Project Review Comments

Back to List


Project Name
Cathedral Pines Filing No. 3, Lots 6-8 (Piasecki Amended Plat)
Description
Cathedral Pines Filing 3: Vacate lots 6, 7, and 8 to create two lots from the three.
Location
Parcels
6201008008 6201008008 6201008009 6201008009 6201008010 6201008010
Applicant
Compass Surveying and Mapping, LLC
Mark Johannes ( mark@csamllc.com )
(719) 354-4120
Mark Johannes ( mark@csamllc.com )
(719) 354-4120
EA Number
EA1989
File Number
SF1917
Project Manager
Lindsay Darden
Status
Closed
Created
5/30/2019 5:03:56 PM

View: Project Documents



Review Comments (15)

Link Agency Comment
PCD Project Manager
12/4/2019 3:28:02 PM
It appears all comments have been addressed. There is one minor comment on the Final Plat Drawings. In the Lower Right Corner of page one the PCD File number has a VR in front of the SF 19-017. That VR should be removed as it is not part of the file number. You can then submit Mylar drawings for signature and a check for recording fees. Recording fees for this will be $13/sheet of mylars.

Prior to being able to sign the mylars and approve, we need zero balance tax certificates from the County Treasurer's office for each of the three lots showing $0 property tax balance.
12/4/2019 3:28:02 PM
PCD Engineering Division
12/2/2019 10:17:55 PM
Engineering comments have been resolved.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
12/2/2019 10:17:55 PM
View EPC Health Department
11/26/2019 2:52:08 PM
11/26/2019 2:52:08 PM
View PCD Project Manager
10/16/2019 11:42:16 AM
Please see redlines on the final plat. 10/16/2019 11:42:16 AM
PCD Project Manager
10/16/2019 11:28:30 AM
Prior to approval, we will need the following:
1. Updated or endorsed title commitment to demonstrate the land has not changed configuration or ownership prior to approval of the final plat. If it has changed configuration (purchase from Piasecki to other owner has already occurred, this will update title work in our system for this approval.
2. Zero balance property tax certification for all three parcels.
3. Please resubmit final plat drawing for review once more so we can verify revisions have been made prior to requesting Mylar.
10/16/2019 11:28:30 AM
PCD Project Manager
10/16/2019 11:02:34 AM
For consistency with the original plat, please hatch the no-build areas which include drainage easements and areas where the slopes exceed 30%. 10/16/2019 11:02:34 AM
PCD Project Manager
10/16/2019 11:07:31 AM
Final Plat Sheet 3 - to comply with LDC Section 7.2.5(C)(3)(b), please rename the proposed lots to Lot 6A and 7A.

Some of the distances on the bearing lines describing the drainage easement cutting across the parcels are slighting off from what was approved on the original plat. Please clarify why this discrepancy.
10/16/2019 11:07:31 AM
PCD Project Manager
10/16/2019 10:55:36 AM
To maintain consistency with our files and also with the Code, please rename the plat to "Cathedral Pines Subdivision Filing No. 3, Lots 6-8." 10/16/2019 10:55:36 AM
PCD Project Manager
10/15/2019 5:25:58 PM
Please show the outline of all three parcels on the vicinity map. 10/15/2019 5:25:58 PM
PCD Project Manager
10/15/2019 5:25:07 PM
Legal Description:

Please list the legal descriptions for each lot individually on this sheet.
10/15/2019 5:25:07 PM
PCD Project Manager
10/15/2019 5:24:06 PM
Application attachment:
Ownership section does not address Lot 6. It has lot 8 duplicated with both owners. Please revise.

Front page of Application form:

Application type: Please check the box next to final plat, Amendment

Existing Land Use: Residential

Zoning District: PUD
10/15/2019 5:24:06 PM
View EPC Parks Department
10/9/2019 10:49:40 AM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (No PAB Endorsement Necessary) 10/9/2019 10:49:40 AM
PCD Engineering Division
10/7/2019 9:56:45 AM
Review 1 comments on the following documents will be uploaded by the project manager:
-Final Plat

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
10/7/2019 9:56:45 AM
Pikes Peak Regional Building Department
10/4/2019 11:20:59 AM
Regarding a request for approval of a final plat for Cathedral Pines Fil. No. 8 , Enumerations has the following comments:

1. With this replat, Lot 1 will retain the use of the address of the existing residence of 4820 Foxchase Way. Lot 2 will retain the address of the existing residence of 4940 Foxchase Way. These addresses must appear on the plat in the appropriate locations.
2. Enumerations will review the mylar as usual for addressing, title block, street names and floodplain statement prior to recording. No Enumerations fee will be due at the time of mylar review since all addresses are existing.


Floodplain has no comment.

Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
10/4/2019 11:20:59 AM
View Mountain View Electric Association, Inc.
9/24/2019 1:58:20 PM
9/24/2019 1:58:20 PM