Project Review Comments

Back to List


Project Name
Black Hills Energy Midway Substation-Transmission Line Site Development Plan
Description
Proposal to replace the existing poles and arms along the transmission corridor. ADM-19-012 completed. Director has determined no 1041 application is required for maintenance of a transmission line.
Location
Applicant
Black Hills Energy
Cristin Cochran ( cristin@msn.com )
(303) 377-9060
Cristin Cochran ( cristin@msn.com )
(303) 377-9060
File Number
PPR1939
Project Manager
Kari Parsons
Status
Closed
Created
5/31/2019 3:00:31 PM

View: Project Documents



Review Comments (1)

Link Agency Comment
PCD Project Manager
9/9/2019 1:31:41 PM
Planning has no comments. If the work proposed expands from the description in the letter of intent and as depicted in the application packet, an additional process may be necessary. This plan depicts the replacement of Poles and arms. New ground disturbance is not anticipated to be over an acre. 9/9/2019 1:31:41 PM