View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
1/10/2021 11:21:03 PM |
Engineering comments have been addressed. No additional comments at this time. Review comments by: Jack Patton jackpatton@elpasoco.com |
1/10/2021 11:21:03 PM | |
PCD Project Manager
1/8/2021 2:57:26 PM |
No Planning comments at this time; previous Planning comments satisfied. Engineering review pending. | 1/8/2021 2:57:26 PM | |
View |
PCD Project Manager
1/5/2021 4:17:16 PM |
Please resubmit attached vicinity map, which I've revised to highlight the subject property more clearly. | 1/5/2021 4:17:16 PM |
View |
PCD Project Manager
1/5/2021 4:16:34 PM |
Please see attached comments to Site Plan drawing. | 1/5/2021 4:16:34 PM |
View |
PCD Project Manager
1/5/2021 4:16:06 PM |
Please see attached comments to Letter of Intent. | 1/5/2021 4:16:06 PM |
PCD Engineering Division
1/5/2021 11:01:32 AM |
-Please add the following lines to the Letter of Intent: "The proposed development will not significantly impact the Average Daily Trips (ADT) to this property." "The proposed development will not adversely impact adjacent and downstream drainage." Review comments provided by: Jack Patton jackpatton@elpasoco.com |
1/5/2021 11:01:32 AM | |
Pikes Peak Regional Building Department
1/5/2021 9:49:40 AM |
Enumerations has no comment. | 1/5/2021 9:49:40 AM | |
View |
Mountain View Electric Association, Inc.
12/23/2020 10:39:16 AM |
12/23/2020 10:39:16 AM |