View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
9/8/2020 1:33:34 PM |
Engineering comments have been resolved. The project manager will upload the engineering documents once approved by the ECM administrator. reviewed by: Daniel Torres, danieltorres@elpasoco.com |
9/8/2020 1:33:34 PM | |
County Attorney - Development Review
9/8/2020 1:28:10 PM |
No further comments from County Attorney's Office at this time. | 9/8/2020 1:28:10 PM | |
CIG Colorado Interstate Gas
8/12/2020 10:53:07 AM |
PLEASE NOTE: THESE PLANS DO NOT REFLECT THE CORRECT CIG RIGHT OF WAY. THERE ARE TWO SEPERATE PIPELINES AND EACH RIGHT OF WAY WIDTH IS 50 FEET. The Site Development Plan was reviewed by a CIG engineer and there are no impacts to the CIG Right Of Way. During Construction: 1. No staging of material or equipment on the CIG right of way. 2. No parking of any type of vehicle over the CIG right of way. 3. The depth of cover over the CIG right of way shall not be reduced nor drainage altered. 4. Planting of trees or shrubs is not permitted in the CIG right of way. 5. Irrigation equipment i.e. backflow devices, meters, valves, valve boxes, etc. shall not be in the CIG right of way. 6. No power poles, light standards, etc., shall be installed in CIG right of way. 7. Follow all state of Colorado One-Call requirements. A CIG will locate and mark the pipelines as needed. |
8/12/2020 10:53:07 AM | |
EPC Stormwater Review
8/3/2020 5:34:22 PM |
All Stormwater comments have been addressed. | 8/3/2020 5:34:22 PM | |
PCD Engineering Division
8/3/2020 5:22:09 PM |
Review 4 comments on the following documents have been provided and will be uploaded. -Drainage Report -Please submit a soil/geotechnical report with the pond embankment recommendations. Per Chapter 11, section 11.3.3 of the El Paso County Drainage Criteria Manual a geotechnical analysis and report with recommendations for the foundation preparation and embankment construction shall be submitted with the complete design analysis for all permanent detention facilities. The GEC plan references a report by RMG. Please submit this report. Provided the few comments on the drainage report are resolved and a soil/geotechnical report with the above information is provided, signed engineering documents may be submitted for approval by the ECM administrator. Engineering comments on the following documents have been resolved. -TIS -GEC plan -GEC checklist -SWMP: minor comment -SWMP checklist -Detention Pond Agreement -Site Development Plan reviewed by: Daniel Torres, danieltorres@elpasoco.com |
8/3/2020 5:22:09 PM | |
View |
County Attorney - Development Review
8/2/2020 10:52:21 AM |
Minor edits to detention maintenance agreement attached. | 8/2/2020 10:52:21 AM |
View |
PCD Project Manager
7/7/2020 12:39:17 PM |
PM and Engineering redlines on site development plan and landscape plan | 7/7/2020 12:39:17 PM |
View |
PCD Engineering Division
6/24/2020 1:40:26 PM |
Site Development Plan redlines | 6/24/2020 1:40:26 PM |
View |
PCD Engineering Division
6/24/2020 1:11:04 PM |
Detention Pond Agreement redlines | 6/24/2020 1:11:04 PM |
View |
PCD Engineering Division
6/24/2020 1:10:40 PM |
SWMP checklist redlines | 6/24/2020 1:10:40 PM |
View |
PCD Engineering Division
6/24/2020 1:10:12 PM |
SWMP redlines | 6/24/2020 1:10:12 PM |
View |
PCD Engineering Division
6/24/2020 1:09:45 PM |
GEC checklist redlines | 6/24/2020 1:09:45 PM |
View |
PCD Engineering Division
6/24/2020 1:09:26 PM |
GEC Plan redlines | 6/24/2020 1:09:26 PM |
View |
PCD Engineering Division
6/24/2020 1:09:04 PM |
TIS redlines | 6/24/2020 1:09:04 PM |
View |
PCD Engineering Division
6/24/2020 1:39:46 PM |
Drainage Report redlines | 6/24/2020 1:39:46 PM |
EPC Stormwater Review
6/22/2020 7:37:26 AM |
See Stormwater comments under PCD Engineering | 6/22/2020 7:37:26 AM | |
County Attorney - Development Review
6/18/2020 12:55:23 PM |
No further changes to Detention Maintenance Agreement. | 6/18/2020 12:55:23 PM | |
PCD Engineering Division
6/24/2020 1:16:41 PM |
Review 3 comments on the following documents have been provided and will be uploaded. -Site Development Plan -Drainage Report -TIS -GEC plan -GEC checklist -SWMP: minor comment -SWMP checklist -Detention Pond Agreement Please submit a soil/geotechnical report with the pond embankment recommendations. Per Chapter 11, section 11.3.3 of the El Paso County Drainage Criteria Manual a geotechnical analysis and report with recommendations for the foundation preparation and embankment construction shall be submitted with the complete design analysis for all permanent detention facilities. Engineering comments on the following documents have been resolved. -Letter of Intent -MS4 Post Construction Form -PBMP Applicability Form -ESQCP reviewed by: Daniel Torres, danieltorres@elpasoco.com Christina Furchak, Stormwater Engineer III Christinafurchack@elpasoco.com |
6/24/2020 1:16:41 PM | |
View |
EPC Health Department
5/19/2020 9:29:15 PM |
See previous comments (attached). | 5/19/2020 9:29:15 PM |
EPC Stormwater Review
5/18/2020 10:51:52 AM |
Stormwater comments have been provided with PCD Engineering Division comments. | 5/18/2020 10:51:52 AM | |
View |
PCD Project Manager
5/18/2020 8:01:10 AM |
Traffic Study | 5/18/2020 8:01:10 AM |
View |
PCD Project Manager
5/18/2020 8:00:31 AM |
SWMP | 5/18/2020 8:00:31 AM |
View |
PCD Project Manager
5/18/2020 7:59:30 AM |
SWMP Checklist | 5/18/2020 7:59:30 AM |
View |
PCD Project Manager
5/18/2020 7:58:57 AM |
Site Development Plan | 5/18/2020 7:58:57 AM |
View |
PCD Project Manager
5/18/2020 7:58:36 AM |
PBMP Applicability Form | 5/18/2020 7:58:36 AM |
View |
PCD Project Manager
5/18/2020 7:58:03 AM |
MS4 Form B | 5/18/2020 7:58:03 AM |
View |
PCD Project Manager
5/18/2020 7:57:33 AM |
MS4 Form A | 5/18/2020 7:57:33 AM |
View |
PCD Project Manager
5/18/2020 7:56:56 AM |
Lighting Plan | 5/18/2020 7:56:56 AM |
View |
PCD Project Manager
5/18/2020 7:56:27 AM |
Letter of Intent | 5/18/2020 7:56:27 AM |
View |
PCD Project Manager
5/18/2020 7:55:56 AM |
GEC Plan | 5/18/2020 7:55:56 AM |
View |
PCD Project Manager
5/18/2020 7:55:16 AM |
GEC Checklist | 5/18/2020 7:55:16 AM |
View |
PCD Project Manager
5/18/2020 7:54:29 AM |
ESQCP | 5/18/2020 7:54:29 AM |
View |
PCD Project Manager
5/18/2020 7:53:40 AM |
Address redlines in the following documents: Letter of Intent Site Development Plan Traffic Study Drainage Report ESQCP GEC Plan GEC Checklist SWMP SWMP Checklist PBMP Applicability Form MS4 Form A MS4 Form B Lighting Plan |
5/18/2020 7:53:40 AM |
Cherokee Metro Dist
5/15/2020 9:28:13 AM |
The Tamlin Road RV and Boat Storage is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer. | 5/15/2020 9:28:13 AM | |
PCD Engineering Division
5/15/2020 2:21:07 PM |
Review 2 comments on the following documents will be uploaded by the project manager: -Letter of Intent: add PCD file # -Site Development Plan -Traffic Study -Drainage Report -ESQCP -GEC plan -GEC checklist -SWMP -SWMP checklist -PBMP applicability form -MS4 Form Pond A & MS4 Form Pond B Per Chapter 11, section 11.3.3 of the El Paso County Drainage Criteria Manual a geotechnical analysis and report with recommendations for the foundation preparation and embankment construction shall be submitted with the complete design analysis for all permanent detention facilities. Comments on the following documents have been resolved. -O&M manual -Proof of state non-jurisdictional water impoundment form -SDI Form Pond A -FAE reviewed by: Daniel Torres danieltorres@elpasoco.com |
5/15/2020 2:21:07 PM | |
County Attorney - Development Review
5/9/2020 4:09:32 PM |
The comments to the Detention Maintenance Agreement dated 10/21 have not been addressed. Please review the proposed edits. If they are acceptable, accept the changes through Track Changes and resubmit a clean document. | 5/9/2020 4:09:32 PM | |
Falcon Fire Protection District
4/1/2020 12:21:35 PM |
please get with Falcon Fire on gate requirements | 4/1/2020 12:21:35 PM | |
View |
EPC Health Department
1/2/2020 12:22:58 PM |
1/2/2020 12:22:58 PM | |
Cherokee Metro Dist
10/25/2019 11:07:23 AM |
Met with developer and their engineer to resolve access to Cherokee water storage tank and associated facilities. Approval pending receipt of updated site plan. Development will not use Cherokee for water or wastewater service. | 10/25/2019 11:07:23 AM | |
CIG Colorado Interstate Gas
10/24/2019 3:22:14 PM |
• Grading and Erosion Control Plans o General note: ? There are 2-20” high-pressure natural gas pipelines within the project area. Each pipeline is within a 50’ easement. ? Both easements must be shown on plans ? CIG must have 24/7 access to the pipelines. How does the owner plan to provide this? o Sheet 3 ? VTC off of Tamlin Rd must be moved off of the CIG easement. ? No overnight/long-term parking or storage is permitted within the CIG easements. ? Gas detection units (sniffer) are required in pavement over the gas pipelines. Attached are the typical drawing for installation and a brochure for procurement. ? Any fence post installed during construction must be a minimum of 5’ from either side of each 20” natural gas pipeline. • Site Plan o Monument sign must be completely off of the CIG easement. o No fence posts will be installed within 5’ of either CIG pipeline. o No light posts are permitted inside the CIG easement. If there are plans to run conduit across the CIG easement for lighting, plans must be submitted to CIG and approved before construction. • Landscape Plan o No trees or large shrubs are permitted within the CIG easements. o No irrigation, except for drip lines, will be permitted within the CIG easement. If the contractor plans to cross the CIG pipelines with heavy equipment, a list of the equipment, to include make model, and operating weight will need to be provided to CIG prior to any crossing. The crossing location needs to be identified and the depth of each pipeline will need to be potholed by hydrovac or hand digging. A CO 811 ticket needs to be submitted prior to construction. All ground disturbance within the CIG easements will require a CIG representative be present, including potholing. |
10/24/2019 3:22:14 PM | |
View |
County Attorney - Development Review
10/21/2019 11:03:31 AM |
Changes to Detention Maintenance Agreement attached. | 10/21/2019 11:03:31 AM |
View |
PCD Project Manager
10/18/2019 9:47:00 AM |
Engineer Traffic Memo redlines | 10/18/2019 9:47:00 AM |
View |
PCD Project Manager
10/18/2019 9:46:16 AM |
Engineer Stormwater Management redlines | 10/18/2019 9:46:16 AM |
View |
PCD Project Manager
10/18/2019 9:45:46 AM |
Engineer Site Development Plan redlines | 10/18/2019 9:45:46 AM |
View |
PCD Project Manager
10/18/2019 9:45:13 AM |
Engineer SDI Pond A redlines | 10/18/2019 9:45:13 AM |
View |
PCD Project Manager
10/18/2019 9:44:41 AM |
Engineer PDBBMP O&M redlines | 10/18/2019 9:44:41 AM |
View |
PCD Project Manager
10/18/2019 9:43:52 AM |
Engineer LOI redlines | 10/18/2019 9:43:52 AM |
View |
PCD Project Manager
10/18/2019 9:43:03 AM |
Engineer Grading and Erosion Control redlines | 10/18/2019 9:43:03 AM |
View |
PCD Project Manager
10/18/2019 9:41:43 AM |
Engineer Financial Assurance redlines | 10/18/2019 9:41:43 AM |
View |
PCD Project Manager
10/18/2019 9:41:22 AM |
Engineer ESQCP redlines | 10/18/2019 9:41:22 AM |
View |
PCD Project Manager
10/18/2019 9:40:47 AM |
Engineer Drainage Report redlines | 10/18/2019 9:40:47 AM |
View |
PCD Project Manager
10/18/2019 9:34:48 AM |
Site Development Plan redlines | 10/18/2019 9:34:48 AM |
View |
PCD Project Manager
10/18/2019 9:34:19 AM |
Landscape redlines | 10/18/2019 9:34:19 AM |
County Attorney - Development Review
10/17/2019 10:14:06 AM |
Please resubmit the Detention Maintenance Agreement in Word for ease of editing. | 10/17/2019 10:14:06 AM | |
Pikes Peak Regional Building Department
10/16/2019 10:42:58 AM |
Regarding a request for approval of a development plan for Tamlin Road Storage, Enumerations has the following comments: 1. Even though there don’t appear to be any structures which would require a building permit shown on this plan, for purposes of emergency response and utility billing, an address should be established for this parcel. Enumerations has assigned the address of 5080 Tamlin Rd. to this parcel. Floodplain has the following comments: 1. This parcel lies in 2 different FEMA FIRM panels. The floodplain statement should be updated to show both panel numbers: 08041C0545G & 08041C0543G Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
10/16/2019 10:42:58 AM | |
PCD Engineering Division
10/17/2019 4:42:01 PM |
Review 1 comments on the following documents will be uploaded by the project manager: -Letter of Intent -Traffic Study -Site Development Plan -Drainage Report -Grading and Erosion Control Plan -SWMP -ESQCP -FAE -PBMP Operations and Maintenance Manual -SDI Pond A -Please fill out and submit the GEC and SWMP checklist. The project manager will provide the appropriate slot for upload upon resubmittal. -Please submit confirmation of State Non-Jurisdictional Impoundment Structure form Per Chapter 11, section 11.3.3 of the El Paso County Drainage Criteria Manual recommendations for the foundation preparation and embankment construction shall be submitted with the complete design analysis for all permanent detention facilities. reviewed by: Daniel Torres danieltorres@elpasoco.com |
10/17/2019 4:42:01 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/11/2019 11:40:26 AM |
Hey Petra, CSU has no comments for the proposed plan. Approval is recommended. Let me know if you need anything else from me. Thanks, Ryne |
10/11/2019 11:40:26 AM | |
View |
Mountain View Electric Association, Inc.
10/3/2019 2:24:50 PM |
10/3/2019 2:24:50 PM |