Project Review Comments
- Project Name
- Grazing Yak Early Grading Permit
- Description
- The project proposes to construct a 35 megawatt solar farm facility on 270 acres of private land located southwest of the Town of Calhan, Colorado. Electricity generated by the project will interconnect into the Golden West Wind project substation via a 1-mile underground collection line, delivering power to Colorado Springs Utilities via an existing 29-mile generation tie line to the Jackson Fuller Substation. Location South of Washington Road, approximately 0.5 mile west of the intersection of Washington Road and Currier Road, Calhan, CO 80808
- Location
- Parcels
- 1200000040 1200000040 1200000056 1200000056 1200000276 1200000276 1200000339 1200000339 1200000387 1200000387 1200000388 1200000388
- Applicant
-
Core Consultants Inc.
Consultant Tina Brazil ( brazil@corecivil.com )
(215) 280-2370 Consultant Tina Brazil ( brazil@corecivil.com )
(215) 280-2370 - EA Number
- EA17223
- File Number
- EGP192
- Project Manager
- Kari Parsons
- Status
- Closed
- Created
- 2/27/2019 7:48:36 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
6/26/2019 9:37:52 AM |
Provide Owner/Developer signature on the following documents: A. The Grading and Erosion Control/ Site Development Plan. B. The Drainage Report. C. The Financial Assurance Estimate. Steve Kuehster 719-520-6813 6/26/19 |
6/26/2019 9:37:52 AM | |
View |
PCD Engineering Division
5/28/2019 12:53:12 PM |
See comment Letter (noted also PPR-19-020 comment letter) Provided By Steve Kuehster. |
5/28/2019 12:53:12 PM |
PCD Project Manager
5/28/2019 12:37:08 PM |
Prior to earthwork, the ER plan and 1041 must be approved. A pre-con meeting is required post approval of the plans. | 5/28/2019 12:37:08 PM | |
View |
PCD Project Manager
5/28/2019 12:35:07 PM |
Grading & Erosion Control Plans | 5/28/2019 12:35:07 PM |
View |
PCD Project Manager
5/28/2019 12:34:33 PM |
FAE Redlines | 5/28/2019 12:34:33 PM |
View |
PCD Project Manager
5/28/2019 12:34:19 PM |
Drainage Report Redlines | 5/28/2019 12:34:19 PM |
View |
PCD Project Manager
5/28/2019 12:33:56 PM |
BMP Redlines | 5/28/2019 12:33:56 PM |