PCD Project Manager
11/14/2019 2:05:42 PM |
Approval is still scheduled for 11/25/19. If the submission is received with edits made, the approval may still proceed. If submission is not received approval will have to be rescheduled. | 11/14/2019 2:05:42 PM | |
View |
PCD Project Manager
11/14/2019 2:04:47 PM |
Application, Type C is required for the Administrative relief. See additional documents for correct application, also make sure the request matches the Site Plan | 11/14/2019 2:04:47 PM |
View |
PCD Project Manager
11/14/2019 2:04:04 PM |
Letter of Intent, see attached redlines. Section 5.5.1.D.1, each bullet needs to be identified in the letter of intent and justification for each one provided. | 11/14/2019 2:04:04 PM |
PCD Engineering Division
11/12/2019 4:49:39 PM |
No transporation or drainage comments. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
11/12/2019 4:49:39 PM | |
View |
Mountain View Electric Association, Inc.
10/30/2019 11:09:56 AM |
10/30/2019 11:09:56 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/29/2019 1:03:23 PM |
Hey Gabe, I have finished with my review for the subject application. CSU has no action items and approval is recommended. Let me know if you need anything further from me. Thanks, Ryne |
10/29/2019 1:03:23 PM |