Project Review Comments

Back to List


Project Name
Claremont Business Park 2 Filing 1, Lot 7
Description
Location
Parcels
5408101054 5408101054
Applicant
Hammers Construction
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
EA Number
EA19107
File Number
PPR2030
Project Manager
John Green
Status
Closed
Created
2/23/2020 5:51:50 PM

View: Project Documents



Review Comments (40)

Link Agency Comment
View EPC Code Enforcement Inspections
10/4/2021 4:26:59 PM
Pictures taken on 10/4/21. 10/4/2021 4:26:59 PM
EPC Code Enforcement Inspections
10/4/2021 4:21:27 PM
No concerns noted by Code Enforcement. 10/4/2021 4:21:27 PM
PCD Project Manager
4/4/2021 3:10:56 PM
Pending Attorney Review 4/4/2021 3:10:56 PM
PCD Engineering Division
3/31/2021 10:14:20 AM
The engineering documents have been approved by the ECM administrator. The project manager will upload the approved documents onto EDARP.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
3/31/2021 10:14:20 AM
View PCD Project Manager
3/9/2021 11:04:33 AM
Please see redline comments on Site Development Plan 3/9/2021 11:04:33 AM
View PCD Project Manager
3/9/2021 11:03:53 AM
Please see redline comments on Drainage Report 3/9/2021 11:03:53 AM
PCD Engineering Division
3/5/2021 10:38:40 PM
Review 3 comments on the following documents will be uploaded by the project manager:
-Drainage letter
-Site Development Plan

John: a short turnaround is ok in regards to the minor engineering comments i had.

reviewed by:
DanielTorres
danieltorres@elpasoco.com
3/5/2021 10:38:40 PM
County Attorney - Development Review
2/24/2021 2:59:20 PM
No further changes to Detention Maintenance Agreement. 2/24/2021 2:59:20 PM
County Attorney - Development Review
1/7/2021 2:57:00 PM
Comments from Oct. 26 have not been addressed. 1/7/2021 2:57:00 PM
View PCD Project Manager
1/5/2021 9:46:11 PM
Please see redline comments for Grading and Erosion Control Plan 1/5/2021 9:46:11 PM
View PCD Project Manager
1/5/2021 9:45:32 PM
Please see redline comments for Drainage Report 1/5/2021 9:45:32 PM
View PCD Project Manager
1/5/2021 9:44:53 PM
Please see redline comments for Site Development Plan 1/5/2021 9:44:53 PM
Cherokee Metro Dist
1/5/2021 12:28:01 PM
Claremont Business Park 2 Filing 1, Lot 7 is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer.

Drawing comments:

Utility Plan Sheet 1 of 2: Cherokee standard for minimum depth of sanitary sewer is 5' to the top of pipe.
1/5/2021 12:28:01 PM
PCD Engineering Division
1/4/2021 4:13:19 PM
Review comments provided by:
Jack Patton
jackpatton@elpasoco.com

Approval of this submittal is pending the approval of SF2014 - Claremont Business Park Filing 2 Final Plat.

Review 1 comments on the following documents were resolved:
- Site Development Plan
- Minor Comments: FAE, GEC, Landscape Plan

Review 2 comments on the following documents will be uploaded by the project manager:
-Final Drainage Letter

Note: PCD Engineering reserves the right to make comments on the GEC until the Final Drainage Letter comments are addressed.
1/4/2021 4:13:19 PM
Colorado Springs Airport Advisory Commission
1/4/2021 11:32:45 AM
Airport staff has no additional comments beyond those previously provided. 1/4/2021 11:32:45 AM
Pikes Peak Regional Building Department
12/29/2020 3:47:05 PM
No further comments

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org
12/29/2020 3:47:05 PM
EPC Stormwater Review
12/29/2020 8:18:43 AM
Review 2: EPC Stormwater comments have been resolved on the following documents:
- GEC Checklist
- GEC Plan
- SWMP
- SWMP Checklist

EPC Stormwater does not have any additional comments on any of the uploaded documents at this time.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer I
glennreese@elpasoco.com
12/29/2020 8:18:43 AM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
12/15/2020 3:45:02 PM
Hey John,

I have finished with the review for CSU and there are no action items, approval can be recommended. Let me know if you have any questions moving forward.

Thanks,

Ryne
rsolberg@csu.org
12/15/2020 3:45:02 PM
View EPC Health Department
11/15/2020 4:56:20 PM
11/15/2020 4:56:20 PM
View Cherokee Metro Dist
10/27/2020 3:47:15 PM
10/27/2020 3:47:15 PM
View County Attorney - Development Review
10/26/2020 2:29:03 PM
Proposed changes to the Detention Maintenance Agreement are attached. 10/26/2020 2:29:03 PM
View PCD Project Manager
10/19/2020 9:13:21 AM
Please see redline comments 10/19/2020 9:13:21 AM
View PCD Project Manager
10/19/2020 9:12:50 AM
Please see redline comments 10/19/2020 9:12:50 AM
View PCD Project Manager
10/19/2020 9:12:32 AM
Please see redline comments 10/19/2020 9:12:32 AM
View PCD Project Manager
10/19/2020 9:12:16 AM
Please see redline comments 10/19/2020 9:12:16 AM
View PCD Project Manager
10/19/2020 9:11:57 AM
Please see redline comments 10/19/2020 9:11:57 AM
View PCD Project Manager
10/19/2020 9:11:42 AM
Please see redline comments 10/19/2020 9:11:42 AM
View PCD Project Manager
10/19/2020 9:11:11 AM
Please see redline comments 10/19/2020 9:11:11 AM
View PCD Project Manager
10/19/2020 9:10:47 AM
Please see redline comments 10/19/2020 9:10:47 AM
View Colorado Springs Airport Advisory Commission
10/15/2020 10:13:01 AM
The attached land use summary with comments will be presented at the October 28, 2020 Airport Advisory Commission meeting. 10/15/2020 10:13:01 AM
County Attorney - Development Review
10/14/2020 8:29:41 PM
It looks like this submittal includes a Detention Maintenance Agreement that was not included in the agency referral. Please make sure to include and re-refer. 10/14/2020 8:29:41 PM
Colorado Springs Public Works
10/14/2020 3:32:18 PM
Traffic Engineering has no comments on this item.

Zaker Alazzeh, P.E.
Traffic Engineering Manager
City of Colorado Springs
(719) 385-5468
Zaker.Alazzeh@coloradosprings.gov
10/14/2020 3:32:18 PM
Pikes Peak Regional Building Department
10/14/2020 3:12:09 PM
1. The address of 7716 Gary Watson Pt. has been preliminarily assigned to this lot as part of the Claremont Commercial Fil. No. 2 final plat. If the configuration of this plat changes before it is recorded, this address may change.
2. Enumerations will not sign off on any buildings plans submitted for review/permit without a copy of the final recorded plat in our records.
10/14/2020 3:12:09 PM
View EPC Stormwater Review
10/14/2020 12:00:18 PM
SWMP checklist_V1 10/14/2020 12:00:18 PM
View EPC Stormwater Review
10/14/2020 11:59:56 AM
Storm Water Management Plan (SWMP)_V1 10/14/2020 11:59:56 AM
View EPC Stormwater Review
10/14/2020 11:59:03 AM
Grading & Erosion Control checklist_V1 10/14/2020 11:59:03 AM
EPC Stormwater Review
10/14/2020 12:01:21 PM
Review 1: EPC Stormwater comments have been provided on the following uploaded documents:
- GEC Checklist
- GEC Plan...............(to be uploaded by PM with PCD comments)
- SWMP
- SWMP Checklist

Notes:
1) GEC Checklist and SWMP Checklist comments are the same as those submitted for PPR2031.
2) PBMP Form and Detention Maintenance Agreement for the access easement (through Lot 7) and two ponds (not on Lot 7) were completed with SF2014 and therefore are not needed for this Lot 7 submittal. Please do not resubmit these two documents.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer I
glennreese@elpasoco.com
10/14/2020 12:01:21 PM
Colorado Springs Public Works
10/14/2020 6:58:47 AM
Engineering Development Review has no comments.
Patrick V. Morris
Civil Engineer II
Public Works/Engineering Development Review
City of Colorado Springs
30 S. Nevada Ave., Suite 401
Colorado Springs, CO 80903
tel: 719-385-5075
Main: 719-385-5979
patrick.morris@coloradosprings.gov
10/14/2020 6:58:47 AM
PCD Engineering Division
10/15/2020 1:22:20 PM
Review comments provided by:
Jack Patton
jackpatton@elpasoco.com
(719) 505-0236

Approval of this submittal is pending the approval of SF2014 - Claremont Business Park Filing 2 Final Plat.

Review 1 comments on the following documents will be uploaded by the project manager:
- Drainage Report
- Site Development Plan
- Minor Comments: FAE, GEC, Landscape Plan

Note: PCD Engineering reserves the right to make comments on the GEC until the FDR comments have been addressed, and a site specific plan is submitted within the FDR.
10/15/2020 1:22:20 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/29/2020 1:13:43 PM
Hey John,

I have finished with the review for CSU and there are no action items, approval can be recommended. Let me know if you have any questions moving forward.

Thanks,

Ryne
rsolberg@csu.org
9/29/2020 1:13:43 PM