View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
7/10/2020 9:31:33 AM |
Call Rad Dickson at 719-520-6447. Not all adjacent homes are owned by Richmond Homes as depicted in the documents. we need owner signatures for the homes owned by SWV 85 LLC and any other owners. Because all of the adjacent homes are not owned by the applicant we will need to mail out a notice and post a two week objection time frame so that adjacent owners and their opinions may be heard. | 7/10/2020 9:31:33 AM | |
Pikes Peak Regional Building Department
7/7/2020 2:11:47 PM |
No comment | 7/7/2020 2:11:47 PM | |
View |
PCD Project Manager
6/15/2020 1:46:01 PM |
Vicinity Location Map V1 Redlines | 6/15/2020 1:46:01 PM |
View |
PCD Project Manager
6/15/2020 1:45:47 PM |
Letter of Intent V1 Redlines | 6/15/2020 1:45:47 PM |
View |
PCD Project Manager
6/15/2020 1:45:31 PM |
Application Petition Form V1 Redlines | 6/15/2020 1:45:31 PM |
View |
PCD Project Manager
6/15/2020 1:45:15 PM |
Adjacent Property Owner Notification V1 Redlines | 6/15/2020 1:45:15 PM |
Pikes Peak Regional Building Department
6/11/2020 3:52:59 PM |
Enumerations has no comment. | 6/11/2020 3:52:59 PM | |
PCD Engineering Division
6/10/2020 2:27:25 PM |
Review I Comments: No engineering comments at this time. Reviewed by: Jack Patton jackpatton@elpasoco.com |
6/10/2020 2:27:25 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
6/4/2020 4:41:09 PM |
Hey Rad, I have finished with CSU's review for the subject application. There are no action items and approval is recommended. Let me know if you need anything further from me. Thanks, Ryne |
6/4/2020 4:41:09 PM |