Project Review Comments

Back to List


Project Name
UPS Distribution Center Filing No. 1 - Monument
Description
Final PD Site Plan CDR 2021, May 4 in for review
Location
Parcels
7135000020 7135000020
Applicant
Town of Monument
Planner II Debbie Flynn ( dflynn@tomgov.org )
(719) 488-1604
Planner II Debbie Flynn ( dflynn@tomgov.org )
(719) 488-1604
File Number
OAR2053
Project Manager
Kari Parsons
Status
Closed
Created
9/25/2020 3:34:10 PM

View: Project Documents



Review Comments (3)

Link Agency Comment
PCD Project Manager
5/18/2021 4:01:02 PM
Dear Ms. Flynn,
The County Engineer and County Attorney’s Office are in the process of completing an IGA with the Town of Monument to annex Baptist Road from I-25 through the round-a-bout , and the southern portion of Woodcarver Road. Until that occurs, the County's criteria (ECM & DCM) are applicable and an access permit would be required to access a County Roadway. A deviation for access spacing would also be required.
5/18/2021 4:01:02 PM
PCD Project Manager
10/21/2020 7:47:47 AM
Planning has no comments at this time. 10/21/2020 7:47:47 AM
PCD Engineering Division
10/20/2020 9:36:34 AM
Review 1:
1. No drainage comments. Runoff is conveyed into the offsite FSD pond constructed with the overall Falcon Commerce Center. The offsite FSD pond is designed to over detain to maintain a developed flow that is equal to or less than existing condition.
2. No transportation comments. It is staff's understanding that an IGA with the Town of Monument is being drafted to include annexation of Woodcarver Road, and a portion of Baptist Road for the overall Falcon Commerce Center.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
10/20/2020 9:36:34 AM