- Project Name
- Gardens At North Carefree PUDSP Amd
- Description
- amendment to plan to remove a lot that was lost due to the size of the pond needing to be increased.
- Location
- Parcels
- 5329400012 5329400012 5329411002 5329411002
- Applicant
-
NES Inc.
Erin Ganaway ( eganaway@nescolorado.com )
(719) 884-1375 Erin Ganaway ( eganaway@nescolorado.com )
(719) 884-1375 - EA Number
- EA18217
- File Number
- PUDSP198
- Project Manager
- Nina Ruiz
- Status
- Closed
- Created
- 8/29/2019 5:03:56 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
EPC Health Department
1/3/2020 3:52:11 PM |
See the original comments submitted 20Sept2018 and the attached comment. | 1/3/2020 3:52:11 PM |
PCD Engineering Division
11/12/2019 4:34:39 PM |
Review 1 comments: 1. PUD/Preliminary Plan: Tract F and G are labeled differently on the final plat. Revise to match the final plat or vice versa. 2. The Final Drainage Report and Grading and Erosion Control Plan are currently in review with the final plat application (PCD File No. SF195). These documents must be signed and approved before approval of the PUDSP amendment. Reviewed By: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
11/12/2019 4:34:39 PM | |
Pikes Peak Regional Building Department
11/5/2019 9:45:20 AM |
Regarding a request for approval of a minor amendment to a development plan for Gardens and North Carefree, Enumerations has the following comments: 1. Enumerations has previously assigned addresses for this project, and the copy we were given to use appears to be the same as the one included in this submittal. Please verify that the lot configuration has not changed since the addresses were provided. Floodplain has the following comments: 1. Update the floodplain statement to show the current FEMA FIRM panel number and effective date. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
11/5/2019 9:45:20 AM | |
PCD Project Manager
11/5/2019 9:38:17 AM |
Please add "amendment" to the title of the drawing. This amendment is to be completed administratively due to the proposed revision being a decrease in density. Please revise the signature block accordingly. Please add a reference to the reception number for the original PUD drawing. |
11/5/2019 9:38:17 AM | |
View |
Colorado Division of Water Resources
11/1/2019 1:54:06 PM |
11/1/2019 1:54:06 PM | |
Colorado Geological Survey
10/31/2019 2:34:31 PM |
The specific corrections and recommendations in CGS's 9/8/2018 review comments have been satisfactorily addressed. CGS's advisory comments regarding removal of fill, and adherence to Entech's 10/25/2017 geotechnical recommendations remain valid. | 10/31/2019 2:34:31 PM | |
View |
Parks Advisory Board
10/30/2019 4:18:52 PM |
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (No PAB Endorsement Necessary for Minor Fee Adjustment) | 10/30/2019 4:18:52 PM |
View |
EPC Parks Department
10/30/2019 4:11:24 PM |
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (No PAB Endorsement Necessary for Minor Fee Adjustments) | 10/30/2019 4:11:24 PM |
Cherokee Metro Dist
10/25/2019 11:03:02 AM |
Proposed change reduces the number of lots and associated water and wastewater demand. Cherokee has no objections and has adequate resources to supply services to this development. | 10/25/2019 11:03:02 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/24/2019 8:06:18 AM |
Hey Nina, CSU has no comments and recommends approval. Thanks, Ryne |
10/24/2019 8:06:18 AM | |
Colorado State Forest Service
10/22/2019 12:58:43 PM |
As there is no forest component to this site no special fire mitigation plans or other actions are necessary for final approval by the Colorado State Forest Service. | 10/22/2019 12:58:43 PM | |
View |
EPC Environmental Services
10/22/2019 8:45:54 AM |
10/22/2019 8:45:54 AM | |
View |
911 Authority - El Paso/Teller County
10/16/2019 3:14:58 PM |
The following names have been reviewed and if approved added to the reserve name list for: Gardens at North Carefree. ESN: 245 City: Falcon PSAP: EPSO Location: Akers Drive and North Carefree. Items in “Red” are not approved street names Items in “Green” are acceptable street names for this project Fallow Lane –Acceptable a natural extension of the existing road into this subdivision. Running Deer Way– Acceptable a natural extension of the existing road into this subdivision. Vineyard Circle Acceptable, previously approved. Request the contractor submit new proposed names for those listed as not acceptable. Information regarding street naming can be found at: https://elpasoteller911.org/191/Street-Emergency-Number-Databases Glenn West |
10/16/2019 3:14:58 PM |
County Attorney - Water
10/16/2019 8:58:50 AM |
It doesn't appear that there will be a change in water supply as a result of the modification of grading and drainage pond, therefore, no comments will be provided from the County Attorney's Office regarding water supply. 10/16/19 | 10/16/2019 8:58:50 AM | |
Central CO Conservation District
10/15/2019 2:21:36 PM |
The Board of Supervisors for the Central Colorado Conservation District have no comments at this time. | 10/15/2019 2:21:36 PM |