Project Review Comments

Back to List


Project Name
Front Range Midway Solar Amended 1041
Description
A request to develop a 100.2MW Solar energy Facility adjacent to two(2) existing sub-stations, utilizing existing transmission lines. Major Amendment. Extension granted for 3 years 2/15/23
Location
Parcels
5717007004 5717007004 5717007005 5717007005 5717007006 5717007006 5717007019 5717007019 5717007047 5717007047 5717007052 5717007052 5717008024 5717008024 5720000003 5720000003 5720000010 5720000010 5720007004 5720007004 5721001008 5721001008 5721001010 5721001010 5721001015 5721001015 5721001019 5721001019 5722001002 5722001002
Applicant
Core Consultants Inc.
jennifer kraus ( kraus@corecivil.com )
(720) 724-3531
jennifer kraus ( kraus@corecivil.com )
(720) 724-3531
EA Number
17-46
File Number
AASI202
Project Manager
Kari Parsons
Status
Closed
Created
9/3/2020 1:09:03 PM

View: Project Documents



Review Comments (17)

Link Agency Comment
PCD Project Manager
1/20/2021 4:18:11 PM
Permit Pending Director approval. A site development plan request to submit has been sent via EDARP. 1/20/2021 4:18:11 PM
EPC County Attorney's Office
1/8/2021 1:48:42 PM
No comments at this time. 1/8/2021 1:48:42 PM
View PCD Project Manager
12/22/2020 5:03:05 PM
Exhibit B summary 12/22/2020 5:03:05 PM
View PCD Project Manager
12/22/2020 5:02:43 PM
Exhibit B comments 12/22/2020 5:02:43 PM
View PCD Project Manager
12/22/2020 5:02:18 PM
Comments addressing 1041 Sections 2.303 & 5.201 12/22/2020 5:02:18 PM
View Colorado Department of Transportation - Pueblo Office
12/22/2020 12:02:37 PM
12/22/2020 12:02:37 PM
PCD Engineering Division
12/18/2020 3:19:42 PM
No engineering comments. Please note that a detailed review of the final drainage report, GEC plan, SWMP, etc. will be conducted at the site development plan stage

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
12/18/2020 3:19:42 PM
View EPC Health Department
12/13/2020 1:18:14 PM
12/13/2020 1:18:14 PM
Pikes Peak Regional Building Department
12/9/2020 9:08:06 AM
Regarding a request for approval of an amended development plan for the Front Range/Midway solar project, Enumerations has the following comments:

1. This project references numerous new buildings to be constructed. The applicant should contact Enumerations prior to submitting building plans for permit in order to establish an address to be used when submitting building plans.


Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
12/9/2020 9:08:06 AM
View EPC Parks Department
12/2/2020 2:57:38 PM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (Administrative Comments Only) 12/2/2020 2:57:38 PM
View EPC Environmental Services
12/2/2020 10:28:50 AM
12/2/2020 10:28:50 AM
View Colorado Department of Public Health and Environment
11/30/2020 4:05:23 PM
11/30/2020 4:05:23 PM
Colorado State Forest Service
11/30/2020 10:08:51 AM
The primary wildland fuel type for this proposal is grassland with scattered trees having a low wildfire hazard potential. No special fire mitigation plans or other actions are necessary for final approval by the Colorado State Forest Service. 11/30/2020 10:08:51 AM
County Attorney - 1041
11/25/2020 10:59:44 AM
This appears to be a duplicate submittal on EDARP. 11/25/2020 10:59:44 AM
911 Authority - El Paso/Teller County
11/24/2020 7:47:15 AM
No new street names requested.
No action for E911.
Thank you.
Justin
11/24/2020 7:47:15 AM
View Colorado Department of Public Health and Environment
11/23/2020 3:59:16 PM
11/23/2020 3:59:16 PM
Hanover Fire Protection District
11/19/2020 8:21:35 AM
Hanover FD has no issues with the recommended changes. 11/19/2020 8:21:35 AM