Fountain Valley School Stealth CMRS
Description
New CMRS
Location
Parcels
5500000164 5500000164
Applicant
Q3 Consulting.com
Mark Paiz ( mark@q3consulting.com )
(303) 915-3428
Mark Paiz ( mark@q3consulting.com )
(303) 915-3428
File Number
AL1921
Project Manager
Lindsay Darden
Status
Closed
Created
11/20/2018 10:39:56 AM

View: Project Documents



Review Comments (19)

Link Agency Comment
View PCD Project Manager
2/13/2020 10:03:55 AM
Repeat Comment: The letter of intent still does not address the special use approval criteria. Please see attached and address these in the letter of intent. 2/13/2020 10:03:55 AM
PCD Project Manager
12/3/2019 8:50:56 PM
Please refer to comments on the related PPR site plan. The same comments apply to this site plan exhibit. 12/3/2019 8:50:56 PM
View PCD Project Manager
12/3/2019 8:48:39 PM
Mineral Rights Certification - in addition to the notarized letter indicating you were not able to find the mineral rights owners, you need to add on our mineral rights certification form as a second page to this upload item. I have attached the certification form below. 12/3/2019 8:48:39 PM
View PCD Project Manager
12/3/2019 8:40:06 PM
Letter of Intent:

Please indicate the number of carriers this tower will accommodate.

Also, as mentioned on the previous review, please address all of the review (specifically in the verbiage of the letter of intent) criteria that are required for approval of a special use (see attached below)
12/3/2019 8:40:06 PM
View EPC Health Department
10/5/2019 8:41:47 PM
10/5/2019 8:41:47 PM
PCD Project Manager
9/23/2019 9:58:02 AM
Schedule B Section II Number 8 of the title commitment indicates there are severed mineral rights for this parcel. This conflicts with the mineral rights certification that indicates there are not mineral rights owners other than the property owner.

1. If there are mineral rights owners, you are required to research them and contact them (or their descendants) to notify them of the proposed development via letter, similarly to how you notified the adjacent parcel owners or the proposed development. If you are unable to located them, you need to write a letter indicating the efforts you made to locate them and/or their descendants and that you were unable to do so.

2. Please modify and re-notarize the mineral rights certification to indicate there are mineral rights owners.

3. Upload the notification letter to the mineral rights estate owner(s) along with the revised mineral rights certification in the same document. Just add the notification letters on subsequent sheets after the mineral rights certification form.
9/23/2019 9:58:02 AM
View PCD Project Manager
9/23/2019 9:45:50 AM
Letter of Intent: It appears you uploaded comment response letter in place of the letter of intent. I will add an upload space for comment response letter for this submittal.

Because this is an application for special use, you need to address the Land Development Approval Criteria for the special use in your letter of intent. I have attached those to this comment.

The site plan reflects acreage of 624.18. The letter of intent reflects 937 acres. Please address this discrepancy so both are consistent.

Indicate the maximum number of carriers this tower will accommodate.
9/23/2019 9:45:50 AM
PCD Project Manager
9/23/2019 9:27:23 AM
Colocation Analysis - It is clear there is a gap in coverage but the coverage maps provided do not show what the coverage would be if you collocate on any or all of those existing towers within the target range. Per the Land Development Code, the applicant shall demonstrate that due to physical constraints, or economic or technological infeasibility, no such location or co-location is available.

Also indicate the proposed number of carriers that this tower can accommodate on the colocation analysis letter.
9/23/2019 9:27:23 AM
PCD Project Manager
9/23/2019 10:43:06 AM
Site Plan:

For the special use application add PCD File Number to the Site Plan Coversheet: PCD File Number: AL-19-021

Project Description section on the coversheet of the site plan: Indicate whether or not the tower will have lighting.

On the site plan (upper drawing on sheet 1) please provide a note indicating the distance to the nearest residential use from the proposed tower location. The Land Development Code sets forth setbacks for the tower in accordance to the distance from nearby residential uses and/or zoning districts.

Label the diameter of the proposed Microwave Antennae. Per Land Development Code, microwave antennae cannot exceed 4' diameter.

Provide a detail for the perimeter fencing of the lease area. Note that the Land Development Code requires that all accessory equipment shall be 100% screened from view. All equipment shelters shall be located within the lease area for the tower. No equipment storage shelter shall exceed 15 feet in heights. Equipment storage shelters shall be grouped as closely together as practical, so as to minimize impact on adjoining properties. We will be looking for fencing that provides 100% screening for the ground level accessory equipment and equipment shelter enclosures that do not exceed 15 feet in height.

The site plan reflects acreage of 624.18. The letter of intent reflects 937 acres. Please address this discrepancy so both are consistent.
9/23/2019 10:43:06 AM
View Colorado Springs Airport Advisory Commission
9/17/2019 8:05:49 AM
This item was reviewed and approved at the Airport Advisory Commission meeting held on August 28, 2019. The final land use review summary with comments is attached. 9/17/2019 8:05:49 AM
PCD Engineering Division
9/16/2019 5:53:34 PM
Comment provided by Elizabeth Nijkamp, 719-520-7852

An access permit is required prior to approval. this permit may be obtained at the Planning and /community Development Department.
9/16/2019 5:53:34 PM
View Colorado Springs Airport Advisory Commission
8/28/2019 4:01:07 PM
The attached land use review summary with comments was approved by the Airport Advisory Commission at the meeting held on August 28, 2019. 8/28/2019 4:01:07 PM
View Colorado Springs Airport Advisory Commission
8/1/2019 2:58:39 PM
The attached land use review summary with comments will be presented at the August 28, 2019 Airport Advisory Commission meeting. 8/1/2019 2:58:39 PM
View PCD Project Manager
8/1/2019 11:20:22 AM
Site Plan Drawing 8/1/2019 11:20:22 AM
View EPC Parks Department
8/1/2019 9:49:43 AM
El Paso County Community Services / Parks Final Comments - See Attached Documents (Administrative Comments Only) 8/1/2019 9:49:43 AM
PCD Engineering Division
7/31/2019 2:24:27 PM
Engineering has the following comments:
-In the letter of intent, discuss the anticipated traffic generated by the proposed tower.
-A driveway access permit must be obtained for the proposed access onto Goldfield Road.

Staff recommends utilizing appropriate erosion and Stormwater control measures during construction to prevent sediment runoff.

Thank you,

Beck Grimm
7/31/2019 2:24:27 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/29/2019 3:27:26 PM
Hey Len,

CSU has no comments for this review, approval is recommended.

Thanks,

Ryne
7/29/2019 3:27:26 PM
View El Paso County Conservation Dist
7/19/2019 1:02:23 PM
7/19/2019 1:02:23 PM
EPC Code Enforcement
7/18/2019 11:25:12 AM
Code Enforcement review not needed. 7/18/2019 11:25:12 AM