Project Review Comments

Back to List


Project Name
Falcon Family Eye Care - Site Development Plan
Description
Location
Parcels
4306301002 4306301002
Applicant
Bucher Design Studio
Nick Sallecchia ( nick@bucherdesign.com )
(719) 484-0480
Nick Sallecchia ( nick@bucherdesign.com )
(719) 484-0480
File Number
PPR2049
Project Manager
John Green
Status
Closed
Created
11/19/2020 4:18:40 PM

View: Project Documents



Review Comments (41)

Link Agency Comment
View PCD Project Manager
3/25/2021 8:54:39 AM
Please see unresolved comment to FAE review 1 3/25/2021 8:54:39 AM
View PCD Project Manager
3/25/2021 8:51:19 AM
Please see attached comments to GEC plan. 3/25/2021 8:51:19 AM
View PCD Project Manager
3/25/2021 8:51:01 AM
Please see attached comments to ESQCP. 3/25/2021 8:51:01 AM
View PCD Project Manager
3/25/2021 8:50:44 AM
Please see attached comments to drainage letter. 3/25/2021 8:50:44 AM
View PCD Project Manager
3/25/2021 8:50:29 AM
Please see attached comments to application. 3/25/2021 8:50:29 AM
View PCD Project Manager
3/25/2021 8:50:11 AM
Please see attached comments to landscape plan. 3/25/2021 8:50:11 AM
View PCD Project Manager
3/25/2021 8:49:55 AM
Please see attached comments to site development plan. 3/25/2021 8:49:55 AM
PCD Engineering Division
3/24/2021 2:13:38 PM
Review 2 comments will be uploaded by the project manager. The following documents have comments pending:

-Drainage report
-GEC plans
-FAE

Please address unresolved comments.

The following documents have comments that have been resolved:

-Landscape plan
-Site development plan

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
3/24/2021 2:13:38 PM
PCD Project Manager
3/18/2021 8:03:16 AM
Planning comments will be issued pending completion of Engineering review. 3/18/2021 8:03:16 AM
Mountain View Electric Association, Inc.
3/12/2021 1:09:55 PM
This area is within Mountain View Electric Association, Inc. certificated area. The Association will serve this area according to our extension policy. Information concerning connection requirements, fees, and upgrades under the Association’s line extension policy can be obtained by contacting the Association’s Engineering Department. The Association has existing facilities within this parcel of land. Any removal or relocation of facilities will be at the expense of the applicant, and a review of easements will be required. Additional easements may be required once a review of civil drawings with grading and erosion plan is provided to MVEA in order to serve. 3/12/2021 1:09:55 PM
View EPC Stormwater Review
3/8/2021 1:29:10 PM
SWMP checklist_V1 3/8/2021 1:29:10 PM
View EPC Stormwater Review
3/8/2021 1:28:13 PM
Storm Water Management Plan (SWMP)_V2 3/8/2021 1:28:13 PM
View EPC Stormwater Review
3/8/2021 1:27:40 PM
PBMP Applicability Form_V2 3/8/2021 1:27:40 PM
EPC Stormwater Review
3/8/2021 1:26:29 PM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report....(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- PBMP Applicability Form
- SWMP Checklist....(See Review 1 checklist with my comments. The majority of these items remain unresolved, as shown in my comments on the Review 2 SWMP.)
- SWMP.....................(please feel free to give me a call if any of these comments are unclear or disagreeable.)

EPC Stormwater comments have been resolved on the following documents:
- ESQCP
- FAE
- GEC Checklist

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer I
glennreese@elpasoco.com
3/8/2021 1:26:29 PM
Woodmen Hills Metro
2/11/2021 9:24:38 AM
Woodmen Hills Metropolitan District will provide this facility with water and sanitary sewer service. All service taps will be paid before connection to WHMD system. Connections will be as per WHMD specifications and will be inspected by WHMD staff. WHMD approves this project. 2/11/2021 9:24:38 AM
View El Paso County Conservation Dist
2/1/2021 7:37:42 AM
2/1/2021 7:37:42 AM
View El Paso County Conservation Dist
2/1/2021 7:37:12 AM
2/1/2021 7:37:12 AM
View PCD Project Manager
1/28/2021 12:31:20 PM
Please see attached Planning & Engineering comments to Financial Assurance forms. 1/28/2021 12:31:20 PM
View PCD Project Manager
1/28/2021 12:30:57 PM
Please see attached Planning & Engineering comments to landscape plan. 1/28/2021 12:30:57 PM
View PCD Project Manager
1/28/2021 12:30:31 PM
Please see attached Planning & Engineering comments to GEC plan. 1/28/2021 12:30:31 PM
View PCD Project Manager
1/28/2021 12:29:48 PM
Please see attached Planning & Engineering comments to drainage letter. 1/28/2021 12:29:48 PM
View PCD Project Manager
1/28/2021 12:29:26 PM
Please see attached Planning & Engineering comments to vicinity map. 1/28/2021 12:29:26 PM
View PCD Project Manager
1/28/2021 12:29:03 PM
Please see attached Planning & Engineering comments to site development plan. 1/28/2021 12:29:03 PM
View PCD Project Manager
1/28/2021 12:27:55 PM
Please see attached Planning & Engineering comments to Lighting Plan. 1/28/2021 12:27:55 PM
View PCD Project Manager
1/28/2021 12:27:29 PM
Please see attached Planning & Engineering comments to Letter of Intent. 1/28/2021 12:27:29 PM
View PCD Project Manager
1/28/2021 12:27:12 PM
Please see attached Planning & Engineering comments to legal description. 1/28/2021 12:27:12 PM
View PCD Project Manager
1/28/2021 12:26:38 PM
Please see attached Planning & Engineering comments to application form. 1/28/2021 12:26:38 PM
EPC Stormwater Review
1/27/2021 10:31:24 AM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report
- ESQCP
- FAE
- GEC Plan
- GEC Checklist
- PBMP Applicability Form
- SWMP Checklist
- SWMP

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer I
glennreese@elpasoco.com
1/27/2021 10:31:24 AM
View EPC Stormwater Review
1/27/2021 10:29:57 AM
SWMP Checklist_V1 1/27/2021 10:29:57 AM
View EPC Stormwater Review
1/27/2021 10:29:42 AM
Storm Water Management Plan_V1 1/27/2021 10:29:42 AM
View EPC Stormwater Review
1/27/2021 10:28:28 AM
PBMP Applicability Form_V1 1/27/2021 10:28:28 AM
View EPC Stormwater Review
1/27/2021 10:28:08 AM
Grading and Erosion Control Checklist_V1 1/27/2021 10:28:08 AM
View EPC Stormwater Review
1/27/2021 5:23:00 PM
Grading & Erosion Control Plan_V1 1/27/2021 5:23:00 PM
View EPC Stormwater Review
1/27/2021 10:27:28 AM
Financial Assurance Forms_V1 1/27/2021 10:27:28 AM
View EPC Stormwater Review
1/27/2021 10:27:11 AM
Erosion and Stormwater Quality Control Permit (ESQCP)_V1 1/27/2021 10:27:11 AM
View EPC Stormwater Review
1/27/2021 5:23:35 PM
Drainage Letter_V1 1/27/2021 5:23:35 PM
Pikes Peak Regional Building Department
1/20/2021 2:01:14 PM
Regarding a request for approval of a site development plan for Falcon Family Eye Care, Enumerations has the following comments:

1. The letter of intent does not indicate if this will be a single tenant or multi-tenant building. If this is a multi-tenant building, then any building plans submitted for review/permit should include secondary addressing for the tenant spaces which follows the secondary addressing guide available on the RBD website.


Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
1/20/2021 2:01:14 PM
View Falcon Fire Protection District
1/18/2021 11:00:21 AM
1/18/2021 11:00:21 AM
PCD Engineering Division
1/26/2021 1:57:06 PM
Review 1 comments on the following documents will be uploaded by the project manager:

-Site Development Plan
-Grading and Erosion Control Plan
-Drainage Letter
-Financial Assurance Estimate
-Landscape Plan

The following documents were not reviewed by PCD Engineering: (Review comments will be provided by the Stormwater Team if applicable)
- GEC & SWMP Checklist
- SWMP

Due to this project being reviewed concurrently with McLaughlin Road Plat Amendment (PCD File No. SF2022), changes to replat project may trigger additional comments to the site development plan (PCD File No. PPR-2049). The Plat Amendment must be approved before the site development plan is approved.

Reviewed by:
Lupe Packman
Engineer I
lupepackman@elpasoco.com
1/26/2021 1:57:06 PM
Upper Black Squirrel Creek GWMD
1/6/2021 11:37:15 AM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment in the future if needed. 1/6/2021 11:37:15 AM
View Mountain View Electric Association, Inc.
12/30/2020 1:59:28 PM
12/30/2020 1:59:28 PM