Project Review Comments
- Project Name
- Red Rock Acres Rezone
- Description
- Rezone RR-0.5
- Location
- Parcels
- 7109000024 7109000024 7109014003 7109014003
- Applicant
-
Olive Real Estate Group, Inc.
Ingrid Richter ( ingridrichter@olivereg.com )
(719) 598-3000 Ingrid Richter ( ingridrichter@olivereg.com )
(719) 598-3000 - File Number
- P2010
- Project Manager
- John Green
- Status
- Closed
- Created
- 11/9/2020 1:51:10 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
8/31/2021 4:43:40 PM |
No additional engineering comments. The traffic study will be uploaded once accepted by the ECM administrator. reviewed by: Daniel Torres danieltorres@elpasoco.com |
8/31/2021 4:43:40 PM | |
PCD Project Manager
8/30/2021 8:39:45 AM |
No Planning Comments | 8/30/2021 8:39:45 AM | |
View |
Colorado Department of Transportation - Pueblo Office
7/29/2021 3:02:53 PM |
7/29/2021 3:02:53 PM | |
Colorado Department of Transportation - Pueblo Office
7/20/2021 11:32:32 AM |
CDOT planning comments are forthcoming. Arthur Gonzales - Access Manager | 7/20/2021 11:32:32 AM | |
PCD Project Manager
6/23/2021 8:09:19 AM |
No additional planning comments. Due to outstanding CDOT review, item will be placed on the Planning Commission agenda for August 5th. | 6/23/2021 8:09:19 AM | |
PCD Engineering Division
6/22/2021 5:33:41 PM |
PCD Engineering comments have been resolved. Please coordinate with CDOT and address any remaining comments. Once comments have been resolved, please submit with signatures for approval. reviewed by: Daniel Torres danieltorres@elpasoco.com |
6/22/2021 5:33:41 PM | |
View |
EPC Environmental Services
6/3/2021 10:12:40 AM |
6/3/2021 10:12:40 AM | |
View |
Colorado Department of Transportation - Pueblo Office
5/18/2021 1:34:27 PM |
5/18/2021 1:34:27 PM | |
View |
PCD Project Manager
5/13/2021 1:27:49 PM |
Please see redline comments on TIS | 5/13/2021 1:27:49 PM |
View |
PCD Project Manager
5/13/2021 1:27:26 PM |
Please see redline comments on LoI | 5/13/2021 1:27:26 PM |
PCD Engineering Division
5/12/2021 8:05:11 AM |
Review 2 comments on the following documents will be uploaded by the project manager: -Letter of Intent -TIS The deviation requests have been provided to the ECM administrator for review and a decision. The deviation requests would not be a part of this rezone as the actual design layout for the proposed access points is not submitted at this stage and so that a decision on the deviation does not hold up the rezone application. You will be informed once a decision has been made. reviewed by: Daniel Torres danieltorres@elpasoco.com |
5/12/2021 8:05:11 AM | |
Mountain View Electric Association, Inc.
4/22/2021 12:30:30 PM |
This site is not within MVEA's service area boundaries. | 4/22/2021 12:30:30 PM | |
County Attorney - Development Review
4/14/2021 10:40:39 PM |
No comments from County Attorney - Development Review at this time. | 4/14/2021 10:40:39 PM | |
Colorado Department of Transportation - Pueblo Office
4/13/2021 8:50:28 AM |
CDOT staff comments will be forthcoming. - Arthur Gonzales | 4/13/2021 8:50:28 AM | |
View |
PCD Project Manager
2/10/2021 4:28:32 PM |
Please see comments from TOWN OF PALMER LAKE | 2/10/2021 4:28:32 PM |
View |
PCD Project Manager
2/10/2021 4:28:01 PM |
Please see Redline comments for Traffic Impact Study | 2/10/2021 4:28:01 PM |
PCD Engineering Division
2/9/2021 5:01:47 PM |
Review 1 comments on the following documents will be uploaded by the project manager: -Traffic Study -Letter of intent reviewed by: Daniel Torres danieltorres@elpasoco.com |
2/9/2021 5:01:47 PM | |
View |
Colorado Department of Transportation - Pueblo Office
2/5/2021 11:12:39 AM |
2/5/2021 11:12:39 AM | |
View |
El Paso County Conservation Dist
2/1/2021 7:39:29 AM |
2/1/2021 7:39:29 AM | |
View |
EPC Parks Department
1/28/2021 7:20:42 AM |
See attached final administrative comments on behalf of El Paso County Parks | 1/28/2021 7:20:42 AM |
View |
PCD Project Manager
2/10/2021 4:27:31 PM |
Please see Redline comments for Letter of intent | 2/10/2021 4:27:31 PM |
Mountain View Electric Association, Inc.
1/25/2021 5:33:10 PM |
This site is not within MVEA's service area boundaries. | 1/25/2021 5:33:10 PM | |
Pikes Peak Regional Building Department
1/25/2021 4:03:11 PM |
No comments at this time. Becky Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org |
1/25/2021 4:03:11 PM | |
View |
Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
1/25/2021 12:09:50 PM |
Please see Red Rock Acres Rezone comments attached. | 1/25/2021 12:09:50 PM |
Colorado Department of Transportation - Pueblo Office
1/22/2021 11:54:54 AM |
Comments will be forthcoming. | 1/22/2021 11:54:54 AM | |
View |
Tri-Lakes-Monument Fire Protection District
1/20/2021 2:25:54 PM |
Attached. JCB | 1/20/2021 2:25:54 PM |
View |
EPC Environmental Services
1/7/2021 1:51:14 PM |
1/7/2021 1:51:14 PM | |
County Attorney - Development Review
1/6/2021 2:40:51 PM |
No comments at this time. | 1/6/2021 2:40:51 PM | |
Lewis Palmer 38
1/5/2021 11:11:00 AM |
Lewis-Palmer School District 38 has previously requested cash in-lieu-of land funding for any residential lots developed in this area. | 1/5/2021 11:11:00 AM |