Claremont Business Park Filing 1C
Description
Subdivide LOT 2 from Claremont Business Park Filing1A (Plat 12398) and a portion of Tract C into two parcels.
Location
Parcels
5408101027 5408101027 5408101054 5408101054
Applicant
Hammers Construction
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
EA Number
EA1974
File Number
VR194
Project Manager
Lindsay Darden
Status
Closed
Created
6/6/2019 1:46:27 PM

View: Project Documents



Review Comments (48)

Link Agency Comment
View PCD Project Manager
6/2/2020 11:56:59 PM
One comment remaining. See redline. 6/2/2020 11:56:59 PM
View EPC County Attorney's Office
5/14/2020 4:29:18 PM
5/14/2020 4:29:18 PM
View PCD Project Manager
5/12/2020 11:52:40 PM
Please see final plat redlines for two minor revisions. 5/12/2020 11:52:40 PM
PCD Project Manager
5/12/2020 11:23:59 PM
Repeat Comment: The Soils and Geology report was prepared in 2018. We have since revised the report requirements in the Land Development Code Section 8.4.9 so the report should either comply with those new requirements or you should submit a request letter with justification for why the previously submitted report will suffice pursuant to LDC Section 8.4.9 (A)(2): Previously Submitted.

"Where a geology and soils report has been completed and reviewed at an earlier stage of the subdivision review process, a new report may not be required if in the determination of the PCD Director the existing report provides the level of site specific detail necessary to review the subdivision application, and the recommendations of the report and Colorado Geological Survey have been followed in the preparation of the preliminary plan."
5/12/2020 11:23:59 PM
PCD Project Manager
5/12/2020 11:19:25 PM
Repeat Comment: Please take a look at the letter of intent. It was supposed to be revised to address each of the final plat criteria specified in LDC Section 7.2.1(D)(3)(f). When I open it, it is one page and looks like maybe part of it was cut off at the bottom. I am wondering if we received the complete document? 5/12/2020 11:19:25 PM
PCD Project Manager
5/12/2020 11:15:18 PM
Repeat Comment: Mineral Rights Certification - please circle one to indicate there "was" or "was not" a mineral rights estate owner on the mineral rights certification form. 5/12/2020 11:15:18 PM
PCD Project Manager
5/12/2020 11:12:06 PM
Repeat Comment: The wastewater commitment report still does not include the wastewater demands and capabilities. It only addresses the water. VR1811 has a wastewater commitment letter from Cherokee that adequately addresses these requirements if you want to refer to an example of what we need. 5/12/2020 11:12:06 PM
County Attorney - Development Review
5/9/2020 4:16:07 PM
Detention Maintenance Agreement looks fine. No further comments. 5/9/2020 4:16:07 PM
View Colorado Division of Water Resources
5/8/2020 10:57:28 AM
5/8/2020 10:57:28 AM
PCD Engineering Division
5/7/2020 9:05:30 PM
Engineering documents have been approved by the ECM administrator. Approved documents will be uploaded by the project manager.

reviewed by
Daniel Torres
danieltorres@elpasoco.com
5/7/2020 9:05:30 PM
PCD Project Manager
4/26/2020 6:02:05 PM
Cherokee wastewater commitment letter should include the wastewater demands and capabilities. 4/26/2020 6:02:05 PM
PCD Project Manager
4/26/2020 6:01:30 PM
Subdivision Summary - update to include the Tract C area. 4/26/2020 6:01:30 PM
PCD Project Manager
4/26/2020 6:00:08 PM
Verify that the mineral rights owners were notified for Tract C as well and fill in the section of the mineral rights certification that indicates there was/was not (circle one) a mineral rights estate owner.

Please upload re-notification receipts and documentation that includes the May hearing date.
4/26/2020 6:00:08 PM
PCD Project Manager
4/26/2020 5:51:51 PM
Ensure that the Letter of Intent addresses all of the review criteria for a final plat (See LDC Section 7.2.1(D)(3)(f). 4/26/2020 5:51:51 PM
PCD Project Manager
4/26/2020 5:49:20 PM
The Soils and Geology report was prepared in 2018. We have since revised the report requirements in the Land Development Code Section 8.4.9 so the report should either comply with those new requirements or you should submit a request letter with justification for why the previously submitted report will suffice pursuant to LDC Section 8.4.9 (A)(2): Previously Submitted.

"Where a geology and soils report has been completed and reviewed at an earlier stage of the subdivision review process, a new report may not be required if in the determination of the PCD Director the existing report provides the level of site specific detail necessary to review the subdivision application, and the recommendations of the report and Colorado Geological Survey have been followed in the preparation of the preliminary plan."
4/26/2020 5:49:20 PM
PCD Project Manager
4/26/2020 5:42:27 PM
Ensure that the fire protection report meets the requirements of LDC Section 6.3.3. 4/26/2020 5:42:27 PM
View PCD Project Manager
4/23/2020 5:21:25 PM
See redlines on the final plat. 4/23/2020 5:21:25 PM
View County Attorney - Development Review
4/20/2020 4:35:52 PM
Changes to Detention Maintenance Agreement attached. 4/20/2020 4:35:52 PM
PCD Engineering Division
4/20/2020 9:36:29 AM
Review 3
A revised Traffic Study addressing the comment from review#2 has not been submitted. Please address the comment and submit a signed Traffic Study to be sent to the ECM Administrator for acceptance.

All other engineering comments have been resolved.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
4/20/2020 9:36:29 AM
PCD Project Manager
4/1/2020 9:40:33 AM
As discussed, please include the adjacent parcel (from tract C) and show on all drawings. Please update any other sheets (survey closures, etc.) as required to ensure all documents match the project scope and show this parcel. 4/1/2020 9:40:33 AM
PCD Engineering Division
3/22/2020 5:42:21 PM
Review 2 comments on the following documents will be uploaded by the project manager:
-Letter of Intent: Minor comments
-Traffic Study: Minor Comment

Engineering comments on the following documents have been resolved
-Final Plat

A signed traffic study may be submitted with the resubmittal for acceptance by the ECM Administrator.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
3/22/2020 5:42:21 PM
Colorado Springs Airport Advisory Commission
3/16/2020 8:41:03 AM
Airport staff has no additional comments beyond those already provided. 3/16/2020 8:41:03 AM
Pikes Peak Regional Building Department
3/13/2020 1:32:11 PM
Regarding a request for approval of a final plat for Claremont Business Park Lots 1 and 2 Filing No. 1B, Enumerations no further comments.


Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
3/13/2020 1:32:11 PM
County Attorney - Development Review
3/11/2020 8:50:28 PM
1. Thank you for the response regarding the Detention Maintenance Agreement. It is difficult to determine, however, which if any of the documents uploaded contain the applicant's most recent draft. Please take the Word document uploaded by the County Attorney's Office on February 5, accept those changes that are acceptable, reject those that are not and suggest an alternative if appropriate, then upload that most recent draft in Word for ease of editing. Please make sure all exhibits are attached.
2. As stated in the Feb. 5 comment, this plat must include all of Tract C. Please correct the plat drawings, legal descriptions, and any other necessary documents to reflect this change.
3/11/2020 8:50:28 PM
Cherokee Metro Dist
3/5/2020 8:37:44 AM
This development is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer. 3/5/2020 8:37:44 AM
EPC County Attorney's Office
3/4/2020 3:45:12 PM
County Attorney's Office will provide a review of water sufficiency once findings are received from the Colorado Division of Water Resources. Lori Seago should be receiving a separate notice related to Development Review. 3/4/2020 3:45:12 PM
View EPC Health Department
2/18/2020 10:46:36 AM
2/18/2020 10:46:36 AM
View County Attorney - Development Review
2/5/2020 10:50:18 AM
1. Comments on and proposed changes to Detention Maintenance Agreement are attached.

2. The entirety of Tract C, Claremont Business Park Filing No. 2 should be included in this vacation and replat so as not to create an illegal subdivision of Tract C.
2/5/2020 10:50:18 AM
View PCD Project Manager
1/24/2020 3:24:19 PM
Please see redlines on the application. 1/24/2020 3:24:19 PM
View PCD Project Manager
1/24/2020 3:23:17 PM
Please see redlines on the final plat drawings 1/24/2020 3:23:17 PM
View PCD Project Manager
1/23/2020 4:36:13 PM
Please see redlines on the subdivision summary. 1/23/2020 4:36:13 PM
View PCD Project Manager
1/23/2020 4:33:15 PM
Please see redlines on the Water Resources Report 1/23/2020 4:33:15 PM
View PCD Project Manager
1/23/2020 4:17:12 PM
Please see redlines on the water supply information summary. 1/23/2020 4:17:12 PM
PCD Project Manager
1/23/2020 11:08:22 AM
Mineral Rights Certification and Title Commitment - please also provide these for the Tract C parcel. 1/23/2020 11:08:22 AM
View PCD Project Manager
1/23/2020 10:18:26 AM
Please see redlines on the Letter of Intent 1/23/2020 10:18:26 AM
PCD Project Manager
1/24/2020 3:25:29 PM
Water and Wastewater Commitment Letters: This indicates that there is no landscaping on site. The approved site plan for these lots has required landscaping. Please get updated commitment letters. 1/24/2020 3:25:29 PM
PCD Project Manager
1/22/2020 4:05:43 PM
Closures Sheet:
Field measurements on the ground must close within a limit of one foot (1) to ten thousand (10,000) feet of perimeter which in decimal format is 0.0001. The closure sheet provided shows errors that do not comply with this requirement. Please revise.
1/22/2020 4:05:43 PM
PCD Project Manager
1/22/2020 3:51:46 PM
Adjacent Notification: Because you are revising part of parcel 5408101054, you have to notify the parcels adjacent to that too. Please upload revised adjacent notification that includes those additional parcels. 1/22/2020 3:51:46 PM
View PCD Project Manager
1/21/2020 4:23:51 PM
Please see redlines on the Traffic Impact Study 1/21/2020 4:23:51 PM
PCD Engineering Division
1/16/2020 3:42:54 PM
Review 1 comments on the following documents will be uploaded by the project manager:
-Letter of Intent
-Final Plat
-Traffic Study


reviewed by:
Daniel Torres
danieltorres@elpasoco.com
1/16/2020 3:42:54 PM
Colorado Geological Survey
1/14/2020 12:17:45 PM
The site is relatively flat, is not undermined, and is not exposed to any geologic hazards or unusual geotechnical constraints that would preclude the proposed increase in density. Terracon's 10/5/2005 characterization of subsurface conditions and geotechnical recommendations are valid. CGS therefore has no objection to approval. 1/14/2020 12:17:45 PM
View Colorado Springs Airport Advisory Commission
1/14/2020 7:59:08 AM
Attached is a land use review summary with comments that will be presented at the January 22, 2020 Airport Advisory Commission meeting. 1/14/2020 7:59:08 AM
Pikes Peak Regional Building Department
1/10/2020 8:56:51 AM
Regarding a request for approval of a final plat for Claremont Business Park 1A-Lot 2- Filing No. 1, Enumerations has the following comments:

1. Proposed Lot 2 does not show an address. The address of 1491 Woolsey Heights was assigned to the building currently under construction in this location and this is the address that should appear on the plat for this lot.
2. Enumerations will review the mylar prior to recording for title block, street names, addressing and floodplain statement. No Enumerations fee will be due since all addresses are existing.


Floodplain has no comment.

Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
1/10/2020 8:56:51 AM
Cherokee Metro Dist
1/3/2020 10:09:27 AM
October 21, 2019 letter from Cherokee documents water and wastewater commitment. 1/3/2020 10:09:27 AM
EPC County Attorney's Office
12/27/2019 3:49:20 PM
County Attorney's Office will provide a review of water sufficiency once findings are received from the Colorado Division of Water Resources. Thank you. 12/27/19 12/27/2019 3:49:20 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
12/24/2019 10:54:29 AM
Hey Lindsay,

I have finished with the review for the subject application. CSU has no action items at this time and approval is recommended. Let me know if you need anything further from me.

Thanks,

Ryne
12/24/2019 10:54:29 AM
View EPC Environmental Services
12/18/2019 2:01:16 PM
12/18/2019 2:01:16 PM
911 Authority - El Paso/Teller County
12/18/2019 9:43:23 AM
No Comment for E911