Project Name
Rolling Thunder Business Park, Peak Gymnastics
Description
Site Development Plan
Location
Parcels
5311101010 5311101010 5311101011 5311101011
Applicant
Hammers Construction
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
File Number
PPR1835
Project Manager
Nina Ruiz
Status
Closed
Created
5/18/2018 7:46:56 AM

View: Project Documents



Review Comments (80)

Link Agency Comment
View EPC Code Enforcement
9/5/2019 10:54:12 AM
9/5/2019 10:54:12 AM
View EPC Code Enforcement
9/5/2019 10:54:00 AM
9/5/2019 10:54:00 AM
View EPC Code Enforcement
9/5/2019 10:53:46 AM
9/5/2019 10:53:46 AM
View EPC Code Enforcement
9/5/2019 10:53:33 AM
9/5/2019 10:53:33 AM
View EPC Code Enforcement
9/5/2019 10:53:15 AM
9/5/2019 10:53:15 AM
View EPC Code Enforcement
9/5/2019 10:53:00 AM
9/5/2019 10:53:00 AM
View EPC Code Enforcement
9/5/2019 10:52:23 AM
9/5/2019 10:52:23 AM
View EPC Code Enforcement
9/5/2019 10:51:24 AM
9/5/2019 10:51:24 AM
View EPC Code Enforcement
9/5/2019 10:51:07 AM
9/5/2019 10:51:07 AM
View EPC Code Enforcement
9/5/2019 10:50:53 AM
9/5/2019 10:50:53 AM
View EPC Code Enforcement
9/5/2019 10:50:38 AM
9/5/2019 10:50:38 AM
View EPC Code Enforcement
9/5/2019 10:50:23 AM
9/5/2019 10:50:23 AM
View EPC Code Enforcement
9/5/2019 10:50:08 AM
9/5/2019 10:50:08 AM
View EPC Code Enforcement
9/5/2019 10:49:30 AM
9/5/2019 10:49:30 AM
View EPC Code Enforcement
9/5/2019 10:49:11 AM
9/5/2019 10:49:11 AM
View EPC Code Enforcement
9/5/2019 10:48:47 AM
9/5/2019 10:48:47 AM
View EPC Code Enforcement
9/5/2019 10:48:31 AM
9/5/2019 10:48:31 AM
View EPC Code Enforcement
9/5/2019 10:48:08 AM
9/5/2019 10:48:08 AM
View EPC Code Enforcement
9/5/2019 10:47:53 AM
9/5/2019 10:47:53 AM
View EPC Code Enforcement
9/5/2019 10:47:36 AM
9/5/2019 10:47:36 AM
View EPC Code Enforcement
9/5/2019 10:47:20 AM
9/5/2019 10:47:20 AM
View EPC Code Enforcement
9/5/2019 10:47:09 AM
9/5/2019 10:47:09 AM
View EPC Code Enforcement
9/5/2019 10:46:54 AM
9/5/2019 10:46:54 AM
View EPC Code Enforcement
9/5/2019 10:46:38 AM
9/5/2019 10:46:38 AM
View EPC Code Enforcement
9/5/2019 10:46:25 AM
9/5/2019 10:46:25 AM
View EPC Code Enforcement
9/5/2019 10:46:09 AM
9/5/2019 10:46:09 AM
View EPC Code Enforcement
9/5/2019 10:45:57 AM
9/5/2019 10:45:57 AM
View EPC Code Enforcement
9/5/2019 10:45:46 AM
9/5/2019 10:45:46 AM
View EPC Code Enforcement
9/5/2019 10:45:33 AM
9/5/2019 10:45:33 AM
View EPC Code Enforcement
9/5/2019 10:45:16 AM
9/5/2019 10:45:16 AM
View EPC Code Enforcement
9/5/2019 10:44:57 AM
9/5/2019 10:44:57 AM
View EPC Code Enforcement
9/5/2019 10:44:44 AM
9/5/2019 10:44:44 AM
View EPC Code Enforcement
9/5/2019 10:44:27 AM
9/5/2019 10:44:27 AM
View EPC Code Enforcement
9/5/2019 10:44:14 AM
9/5/2019 10:44:14 AM
View EPC Code Enforcement
9/5/2019 10:44:03 AM
9/5/2019 10:44:03 AM
View EPC Code Enforcement
9/5/2019 10:43:49 AM
9/5/2019 10:43:49 AM
View PCD Engineering Division
1/23/2019 10:38:11 AM
All engineering documents have been approved and will be uploaded by the project manager. 1/23/2019 10:38:11 AM
PCD Project Manager
1/16/2019 11:44:19 AM
Per engineer comments, the application is not yet ready for approval. 1/16/2019 11:44:19 AM
View PCD Engineering Division
1/16/2019 11:23:52 AM
Please see attached the submitted deviation request with engineering comments provided. 1/16/2019 11:23:52 AM
View EPC Health Department
1/9/2019 8:55:42 AM
1/9/2019 8:55:42 AM
EPC County Attorney's Office
12/27/2018 10:38:41 AM
The Detention Maintenance Agreement provided, recorded in 2008, applies to detention basins on Tract A and Lots 9, 10 and 11, Rolling Thunder Business Park. The drainage report for this project indicates that runoff will flow to an existing pond on Lots 9 & 10. Based on this information, it appears that no new Detention Maintenance Agreement is needed. 12/27/2018 10:38:41 AM
PCD Engineering Division
12/19/2018 3:02:44 PM
It does not appear the a deviation was submitted for the water quality exclusion.

Per new policy, provide a deviation request for drainage Basin D not being treated for water quality. ECM I.7.1.B states that "WQCV shall be provided for the total site..."

For justification, use the MS4 permit Section 4.a.iv.(A).
12/19/2018 3:02:44 PM
Falcon Fire Protection District
12/5/2018 8:29:09 AM
Falcon Fire has no new comments 12/5/2018 8:29:09 AM
View PCD Project Manager
12/4/2018 12:43:30 PM
Drainage Redlines 12/4/2018 12:43:30 PM
PCD Engineering Division
12/4/2018 10:37:40 AM
Engineering comments have been resolved on the following documents:
-GEC
-SWMP

Engineering comments can be found on the following document, which will be uploaded by the project manager:
-Drainage Report

Engineering documents may be submitted for signature with the appropriate changes.

Note: Per new policy, provide a deviation request for drainage Basin D not being treated for water quality. ECM I.7.1.B states that "WQCV shall be provided for the total site..."

For justification, use the MS4 permit Section 4.a.iv.(A).
12/4/2018 10:37:40 AM
PCD Project Manager
12/3/2018 1:17:10 PM
The only remaining comment is regarding the landscaping within the ROW. 12/3/2018 1:17:10 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
11/26/2018 11:00:21 AM
Hey Nina,

CSU has no action items at this time and is recommending approval. Let me know if you need anything further from me.

Thanks -- Ryne
11/26/2018 11:00:21 AM
EPC County Attorney's Office
11/26/2018 10:19:21 AM
1. Please definitively state whether the existing water quality control pond has an existing detention maintenance agreement. If so, please provide a copy.

2. If there is no existing detention maintenance agreement for the existing pond, one must be provided for it, along with any other detention or water quality improvement. The agreement must comply with our approved template to be signed by both the property owner and the metro district.
11/26/2018 10:19:21 AM
View EPC Health Department
11/7/2018 8:46:21 PM
11/7/2018 8:46:21 PM
View PCD Project Manager
11/7/2018 4:54:34 PM
Elevation Redlines 11/7/2018 4:54:34 PM
View PCD Project Manager
11/7/2018 4:53:54 PM
Landscape Redlines 11/7/2018 4:53:54 PM
View PCD Project Manager
11/7/2018 4:52:48 PM
GEC Redlines 11/7/2018 4:52:48 PM
View PCD Project Manager
11/7/2018 4:52:32 PM
SWMP Redlines 11/7/2018 4:52:32 PM
View PCD Project Manager
11/7/2018 4:52:15 PM
Drainage Redlines 11/7/2018 4:52:15 PM
View PCD Project Manager
11/7/2018 4:51:56 PM
Site Development Redlines 11/7/2018 4:51:56 PM
View PCD Engineering Division
11/5/2018 5:22:20 PM
Engineering comments have been resolved on the following documents:
-ESQCP
-O&M
-Site Plan
-Letter of Intent
-FAS
-Vacation Plan

Engineering has comments on the following documents:
-Drainage Letter
-SWMP
-GEC

Please see attached the SWMP and GEC checklist
11/5/2018 5:22:20 PM
PCD Project Manager
10/31/2018 3:29:09 PM
Redlines and additional comments will be uploaded following the completion of the PCD Engineering Review. 10/31/2018 3:29:09 PM
View Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/24/2018 2:27:18 PM
Hey Nina,

Attached is the review memo for the subject application. CSU has no action items at this time and recommending approval. Let me know if you need anything further from me.

Thanks -- Ryne
10/24/2018 2:27:18 PM
Falcon Fire Protection District
10/23/2018 3:52:33 PM
Falcon Fire has no further comments. 10/23/2018 3:52:33 PM
Woodmen Road Metro
10/23/2018 8:53:40 AM
REVISED due to building square footage change:
In response to the proposed project this parcel will be subject to the Commercial Woodmen Road Metropolitan District Fee’s and mill levies

This parcel is already Platted no Platting Fees due at time of final plat.

Building Permit Fees are due at time of Building Permit.
Building Permit Fees of $1.10/Sq Foot x 14,250(Square Foot Building) = $15,675.00

Please contact our office should there be any questions.
10/23/2018 8:53:40 AM
EPC County Attorney's Office
10/22/2018 10:50:44 AM
If a detention maintenance agreement for the pond on this site has already been executed and recorded, for example with the final plat, then please upload a copy of that agreement. If there is not an existing agreement, then a new agreement must be created that includes the property owner and the entity responsible for maintenance, whether the property owners' association or the metro district. 10/22/2018 10:50:44 AM
PCD Project Manager
9/13/2018 7:52:12 AM
On Tuesday September 11, 2018 staff conducted a site visit of the existing Peak Gymnastics facility located to the north of the subject parcel in order to gain a better understanding of anticipated traffic and parking needs. Per the Peak Gymnastics website on this date four classes ended at 5:15 and four new class begun at 5:30. Staff observed the following:
5:15- 25 cars in the parking lot
5:20- 15 cars in the parking lot
5:25- 16 cars in the parking lot
5:30- 13 cars in the parking lot
5:35- 19 cars in the parking lot

Based upon observation it did not appear as though parents were dropping their children off and leaving the facility. Some parents did choose to wait in their cars but it did not appear as though they were leaving he parking lot. Based upon the highest number of vehicles observed of 25 spaces, this would be the equivalent of 1 space per 200 sq ft. 1 space per 200 sq ft is what has been approved in the past for gymnastic facilities in unincorporated El Paso County.

Staff also visited Aerials Gymnastics within the City limits located at 3536 Hartsel Dr. This facility is 20,700 sq ft in size. Based upon their website they have the potential for 10 classes to be occurring between 5:40-6:40pm on Tuesdays. Staff arrived at the site at 5:50pm and observed 29 cars in the parking lot. This is equivalent to 1 space per 713 sq ft. The website did not provide enough information for it to be determined if the classes were full, or if all of the available classes were being conducted. The facility is also a part of a larger shopping center development so it is difficult to determine if those in the designated parking area were the only vehicles for the use. Staff does not feel as though this is an accurate depiction of anticipated traffic.

Your existing facility is 5,000 sq ft in size and the new facility is proposed to be 14,800 sq ft in size. If your existing facility were to be tripled in size with the same operation, and based upon observation in the field, we would require 75 parking spaces whereas you are proposing 66. This is a deficiency of 9 parking spaces.

The PCD Director will not approve the alternative parking ratio requested of 1 space per 250 sq ft. The PDC Director will allow for an alternative parking ratio of 1 space per 200 sq ft. This will require the building size to be reduced, or the site to be revised to allow for additional parking.
9/13/2018 7:52:12 AM
PCD Project Manager
8/29/2018 10:17:47 AM
The PCD Deputy Director requests that the alternative landscape request be submitted via a separate letter that includes additional information pertaining to Section 6.2.5.D.1.a.vi be added. The request will then be reconsidered for approval/denial. Any administrative decision is appealable within 30 dats from the date the decision is made. 8/29/2018 10:17:47 AM
View EPC Health Department
8/14/2018 6:25:09 PM
8/14/2018 6:25:09 PM
View PCD Project Manager
8/2/2018 7:32:12 AM
MDT Letter 8/2/2018 7:32:12 AM
View PCD Project Manager
8/2/2018 7:30:48 AM
Landscape Redline 8/2/2018 7:30:48 AM
View PCD Project Manager
8/2/2018 7:30:14 AM
SWMP Redline 8/2/2018 7:30:14 AM
View PCD Project Manager
8/2/2018 7:29:48 AM
LOI Redlines 8/2/2018 7:29:48 AM
View PCD Project Manager
8/2/2018 7:29:26 AM
Site Development Redline 8/2/2018 7:29:26 AM
View PCD Project Manager
8/2/2018 7:27:10 AM
O&M Redline 8/2/2018 7:27:10 AM
View PCD Project Manager
8/2/2018 7:26:52 AM
GEC Redline 8/2/2018 7:26:52 AM
View PCD Project Manager
8/2/2018 7:25:57 AM
ESQCP Redline 8/2/2018 7:25:57 AM
View PCD Project Manager
8/2/2018 7:25:41 AM
Drainage Redlines 8/2/2018 7:25:41 AM
View PCD Engineering Division
7/31/2018 9:31:39 AM
Review 1 Engineering comments have been provided on the following documents, which will be uploaded by the project manager:
-Drainage
-ESQCP
-FAS
-GEC
-O&M
-Site Plan
-LOI
-SWMP

Provide a copy of the maintenance agreement for the pond.

Attached are the checklists for the GEC and SWMP showing the missing items.
7/31/2018 9:31:39 AM
PCD Project Manager
7/25/2018 2:31:58 PM
In discussion with the PCD Deputy Director the alternative parking ratio would not be supported given the justification and information provided. The applicant will need to either comply with the parking requirement of 1/150 or supply additional supporting information to justify the request. 7/25/2018 2:31:58 PM
View EPC County Attorney's Office
7/25/2018 2:22:02 PM
Comments to Detention Maintenance Agreement are attached. 7/25/2018 2:22:02 PM
View Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/24/2018 11:51:24 AM
Hey Nina,
Attached is a review memo fro the subject application. There is an information item pertaining to the gas line, but no action items. Approval is recommended. Let me know if you need anything else from me.

Thanks -- Ryne
7/24/2018 11:51:24 AM
PCD Project Manager
7/23/2018 2:03:33 PM
1. All signs require a sign permit.
2. All proposed improvements must be installed prior to receiving a CO for the building.
3. A driveway permit and ESQCP permit are required. Financial assurance must be submitted prior to the pre-con meeting.
4. The proposed light exceeds the height allowance listed in the PUD.
5. It does not appear as though the building meets the architectural guidelines of the PUD. Please submit proof of approval from the POA.
6. The following note should be added to all site development plans or non-residential site plans, as applicable, prior to PCD approval:
The parties responsible for this plan have familiarized themselves with all current accessibility criteria and specifications and the proposed plan reflects all site elements required by the applicable ADA design standards and guidelines as published by the United States Department of Justice. Approval of this plan by El Paso County does not assure compliance with the ADA or any regulations or guidelines enacted or promulgated under or with respect to such laws.
7. Add PPR-18-035 to all submittal items.
7/23/2018 2:03:33 PM
Woodmen Road Metro
7/17/2018 9:32:20 AM
In response to the proposed project this parcel will be subject to the Commercial Woodmen Road Metropolitan District Fee’s and mill levies

This parcel is already Platted no Platting Fees due at time of final plat.

Building Permit Fees are due at time of Building Permit.
Building Permit Fees of $1.10/Sq Foot x 14,800 (Square Foot Building) = $16,280.00

Please contact our office should there be any questions.
7/17/2018 9:32:20 AM
View Falcon Fire Protection District
7/16/2018 4:24:15 PM
7/16/2018 4:24:15 PM