View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
3/16/2021 7:24:38 AM |
There are no further engineering comments. Approved documents will be uploaded by the project manager. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
3/16/2021 7:24:38 AM | |
PCD Project Manager
3/1/2021 9:50:59 AM |
All comments have been satisfied. Please upload requested engineering items. | 3/1/2021 9:50:59 AM | |
View |
PCD Project Manager
2/19/2021 4:31:07 PM |
Please see attached landscape drawings comments. | 2/19/2021 4:31:07 PM |
PCD Engineering Division
2/9/2021 4:17:27 PM |
All engineering comments have been resolved. Please upload the documents listed below with their appropriate signatures/stamps for approval. -Drainage Letter -Utility and GEC plans (provide the wet stamp on all plan sheets.) This project was reviewed by: Lupe Packman Review Engineer 1 lupepackman@elpasoco.com |
2/9/2021 4:17:27 PM | |
View |
PCD Project Manager
2/1/2021 3:16:27 PM |
Please see attached Planning comments to Lighting Plan. | 2/1/2021 3:16:27 PM |
View |
PCD Project Manager
2/1/2021 3:15:23 PM |
Please see attached Planning comments to Landscape Plan. | 2/1/2021 3:15:23 PM |
View |
PCD Project Manager
2/1/2021 3:14:49 PM |
Please see attached Planning comments to Site Development Plan. | 2/1/2021 3:14:49 PM |
PCD Engineering Division
1/25/2021 4:37:10 PM |
All PDC Engineering comments have been resolved. Please upload engineering documents with the appropriate signatures/stamps for approval. Reviewed by: Lupe Packman Review Engineer 1 lupepackman@elpasoco.com |
1/25/2021 4:37:10 PM | |
Woodmen Hills Metro
12/9/2020 8:10:22 AM |
Woodmen Hills is pleased to see this project moving forward. | 12/9/2020 8:10:22 AM | |
View |
PCD Project Manager
11/24/2020 8:12:25 AM |
Please see attached PCD comments to Lighting Plan. | 11/24/2020 8:12:25 AM |
View |
PCD Project Manager
11/24/2020 8:11:49 AM |
Please see attached PCD comments to Letter of Intent. | 11/24/2020 8:11:49 AM |
View |
PCD Project Manager
11/24/2020 8:10:41 AM |
Please see attached PCD comments to Landscape Plan. | 11/24/2020 8:10:41 AM |
View |
PCD Project Manager
11/24/2020 8:09:48 AM |
Please see attached PCD comments to Site Development Plan. | 11/24/2020 8:09:48 AM |
View |
PCD Project Manager
11/24/2020 8:09:24 AM |
Please see attached PCD comments to Drainage Letter. | 11/24/2020 8:09:24 AM |
Falcon Fire Protection District
11/23/2020 10:11:17 AM |
Falcon Fire has reviewed this proposed site plan for the Woodmen Hills Recreation Expansion and has no objections to the proposed site plan. Construction Drawings will be reviewed and used for hydrant requirements and location. If additional hydrants are required we will work directly with the builder and owners as needed. Emergency Access is required that allows a maximum hose lay of 150' from stopping point of fire engine to all exterior portions of building. Falcon Fire has waived Development Plan Review Fees for this project. |
11/23/2020 10:11:17 AM | |
PCD Engineering Division
11/5/2020 4:49:33 PM |
Review 1 Redline comments on the following documents will be uploaded by the project manager. - Drainage letter v_1 (comments are minor, address and submit with final signatures for approval.) - Landscape plan drawings v_1 Reviewed by: Lupe Packman, E.I. Engineer I El Paso County Planning and Community Development 2880 International Circle, Suite 110 Colorado Springs, CO 80910 Direct: (719) 520-7550 Cell: (719) 313-6215 |
11/5/2020 4:49:33 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
11/4/2020 6:09:40 PM |
No apparent conflicts - recommend approval. -Kyle Schelhaas, 719-668-8126, kschelhaas@csu.org |
11/4/2020 6:09:40 PM | |
Upper Black Squirrel Creek GWMD
11/4/2020 2:33:07 PM |
The Upper Black Squirrel Creek GWMD does not have any issues with this application. | 11/4/2020 2:33:07 PM | |
Meadow Lake Airport Association
11/2/2020 7:13:56 PM |
MLAA has no objection to the location and elevations as proposed | 11/2/2020 7:13:56 PM |