View: Project Documents
Agency | Comment | ||
---|---|---|---|
Pikes Peak Regional Building Department
7/8/2019 2:06:48 PM |
No comment | 7/8/2019 2:06:48 PM | |
PCD Project Manager
7/8/2019 11:00:45 AM |
pending approval by the Director 7/10 | 7/8/2019 11:00:45 AM | |
PCD Engineering Division
7/3/2019 8:24:53 AM |
Engineering comments have been resolved on the site plan and letter of intent. Engineering has no additional comments. |
7/3/2019 8:24:53 AM | |
Falcon Fire Protection District
7/2/2019 2:09:17 PM |
Falcon Fire has no objection to this this set back adjustment. | 7/2/2019 2:09:17 PM | |
EPC Code Enforcement
5/7/2019 2:30:59 PM |
No record of an agricultural structure exemption found. A revocation of an exemption is not needed to allow for the owners to obtain building permits. | 5/7/2019 2:30:59 PM | |
View |
EPC Code Enforcement
5/7/2019 2:29:47 PM |
5/7/2019 2:29:47 PM | |
View |
EPC Code Enforcement
5/7/2019 2:29:32 PM |
5/7/2019 2:29:32 PM | |
View |
EPC Code Enforcement
5/7/2019 2:29:18 PM |
5/7/2019 2:29:18 PM | |
View |
EPC Code Enforcement
5/7/2019 2:29:04 PM |
5/7/2019 2:29:04 PM | |
View |
PCD Project Manager
5/6/2019 2:50:52 PM |
Site Plan Redlines | 5/6/2019 2:50:52 PM |
View |
PCD Project Manager
5/6/2019 2:50:37 PM |
Letter of Intent Redlines | 5/6/2019 2:50:37 PM |
View |
Colorado Springs Airport Advisory Commission
5/3/2019 2:12:55 PM |
Attached is the summary with comments for the subject land use item. This will be presented at the May 22, 2019 Airport Advisory Commission meeting. | 5/3/2019 2:12:55 PM |
Pikes Peak Regional Building Department
5/3/2019 11:41:00 AM |
Second structure for family use would receive the same address but a “B” added for behind structure. No further comment. |
5/3/2019 11:41:00 AM | |
Falcon Fire Protection District
5/3/2019 11:12:22 AM |
Falcon Fire has no fire code concerns or comments on this proposed set back request. | 5/3/2019 11:12:22 AM | |
View |
PCD Engineering Division
4/30/2019 3:07:42 PM |
Engineering comments can be found on the following documents, which will be uploaded by the project manager: -Letter of Intent -Site Plan A driveway access permit was not found on file for the existing access location. A driveway access permit must be obtained. Please see attached the application for a driveway access permit. The permit application can be sent to petrarangel@elpasoco.com. |
4/30/2019 3:07:42 PM |
PCD Project Manager
4/25/2019 5:31:46 PM |
1. A guest house affidavit will be required for the conversion of the structure. Please review the guest house section of the Code to ensure you will comply with all regulations. | 4/25/2019 5:31:46 PM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/25/2019 2:40:04 PM |
Please see the attached memo for comments. Please contact me if there are any questions! | 4/25/2019 2:40:04 PM |