Project Review Comments

Back to List


Project Name
Claremont Business Park 2 Filing 1, Lot 4
Description
Location
Parcels
5404121002 5404121002
Applicant
Hammers Construction
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
EA Number
EA19107
File Number
PPR2110
Project Manager
Mercedes Rivas
Status
Closed
Created
2/23/2020 5:43:01 PM

View: Project Documents



Review Comments (30)

Link Agency Comment
View EPC Code Enforcement Inspections
12/2/2021 6:59:06 AM
See attached pictures. No concerns were noted by the Code Enforcement Officer. 12/2/2021 6:59:06 AM
Cherokee Metro Dist
5/26/2021 3:33:04 PM
Utility Service Plan Sheet 2 of 2 Comments:
Install curb stop on the water service line at the property line
Label valve on 6" fire line
Service line to be 1" HDPE (blue) CTS not IPS as labeled
5/26/2021 3:33:04 PM
Pikes Peak Regional Building Department
5/17/2021 8:19:23 AM
No further comments.

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
5/17/2021 8:19:23 AM
PCD Engineering Division
5/17/2021 7:19:02 AM
All PCD engineering comments have been resolved. The project manager will upload approved documents.

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
5/17/2021 7:19:02 AM
EPC Stormwater Review
5/14/2021 5:57:12 PM
All EPC Stormwater comments have been resolved.

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
5/14/2021 5:57:12 PM
PCD Project Manager
5/13/2021 4:53:22 PM
Please address the following comments from the first set of redlines on the site plan:

-This symbology looks similar. Please change symbology.
-Bicycle parking facilities shall be at least 2 feet in width and 5½ feet in length, with additional back-out or maneuvering space of at least 5 feet.
5/13/2021 4:53:22 PM
Cherokee Metro Dist
5/12/2021 3:48:56 PM
The Claremont Business Park 2 Filing 1, Lot 4 development is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer.

Comments to PPR:
Utility Service Plan Sheet 2 of 2: Show curb stop located at property line or add note. Also service line labeled 1" HDPE IPS. Change to 1" HDPE CTS.
5/12/2021 3:48:56 PM
Colorado Springs Airport Advisory Commission
5/10/2021 1:16:39 PM
There are no additional comments beyond those previously provided. 5/10/2021 1:16:39 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/23/2021 9:05:17 AM
Hey Mercedes,

I have finished with the review for the proposed development. CSU has no action items at this time and approval can be recommended. Let me know if you need anything else from me.

Thanks,
Ryne Solberg
rsolberg@csu.org
4/23/2021 9:05:17 AM
EPC County Attorney's Office
4/22/2021 9:33:53 AM
Water review not needed - please send referral to County Attorney-Development Review. Thank you. 4/22/2021 9:33:53 AM
View EPC Health Department
4/21/2021 10:31:54 AM
4/21/2021 10:31:54 AM
View EPC Health Department
4/13/2021 4:30:30 PM
4/13/2021 4:30:30 PM
View Colorado Springs Airport Advisory Commission
4/8/2021 5:43:45 PM
The attached summary with comments will be presented at the April 28, 2021 Airport Advisory Commission meeting. 4/8/2021 5:43:45 PM
View PCD Project Manager
3/29/2021 4:45:39 PM
SWMP Checklist redlines 3/29/2021 4:45:39 PM
View PCD Project Manager
3/29/2021 4:45:15 PM
Site Development Plan redlines 3/29/2021 4:45:15 PM
View PCD Project Manager
3/29/2021 4:44:48 PM
Grading and Erosion Control Plan redlines 3/29/2021 4:44:48 PM
View PCD Project Manager
3/29/2021 4:44:27 PM
Grading and Erosion Control Checklist redlines 3/29/2021 4:44:27 PM
View PCD Project Manager
3/29/2021 4:44:04 PM
Financial Assurnace Form redlines 3/29/2021 4:44:04 PM
View PCD Project Manager
3/29/2021 4:43:43 PM
Erosion and Stormwater Quality Control Permit redlines 3/29/2021 4:43:43 PM
View PCD Project Manager
3/29/2021 4:42:06 PM
Final Drainage Report redlines 3/29/2021 4:42:06 PM
PCD Engineering Division
3/29/2021 9:40:43 AM
Review 1 comments will be uploaded by the project manager. The following documents have generated comments:

-Drainage report
-GEC plans
-Site development plans
-FAE

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
3/29/2021 9:40:43 AM
Pikes Peak Regional Building Department
3/29/2021 8:36:29 AM
1. It appears the proposed building is for a single tenant, if this is not the case, please provide secondary addressing for each building.
2. Recorded plat has been provided to this department, thank you. Enumerations has entered the streets into the roads database.
3. No further comments.

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
3/29/2021 8:36:29 AM
View Cherokee Metro Dist
3/26/2021 10:42:01 AM
See notes on attached Utility Service Plan Sheet 1

The Claremont Business Park 2 Filing 1, Lot 4 development is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer.
3/26/2021 10:42:01 AM
View EPC Stormwater Review
3/26/2021 10:07:08 AM
ESQCP_v1 3/26/2021 10:07:08 AM
View EPC Stormwater Review
3/26/2021 10:06:45 AM
SWMP Checklist_v1 3/26/2021 10:06:45 AM
View EPC Stormwater Review
3/26/2021 10:06:09 AM
GEC Checklist_v1 3/26/2021 10:06:09 AM
EPC Stormwater Review
3/26/2021 10:03:57 AM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- GEC Plan (to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP Checklist
- ESQCP

Comments on the following document have been provided in PPR-21-009:
- SWMP

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
3/26/2021 10:03:57 AM
PCD Project Manager
3/25/2021 3:06:31 PM
Planning comments will be issued pending completion of Engineering review 3/25/2021 3:06:31 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/9/2021 7:02:59 PM
Hey Mercedes,

I have finished with the review for the proposed development. CSU has no action items at this time and approval can be recommended. Let me know if you need anything else from me.

Thanks,
Ryne Solberg
rsolberg@csu.org
3/9/2021 7:02:59 PM
EPC County Attorney's Office
3/2/2021 11:42:12 AM
No review needed by County Attorney-Water. Please refer matter to County Attorney-Development Review. Thank you. 3/2/2021 11:42:12 AM