Project Review Comments

Back to List


Project Name
Mountain View Academy Early Grading
Description
Location
Parcels
5404121002 5404121002
Applicant
Charter Development Company, LLC
Jeff Chamberlain ( jchamberlain@nhaschools.com )
(616) 954-6381
Jeff Chamberlain ( jchamberlain@nhaschools.com )
(616) 954-6381
EA Number
EA19170
File Number
EGP202
Project Manager
Lindsay Darden
Status
Closed
Created
1/22/2020 1:56:19 PM

View: Project Documents



Review Comments (12)

Link Agency Comment
PCD Engineering Division
5/11/2020 9:07:39 AM
No additional comments. Approved plans will be uploaded by the project manager. 5/11/2020 9:07:39 AM
View PCD Engineering Division
4/28/2020 4:44:00 PM
Review 2 redline comments on the following documents is attached:
* Preliminary Drainage Report (see page 8 for comment)

Remaining comment is minor in nature. Therefore, make the necessary revisions and upload all engineering documents with signatures and stamps for final approval. Make sure each sheet of the grading and erosion control plans includes the PE stamp with signature and date of signature through the stamp. SWMP and GEC checklist also requires PE signature and/or stamp.


Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
4/28/2020 4:44:00 PM
PCD Project Manager
3/19/2020 4:11:00 PM
Add file number EGP202 to the GEC plan sheets. 3/19/2020 4:11:00 PM
View PCD Engineering Division
3/17/2020 10:44:28 AM
Review 1 redline: SWMP Report 3/17/2020 10:44:28 AM
View PCD Engineering Division
3/17/2020 10:43:56 AM
Review 1 redline: SWMP Checklist 3/17/2020 10:43:56 AM
View PCD Engineering Division
3/17/2020 10:43:08 AM
Review 1 redline: GEC Plan 3/17/2020 10:43:08 AM
View PCD Engineering Division
3/17/2020 10:42:39 AM
Review 1 redline: GEC Checklist 3/17/2020 10:42:39 AM
View PCD Engineering Division
3/17/2020 10:42:10 AM
Review 1 redline: FAE 3/17/2020 10:42:10 AM
View PCD Engineering Division
3/17/2020 10:41:28 AM
Review 1 redline: ESQCP 3/17/2020 10:41:28 AM
View PCD Engineering Division
3/17/2020 10:40:44 AM
Review 1 redline: Drainage Report 3/17/2020 10:40:44 AM
PCD Engineering Division
3/17/2020 10:07:53 AM
Review 1: Stormwater comments have been provided in the following documents and will be uploaded by the project manager:
- SWMP
- SWMP Checklist

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
3/17/2020 10:07:53 AM
PCD Engineering Division
3/17/2020 10:39:37 AM
Review 1 redline comments on the following documents will be uploaded individually:
- ESQCP
- GEC Plan
- GEC Checklist
- FAE
- Preliminary Drainage Report

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
3/17/2020 10:39:37 AM