Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
1/10/2020 1:38:00 PM |
El Paso County Planning and Community Development Engineering staff has the following comments: (Jeff Rice 719-520-7877) 1. (Previous comment unresolved): It is not clear what the traffic impacts of this project will be on El Paso County roads, including Grinnell Blvd., Fontaine Blvd., and Bradley Road. Please provide an update on the traffic study identifying the anticipated directional distribution and required improvements to any County roads and intersections that are impacted by the proposed development. 2. Additional comments may be provided separately by the County Engineer. |
1/10/2020 1:38:00 PM | |
View |
PCD Project Manager
12/9/2019 10:37:23 AM |
Comments | 12/9/2019 10:37:23 AM |
PCD Engineering Division
12/6/2019 8:34:12 AM |
El Paso County Planning and Community Development Engineering staff has the following comments: (Jeff Rice 719-520-7877) 1. (Previous comment unresolved): It is not clear what the traffic impacts of this project will be on El Paso County roads, including Grinnell Blvd., Fontaine Blvd., and Bradley Road. Please provide an update on the traffic study identifying the anticipated directional distribution and required improvements to any County roads and intersections that are impacted by the proposed development. 2. Additional comments may be provided separately by the County Engineer. |
12/6/2019 8:34:12 AM | |
View |
PCD Project Manager
10/22/2019 7:02:03 AM |
MDT Letter minus County Engineer | 10/22/2019 7:02:03 AM |
PCD Engineering Division
10/21/2019 3:17:30 PM |
1. It is not clear what the traffic impacts of this project will be on El Paso County roads, including Grinnell Blvd., Fontaine Blvd., and Bradley Road. Please provide an update on the traffic study identifying the anticipated directional distribution and required improvements to any County roads and intersections that are impacted by the proposed development. | 10/21/2019 3:17:30 PM |