Project Review Comments
- Project Name
- Woodmen Hills Metropolitan District Lift Station #1
- Description
- Replace existing lift station.
- Location
- Parcels
- 4307300006 4307300006
- Applicant
-
JDS-Hydro Consultants, Inc.
Ryan Mangino ( rmangino@jdshydro.com )
(719) 227-0072 x103 Ryan Mangino ( rmangino@jdshydro.com )
(719) 227-0072 x103 - EA Number
- EA18116
- File Number
- PPR1841
- Project Manager
- Len Kendall
- Status
- Closed
- Created
- 8/7/2018 10:14:24 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
EPC County Attorney's Office
5/21/2019 2:32:32 PM |
No further comments from County Attorney's Office | 5/21/2019 2:32:32 PM | |
EPC County Attorney's Office
5/3/2019 12:12:00 PM |
Please delete the two comments still displayed on the Detention Maintenance Agreement before submitting an executed agreement. No further changes needed. | 5/3/2019 12:12:00 PM | |
EPC County Attorney's Office
5/2/2019 9:31:25 AM |
The Detention Maintenance Agreement I'm seeing in eDARP is still the redlined version with all of my proposed changes. If those changes are acceptable, please accept them within the document and submit a clean Word document for final review. | 5/2/2019 9:31:25 AM | |
EPC County Attorney's Office
4/12/2019 1:47:35 PM |
If the County's changes to the Detention Maintenance Agreement are acceptable, please accept all changes and resubmit a clean version for final review. | 4/12/2019 1:47:35 PM | |
EPC County Attorney's Office
4/3/2019 11:47:56 AM |
Same comment as March 20. Changes to detention maintenance agreement have not yet been made. | 4/3/2019 11:47:56 AM | |
PCD Project Manager
3/28/2019 9:20:48 AM |
No additional planning comments | 3/28/2019 9:20:48 AM | |
View |
EPC County Attorney's Office
3/20/2019 1:02:37 PM |
Changes to Detention Maintenance Agreement are attached. | 3/20/2019 1:02:37 PM |
View |
PCD Project Manager
3/19/2019 3:23:26 PM |
Landscape Plan redlined document. Trees for roadway must be within 20 feet of roadway. 1 tree per every 500 square feet of internal landscaping is required. If these cannot be met you can ask for an alternative landscaping request. Mark plan and include in Letter of intent. |
3/19/2019 3:23:26 PM |
PCD Engineering Division
3/19/2019 9:46:08 AM |
All engineering comments have been resolved. The project manager will upload the approved engineering documents when approved by the ECM administrator. | 3/19/2019 9:46:08 AM | |
View |
PCD Project Manager
2/27/2019 7:47:53 AM |
Financial Assurance Redlined document | 2/27/2019 7:47:53 AM |
View |
PCD Project Manager
2/27/2019 7:47:05 AM |
O and M redlined document | 2/27/2019 7:47:05 AM |
View |
PCD Project Manager
2/27/2019 7:46:33 AM |
SWMP redlined document | 2/27/2019 7:46:33 AM |
View |
PCD Project Manager
2/27/2019 7:45:19 AM |
Grading and Erosion Control redlined document | 2/27/2019 7:45:19 AM |
View |
PCD Project Manager
2/27/2019 7:44:41 AM |
Drainage Letter redlined document | 2/27/2019 7:44:41 AM |
View |
PCD Project Manager
2/27/2019 7:38:02 AM |
Landscape Plan redlined document | 2/27/2019 7:38:02 AM |
PCD Engineering Division
2/21/2019 9:21:25 AM |
Review #2 comments on the following documents will be uploaded by the project manager: -Drainage Letter -Grading and Erosion Control -SWMP -O&M -FAE Comments resolved on the following documents: - Letter of Intent - Site Development Plan Please submit the following documents as separate documents. They do not need to be removed from the SWMP report: ESQCP, Soil Report |
2/21/2019 9:21:25 AM | |
El Paso County Conservation Dist
10/12/2018 2:06:48 PM |
The Board of the El Paso County Conservation District have no comments at this time. | 10/12/2018 2:06:48 PM | |
View |
EPC Health Department
10/10/2018 1:25:56 PM |
10/10/2018 1:25:56 PM | |
View |
PCD Project Manager
10/5/2018 12:42:52 PM |
Grading and Erosion Control Plan redlined document | 10/5/2018 12:42:52 PM |
View |
PCD Project Manager
10/5/2018 12:41:53 PM |
Drainage Letter redlined document | 10/5/2018 12:41:53 PM |
View |
PCD Project Manager
10/5/2018 12:31:41 PM |
Multi-Discipline Team Comment Letter | 10/5/2018 12:31:41 PM |
View |
PCD Project Manager
10/5/2018 12:16:35 PM |
Site Development Plan redlined document | 10/5/2018 12:16:35 PM |
View |
PCD Project Manager
10/5/2018 12:15:22 PM |
Landscape Plan redlined document | 10/5/2018 12:15:22 PM |
View |
PCD Project Manager
10/5/2018 12:14:42 PM |
Elevations redlined document | 10/5/2018 12:14:42 PM |
View |
PCD Project Manager
10/5/2018 12:13:51 PM |
Application redlined document | 10/5/2018 12:13:51 PM |
View |
PCD Project Manager
10/5/2018 12:12:10 PM |
Letter of Intent redlined document | 10/5/2018 12:12:10 PM |
View |
PCD Engineering Division
10/4/2018 2:21:27 PM |
Review #1 comments on the following documents will be uploaded by the project manager: -Drainage Letter -Grading and Erosion Control -Letter of Intent -Site Development Plan Please submit the following additional documents: -SWMP, FAE, O&M, and Maintenance agreement |
10/4/2018 2:21:27 PM |
Pikes Peak Regional Building Department
9/27/2018 1:31:01 PM |
Enumerations/Floodplain has the following comments: 1. We have record of a permit for the existing electrical work at 12048 Falcon Hwy. We do not have record of the streel structure that is existing, that holds that has the holding tank for wastewater and steel structure that houses the pumping equipment. What address is associated with this structure. Is the address to this site 12048 Falcon Hwy? 2. The address to the site is the school at 12050 Falcon Hwy. The wastewater tank and pump room and 24’x25’ room with bathroom & electrical/control equipment will receive separate addresses, if all of the equipment and structures are not attached to the existing. Please clarify. 3. Very small portion of site has 100 floodplain. Should not affect this project. |
9/27/2018 1:31:01 PM | |
View |
Mountain View Electric Association, Inc.
9/26/2018 2:57:29 PM |
9/26/2018 2:57:29 PM | |
EPC County Attorney's Office
9/21/2018 10:11:01 AM |
No comments from County Attorney's Office at this time. | 9/21/2018 10:11:01 AM | |
Falcon Fire Protection District
9/21/2018 9:39:32 AM |
Falcon Fire has reviewed the proposed plot plan and supporting documents for the Woodmen Hills Meto. District lift station #1 project and has no objections or concerns with the proposal. Fire approves the proposed plot plan with no additional notes required. | 9/21/2018 9:39:32 AM |