View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
1/4/2021 4:30:01 PM |
The revised CDs have been saved for approval and will be uploaded when signed. -- Jeff Rice - 719-520-7877 |
1/4/2021 4:30:01 PM | |
View |
PCD Engineering Division
12/16/2020 4:00:56 PM |
(deviation request redlines) | 12/16/2020 4:00:56 PM |
View |
PCD Engineering Division
12/16/2020 4:00:29 PM |
See comment letter and deviation request redlines. | 12/16/2020 4:00:29 PM |
PCD Project Manager
12/16/2020 2:49:31 PM |
Please provide ramps where trail in power line easement crosses two collectors for efficient and safe pedestrian access. | 12/16/2020 2:49:31 PM | |
View |
PCD Engineering Division
11/13/2020 5:47:30 PM |
See comment letter (no redlines provided). Provide signed CDs and revised and signed FAE. | 11/13/2020 5:47:30 PM |
PCD Project Manager
11/4/2020 2:38:33 PM |
These Plans must be approved 100 percent by November 30th to make BoCC Dec 8th. | 11/4/2020 2:38:33 PM | |
PCD Engineering Division
8/26/2020 12:15:25 PM |
Note: the LOI submitted was for the EGP; please resubmit if it has been revised since the first submittal. | 8/26/2020 12:15:25 PM | |
View |
PCD Engineering Division
8/26/2020 12:14:37 PM |
(FAE redlines) | 8/26/2020 12:14:37 PM |
View |
PCD Engineering Division
8/26/2020 12:14:10 PM |
(CD redlines summary) | 8/26/2020 12:14:10 PM |
View |
PCD Engineering Division
8/26/2020 12:13:44 PM |
(CD redlines) | 8/26/2020 12:13:44 PM |
View |
PCD Engineering Division
8/26/2020 12:13:10 PM |
See comment letter and redlines. | 8/26/2020 12:13:10 PM |
EPC Stormwater Review
8/19/2020 7:44:51 AM |
All Stormwater comments have been resolved. | 8/19/2020 7:44:51 AM | |
View |
PCD Engineering Division
7/23/2020 5:01:45 PM |
(CD redlines summary) | 7/23/2020 5:01:45 PM |
View |
PCD Engineering Division
7/23/2020 5:01:06 PM |
(CD redlines) | 7/23/2020 5:01:06 PM |
View |
PCD Engineering Division
7/23/2020 4:59:48 PM |
See comment letter and CD redlines. | 7/23/2020 4:59:48 PM |
PCD Project Manager
7/17/2020 8:42:12 AM |
Engineering staff will provide review comments for the CDR. Please add the request to construct all items in the CDR to the LOI for the PUDSP. Justify why you need additional approvals beyond pre-site development grading. | 7/17/2020 8:42:12 AM | |
EPC Stormwater Review
7/8/2020 1:50:33 PM |
Review 1: See Stormwater comments on Hills at Lorson Ranch project number PUDSP-20-003 Reviewed by: Christina Furchak Stormwater Engineer III christinafurchak@elpasoco.com |
7/8/2020 1:50:33 PM | |
View |
Mountain View Electric Association, Inc.
6/18/2020 3:02:29 PM |
6/18/2020 3:02:29 PM |