View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Project Manager
7/19/2021 5:11:31 PM |
Site Plan Drawing_v3 redlines | 7/19/2021 5:11:31 PM |
View |
PCD Project Manager
7/19/2021 5:11:14 PM |
Traffic Memo_v3 redlines | 7/19/2021 5:11:14 PM |
PCD Engineering Division
7/19/2021 5:06:16 PM |
Engineering comments have been resolved on the traffic study. The Traffic Study was signed by Matthew Johnson, Agent under the developer's statement of the signature block. Only an authorized representative may sign for the developer. Either add Matthew Johnson as an authorized representative on the application or have the developer sign the traffic study. Please let the project manager know which direction you choose. Mercedes, a 2-day turnaround is ok for sending the traffic study to the ECM administrator for acceptance. reviewed by: Daniel Torres danieltorres@elpasoco.com |
7/19/2021 5:06:16 PM | |
Mountain View Electric Association, Inc.
7/12/2021 8:06:14 AM |
Mountain View Electric Association has no objections to the current Special Use plan. | 7/12/2021 8:06:14 AM | |
RBD Floodplain
6/28/2021 5:09:29 PM |
lot 4 is not in the SFHA, floodplain has no comment on "special use" | 6/28/2021 5:09:29 PM | |
View |
PCD Project Manager
5/20/2021 4:20:19 PM |
Site Plan Drawing_V2 redlines | 5/20/2021 4:20:19 PM |
View |
PCD Project Manager
5/20/2021 4:19:53 PM |
Traffic Memo_V2 redlines | 5/20/2021 4:19:53 PM |
PCD Engineering Division
5/20/2021 4:11:57 PM |
review 2 comments on the following documents will be uploaded by the project manager: -TIS Provided the comments on the TIS are addressed, a signed (by owner & engineer) may be submitted for approval/acceptance by the ECM administrator reviewed by: Daniel Torres danieltorres@elpasoco.com |
5/20/2021 4:11:57 PM | |
PCD Project Manager
4/26/2021 9:28:15 AM |
Planning staff will issue comments when the engineering staff has finished their review. | 4/26/2021 9:28:15 AM | |
Woodmen Road Metro
4/7/2021 12:10:02 PM |
This property is located within the Woodmen Road Metropolitan District or its service area. The District assess platting and building permit fees for new development in the District and requires developed parcels to be included in the Metro District boundaries through an Inclusion process; the District assess a mill levy on property in the District. The fees for 2020 are: Platting Fees: Commercial- $1540/ACRE Residential- $385.00/LOT Building Permit Fees: Commercial: Destination/hotel- $1.37/SQUARE FOOT Convenience Commercial- $5.51/SQUARE FOOT All Other Uses- $1.10/SQUARE FOOT Residential- Single Family- $550/UNIT Multi Family- $385/UNIT |
4/7/2021 12:10:02 PM | |
View |
PCD Project Manager
4/1/2021 1:21:11 PM |
Letter of Intent | 4/1/2021 1:21:11 PM |
View |
PCD Project Manager
4/1/2021 1:20:41 PM |
Traffic Memo redlines | 4/1/2021 1:20:41 PM |
View |
PCD Project Manager
4/1/2021 1:20:16 PM |
Site Plan Drawing redlines | 4/1/2021 1:20:16 PM |
PCD Engineering Division
3/31/2021 2:00:19 PM |
Review 1 comments on the following documents will be uploaded by the project manager: -Letter of Intent -Traffic Memo -Site Plan reviewed by: Daniel Torres danieltorres@elpasoco.com |
3/31/2021 2:00:19 PM | |
View |
Mountain View Electric Association, Inc.
3/25/2021 4:34:58 PM |
See MVEA Comments | 3/25/2021 4:34:58 PM |
PCD Project Manager
3/22/2021 8:25:22 AM |
Redlines will be uploaded upon completion of the PCD engineering division review. | 3/22/2021 8:25:22 AM | |
Pikes Peak Regional Building Department
3/19/2021 10:22:44 AM |
Enumerations has no comment to the special use permit. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
3/19/2021 10:22:44 AM | |
View |
El Paso County Conservation Dist
3/17/2021 7:35:05 AM |
3/17/2021 7:35:05 AM | |
View |
El Paso County Conservation Dist
3/17/2021 7:32:05 AM |
3/17/2021 7:32:05 AM | |
PCD Administrative Notice
3/11/2021 3:39:29 PM |
Adjacent property notifications have been mailed indicating the anticipated decision date and how to provide comment | 3/11/2021 3:39:29 PM | |
911 Authority - El Paso/Teller County
3/11/2021 10:32:21 AM |
No new street names requested on this submittal. No action for E911. Thank you. Justin |
3/11/2021 10:32:21 AM | |
Woodmen Hills Metro
3/9/2021 2:52:31 PM |
Woodmen Hills Metropolitan District approves the plan as presented. | 3/9/2021 2:52:31 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/4/2021 7:15:50 PM |
Hey Ryan, I am finished with CSU's review for the subject application. CSU has no action items and approval can be recommended. Thanks, Ryne Solberg rsolberg@csu.org |
3/4/2021 7:15:50 PM | |
Upper Black Squirrel Creek GWMD
3/3/2021 2:23:39 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment in the future if needed. | 3/3/2021 2:23:39 PM | |
Falcon Fire Protection District
3/3/2021 1:45:30 PM |
Falcon Fire has reviewed the Discount Tire Store (auto service/repair use) special use request for a SUP within the Commercial Regional (CR) Zone District and has no objections or concerns with the request. Final Development plan review comments will be separate. | 3/3/2021 1:45:30 PM | |
RBD Floodplain
2/26/2021 11:57:09 AM |
site plan indicates this project is on lot 4 which is not in the SFHA , no comment EDARP parcel number on the main project page lists schedule number 5301403002, which is lot 6 and is not correct. |
2/26/2021 11:57:09 AM |