View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
3/22/2021 11:04:59 AM |
The approved engineering documents will be uploaded by the project manager once approved by the ECM administrator. reviewed by: Daniel Torres danieltorres@elpasoco.com |
3/22/2021 11:04:59 AM | |
View |
PCD Engineering Division
2/22/2021 3:35:25 PM |
TIS redlines (minor comments) | 2/22/2021 3:35:25 PM |
View |
PCD Engineering Division
2/22/2021 5:05:56 PM |
Construction Drawing redlines (minor comments) | 2/22/2021 5:05:56 PM |
PCD Engineering Division
2/22/2021 3:36:22 PM |
Please address the minor comments on the following documents and submit all signed engineering documents for approval by the ECM administrator: -Construction Drawings -TIS Please also upload the latest Plat drawing with the revised note so that it is posted on EDARP. reviewed by: Daniel Torres danieltorres@elapasoco.com |
2/22/2021 3:36:22 PM | |
View |
PCD Engineering Division
1/4/2021 7:40:50 AM |
Construction Drawings Redlines | 1/4/2021 7:40:50 AM |
View |
PCD Engineering Division
1/4/2021 7:40:07 AM |
Review 5 comments on the following documents will be uploaded: -Construction Drawings : note there is a comment on the CD that will affect the plat drawing. Please update the plat drawing accordingly. -TIS: comments from the previous review where not addressed. Also comments have been provided on the deviation request that was attached to the TIS. TIS comments are not complete. A meeting has been scheduled with the applicant/consultant, PCD, and the County Engineer to discuss the traffic study. reviewed by: Daniel Torres danieltorres@elapasoco.com |
1/4/2021 7:40:07 AM |
View |
PCD Engineering Division
11/9/2020 9:50:47 AM |
Drainage report redlines | 11/9/2020 9:50:47 AM |
View |
PCD Engineering Division
11/9/2020 9:50:01 AM |
Construction documents redlines | 11/9/2020 9:50:01 AM |
View |
PCD Engineering Division
11/9/2020 9:49:18 AM |
TIS redlines | 11/9/2020 9:49:18 AM |
View |
PCD Engineering Division
11/9/2020 9:48:40 AM |
SDI worksheet redlines | 11/9/2020 9:48:40 AM |
PCD Engineering Division
11/9/2020 9:04:49 AM |
Review 4 comments on the following documents will be uploaded by the project manager: -Drainage report -Construction Drawings (Please see comment below. Also, please be sure to include all recommended improvements indicated in the TIS for filing 10.) -TIS -SDI worksheet It appears that an older set of construction drawings was submitted as many of the previous corrections/updates are missing. The previously submitted construction documents are dated May 27, 2020. The submitted documents are dated September 27, 2019 matching the date on the original documents submitted for the 1st review. Please submit the latest documents for review. reviewed by: Daniel Torres danieltorres@elapasoco.com |
11/9/2020 9:04:49 AM | |
PCD Project Manager
7/14/2020 12:46:32 PM |
Project cannot be scheduled for public hearing until all engineering documents are corrected and resubmitted for another review. No planning comments at this time, project will be reassigned to Nina Ruiz for completion and scheduling. |
7/14/2020 12:46:32 PM | |
View |
PCD Project Manager
7/14/2020 12:45:20 PM |
TIS_V3, see attached | 7/14/2020 12:45:20 PM |
View |
PCD Project Manager
7/14/2020 12:44:50 PM |
Drainage Report_V3, see attached | 7/14/2020 12:44:50 PM |
View |
PCD Project Manager
7/14/2020 12:43:06 PM |
Construction Drawings_V3, see attached | 7/14/2020 12:43:06 PM |
PCD Engineering Division
7/13/2020 8:18:15 PM |
Review 3 comments on the following documents will be uploaded by the project manager: -Drainage report -Construction Drawings -TIS -Please update the SDI worksheet based on the revised pond design. Engineering comments on the following documents have been resolved: -GEC checklist -SWMP -SWMP Checklist -Plat -FAE -Soils Report Reviewed by: Daniel Torres danieltorres@elpasoco.com |
7/13/2020 8:18:15 PM | |
County Attorney - Development Review
7/1/2020 5:30:12 PM |
No further comments from County Attorney's Office - Development Review. | 7/1/2020 5:30:12 PM | |
View |
Colorado Springs Airport Advisory Commission
4/27/2020 9:22:27 AM |
The attached land use review summary with comments was presented and approved at the Airport Advisory Commission meeting held on April 22, 2020. | 4/27/2020 9:22:27 AM |
View |
EPC Health Department
4/20/2020 12:31:12 PM |
4/20/2020 12:31:12 PM | |
View |
PCD Project Manager
4/13/2020 4:35:32 PM |
TIS_V2 see attached redlines | 4/13/2020 4:35:32 PM |
View |
PCD Project Manager
4/13/2020 4:35:02 PM |
SWMP_V2 see attached redlines | 4/13/2020 4:35:02 PM |
View |
PCD Project Manager
4/13/2020 4:33:04 PM |
SWMP Checklist_V2 see attached redlines | 4/13/2020 4:33:04 PM |
View |
PCD Project Manager
4/13/2020 4:32:36 PM |
Soils and Geology Report_V2 see attached redlines | 4/13/2020 4:32:36 PM |
View |
PCD Project Manager
4/13/2020 4:32:00 PM |
Final Plat_V2 see attached redlines | 4/13/2020 4:32:00 PM |
View |
PCD Project Manager
4/13/2020 4:31:33 PM |
FAE_V2, see attached redlines | 4/13/2020 4:31:33 PM |
View |
PCD Project Manager
4/13/2020 4:31:02 PM |
Drainage Report_V2 see attached redlines | 4/13/2020 4:31:02 PM |
View |
PCD Project Manager
4/13/2020 4:30:25 PM |
Construction Drawings_V2 see attached redlines | 4/13/2020 4:30:25 PM |
PCD Engineering Division
4/13/2020 2:39:09 PM |
Review 2 comments on the following documents will be uploaded by the project manager: -Plat -Drainage report -Construction Drawings (includes GEC) -FAE -Soils Report: Per DCM Vol. 1 11.3.3, recommendations for the foundation preparation and embankment construction shall be provided for all permanent detention facilities. -GEC checklist: The one submitted is not the current approved checklist. Use the checklist attached to the GEC plan in the construction documents. -SWMP -SWMP checklist -TIS Engineering comments on the following documents have been resolved: -O&M -ESQCP -SDI worksheet Reviewed by: Daniel Torres danieltorres@elpasoco.com |
4/13/2020 2:39:09 PM | |
View |
County Attorney - Development Review
4/2/2020 8:45:25 AM |
1. No additional changes to SIA. 2. Please provide a legal description of the subdivision for the PID Petition. 3. Minor changes to the Detention Maintenance Agreement are attached. Please change Exhibit A to a legal description of the subdivision. |
4/2/2020 8:45:25 AM |
Pikes Peak Regional Building Department
4/1/2020 2:15:52 PM |
Regarding a request for approval of a final plat for The Glen at Widefield Filing No. 10, Enumerations has no further comments. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
4/1/2020 2:15:52 PM | |
View |
US Postal Service
3/26/2020 8:05:36 AM |
Developer can contact USPS to confirm pad location and mode of delivery Elaine Kelly Elaine.f.kelly@usps.gov Rita Minnard oreta.j.minnard@usps.gov |
3/26/2020 8:05:36 AM |
Mountain View Electric Association, Inc.
3/25/2020 1:20:35 PM |
Thank you for the opportunity to review this project. No additional comments at this time. Cathy Mountain View Electric Association, Inc. |
3/25/2020 1:20:35 PM | |
View |
Colorado Springs Airport Advisory Commission
3/23/2020 2:58:51 PM |
The attached land use review summary with comments was to be presented at the March 25, 2020 Airport Advisory Commission meeting prior to it being canceled. The summary will be presented at the next Commission meeting. | 3/23/2020 2:58:51 PM |
View |
EPC County Attorney's Office
3/23/2020 1:47:59 PM |
3/23/2020 1:47:59 PM | |
View |
EPC Health Department
1/29/2020 1:44:57 PM |
1/29/2020 1:44:57 PM | |
View |
Parks Advisory Board
12/12/2019 10:08:18 AM |
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (PAB Endorsed 12/11/2019) | 12/12/2019 10:08:18 AM |
View |
EPC Parks Department
12/12/2019 10:04:41 AM |
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (PAB Endorsed 12/11/2019) | 12/12/2019 10:04:41 AM |
PCD Project Manager
12/5/2019 8:36:08 AM |
General Comments: comments in blue are engineer, comments in green are planner. see comments from county attorney in regards to PID Make all necessary changes and resubmit construction plan review fees required prior to next submittal triage |
12/5/2019 8:36:08 AM | |
View |
PCD Project Manager
12/5/2019 8:30:30 AM |
Traffic Impact Study, see attached | 12/5/2019 8:30:30 AM |
View |
PCD Project Manager
12/5/2019 8:30:06 AM |
SWMP see attached | 12/5/2019 8:30:06 AM |
View |
PCD Project Manager
12/5/2019 8:29:43 AM |
Soils and Geology report, see attached, but the original soils and geology report needs to be submitted as well, as this project should stand on its own merit. | 12/5/2019 8:29:43 AM |
View |
PCD Project Manager
12/5/2019 8:28:49 AM |
SDI Worksheet, see attached | 12/5/2019 8:28:49 AM |
View |
PCD Project Manager
12/5/2019 8:28:27 AM |
PDB-BMP Operations Manual, see attached | 12/5/2019 8:28:27 AM |
View |
PCD Project Manager
12/5/2019 8:27:53 AM |
Mineral Rights Cert, see attached | 12/5/2019 8:27:53 AM |
View |
PCD Project Manager
12/5/2019 8:27:28 AM |
Letter of Intent, see attached | 12/5/2019 8:27:28 AM |
View |
PCD Project Manager
12/5/2019 8:27:03 AM |
GEC Plan, see attached | 12/5/2019 8:27:03 AM |
View |
PCD Project Manager
12/5/2019 8:26:38 AM |
Final Plt, see attached | 12/5/2019 8:26:38 AM |
View |
PCD Project Manager
12/5/2019 8:26:10 AM |
FAE, see attached | 12/5/2019 8:26:10 AM |
View |
PCD Project Manager
12/5/2019 8:25:47 AM |
ESQCP, see attached | 12/5/2019 8:25:47 AM |
View |
PCD Project Manager
12/5/2019 8:25:23 AM |
Drainage Report, see attached | 12/5/2019 8:25:23 AM |
View |
PCD Project Manager
12/5/2019 8:25:02 AM |
Construction Plans, see attached | 12/5/2019 8:25:02 AM |
View |
PCD Project Manager
12/5/2019 8:24:35 AM |
Adjacent Neighbor Notification, addresses missing, please see attached, when resubmitting make sure that new documents are added to the original documents, not in place of. | 12/5/2019 8:24:35 AM |
PCD Engineering Division
12/4/2019 12:33:52 PM |
Review 1 comments on the following documents will be uploaded by the project manager: -Plat -Drainage report -Construction Drawings -GEC -ESQCP -FAE -O&M (add PCD file number on cover sheet) -SDI worksheet -Soils Report -SWMP -TIS Please submit the following documents. These checklist/form can be found on the County website. The project manager shall add slots for uploading these documents in the resubmittal: GEC checklist SWMP checklist PBMP Applicability form Reviewed by: Daniel Torres danieltorres@elpasoco.com |
12/4/2019 12:33:52 PM | |
View |
County Attorney - Development Review
12/2/2019 2:58:06 PM |
Attached is a petition for inclusion of the subdivision in PID No. 2 for the purpose of partial payment of the EPC Road Impact Fee. If the developer wishes to join the PID, please complete the petition and return, along with a legal description of the entire subdivision in Word. The County Attorney's Office will attempt to schedule the inclusion hearing on the same date as the final plat is heard by the BoCC. If administrative plat approval has been requested, we will try to schedule the inclusion hearing as near to the administrative approval date as possible. The developer and County planner are responsible for keeping the County Attorney's Office informed of these dates. The inclusion must be approved before the plat is recorded. Developer is responsible for reimbursing the County Attorney's Office for the cost of publishing legal notice of the inclusion hearing, which is required by law. | 12/2/2019 2:58:06 PM |
View |
Colorado Division of Water Resources
11/25/2019 11:54:17 AM |
11/25/2019 11:54:17 AM | |
View |
County Attorney - Development Review
11/21/2019 12:20:56 PM |
1) Changes to the SIA are attached. Please submit future drafts in Word for ease of editing. 2) Regarding the Detention Maintenance Agreement, your letter of intent states that that the Metro District will be maintaining the facility. If this is accurate, then please prepare and submit the Agreement template for Metro District maintenance. Exhibit A must be a legal description of Filing 10. Exhibit B must be a legal description, and a depiction if desired, of the easement being granted to the County for access to and inspection of the detention facility. Please make sure when defining the easement that it is adjacent to or has legal access from a public roadway. |
11/21/2019 12:20:56 PM |
Pikes Peak Regional Building Department
11/19/2019 10:59:42 AM |
1. Per Regional Building Code, section RBC312.8 addresses must appear on plats. Submit a 100 scale copy of the plat to our office for addressing. Place an (xxxx) on all lots and tracts which will require an address, in the location the address will be needed. Once addressing is completed, the addresses will be returned so that they may be placed on the mylar prior to recording. 2. Prior to recording, Enumerations will review the mylar for addressing, title block, street names and floodplain statement. A fee of $10 per lot/tract addressed, payable to Pikes Peak Regional Building Department will be due at the time of mylar review. 3. Provide a copy of the final recorded plat to Enumerations. Approval of any plans submitted for this development will be pending receipt in our office of a copy of the final recorded plat. Floodplain has no comment or objection to this submittal |
11/19/2019 10:59:42 AM | |
View |
Mountain View Electric Association, Inc.
11/18/2019 2:25:12 PM |
11/18/2019 2:25:12 PM | |
View |
EPC Environmental Services
11/5/2019 10:49:26 AM |
11/5/2019 10:49:26 AM | |
911 Authority - El Paso/Teller County
11/4/2019 9:06:46 AM |
Buffalo Bur Trail is available and has been reserved for this project. Thank you. Justin |
11/4/2019 9:06:46 AM | |
EPC County Attorney's Office
10/31/2019 4:06:23 PM |
The County Attorney's Office will provide its review of water supply once a letter of sufficiency is received from the State Engineer's Office. 10/31/19 | 10/31/2019 4:06:23 PM |