construction Drawings
- Drainage Letter


Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
11/2/2021 1:33:40 PM
EPC Stormwater Review
11/2/2021 5:30:43 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CD.........................(to be uploaded by PM with PCD comments)
- Drainage Letter...(to be uploaded by PM with PCD comments)
- FAE.......................(to be uploaded by PM with PCD comments)
- GEC Checklist
- MS4 Post Construction Form

Please provide the following documents on resubmittal:
- PBMP Applicability Form --- downloadable from: https://publicworks.elpasoco.com/stormwater/
- Private Detention Basin / Stormwater Quality BMP Maintenance Agreement (provide an updated one, the one from 2002 is outdated).
- SWMP
- SWMP Checklist --- downloadable from: https://publicworks.elpasoco.com/stormwater/

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
11/2/2021 5:30:43 PM
Cherokee Metro Dist
10/21/2021 3:10:44 PM
No comments 10/21/2021 3:10:44 PM
View El Paso County Conservation Dist
10/18/2021 11:35:58 AM
10/18/2021 11:35:58 AM
View El Paso County Conservation Dist
10/18/2021 11:35:43 AM
10/18/2021 11:35:43 AM
Ellicott Fire Protection District
10/13/2021 2:48:52 PM
The Ellicott Fire Department has no objections to these repairs as described. No Review Fee 10/13/2021 2:48:52 PM
PCD Project Manager
8/12/2021 5:14:22 PM
Planning Division does not have any comments at this time. 8/12/2021 5:14:22 PM
View PCD Engineering Division
8/11/2021 10:46:26 AM
Review 1: Construction Drawings 8/11/2021 10:46:26 AM
View PCD Engineering Division
8/11/2021 10:45:59 AM
Review 1: Financial Assurance Estimate 8/11/2021 10:45:59 AM
PCD Engineering Division
8/11/2021 12:53:43 PM
Review 1 redline comments to the following documents will be uploaded as separate comments:
- Financial Assurance Estimate
- Construction Drawings

Per the Early Assistance meeting submit the following documents:
- ESQCP
- Letter of Intent
- Drainage Letter
- Construction drawings for any required retrofit of the pond.
- SDI Worksheet
- MS4 Post Construction Form
- Pond Operations and Maintenance Manual

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
8/11/2021 12:53:43 PM
View County Attorney - Development Review
7/28/2021 1:34:37 PM
Proposed changes to SIA are attached. 7/28/2021 1:34:37 PM