Project Review Comments
- Project Name
- Redtail Ranch Final Plat
- Description
- Final plat to develop 12 five (5) acre lots
- Location
- The properties are located near the northwest corner of the Vollmer Road and Shoup Road intersection
- Parcels
- 5209000128 5209000128 5209000129 5209000129 5209002006 5209002006 5209002008 5209002008
- Applicant
-
NES Inc.
Marc Whorton ( mwhorton@classicconsulting.net ) Marc Whorton ( mwhorton@classicconsulting.net ) - EA Number
- EA-17-025
- File Number
- SF1821
- Project Manager
- Kari Parsons
- Status
- Closed
- Created
- 4/2/2018 9:44:43 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
6/12/2020 12:24:06 PM |
The revised documents are ready for approval. Approved versions will be uploaded to EDARP when complete. | 6/12/2020 12:24:06 PM | |
PCD Project Manager
6/11/2020 12:34:18 PM |
Planning has no comment, Please continue to work with review engineer. | 6/11/2020 12:34:18 PM | |
PCD Engineering Division
6/2/2020 6:10:04 PM |
Provide signed and stamped CD sheets and FDR addendum. Note to PM: The revised O&M document needs to be recorded to supersede the previous version recorded with the PDB/BMP agreement. . |
6/2/2020 6:10:04 PM | |
View |
PCD Engineering Division
4/23/2019 1:53:52 PM |
See comment letter regarding SWMP field updates, SIA and PDB/BMP agreement. Engineering documents submitted are ready for approval. | 4/23/2019 1:53:52 PM |
View |
PCD Project Manager
4/3/2019 12:06:03 PM |
Drainage Redlines 4 | 4/3/2019 12:06:03 PM |
View |
PCD Project Manager
4/3/2019 12:03:45 PM |
CD Summary 4 | 4/3/2019 12:03:45 PM |
View |
PCD Project Manager
4/3/2019 12:02:58 PM |
CDS Redlines 4 | 4/3/2019 12:02:58 PM |
View |
PCD Engineering Division
4/3/2019 11:49:26 AM |
See comment letter and redlines. | 4/3/2019 11:49:26 AM |
PCD Project Manager
3/4/2019 9:44:57 AM |
No redlines for the drainage report were available to upload. Please call Jeff Rice. | 3/4/2019 9:44:57 AM | |
View |
PCD Project Manager
3/4/2019 9:44:20 AM |
CD redlines 3 | 3/4/2019 9:44:20 AM |
View |
PCD Project Manager
3/4/2019 9:43:52 AM |
FAE redlines 3 | 3/4/2019 9:43:52 AM |
View |
PCD Project Manager
3/4/2019 9:43:21 AM |
LOI comments 3 | 3/4/2019 9:43:21 AM |
View |
PCD Project Manager
3/4/2019 9:42:46 AM |
SWMP Redlines 3 | 3/4/2019 9:42:46 AM |
View |
PCD Project Manager
3/4/2019 9:42:15 AM |
Plat Redlines 3 | 3/4/2019 9:42:15 AM |
View |
PCD Engineering Division
3/1/2019 8:58:26 AM |
See comment letter and redlines. | 3/1/2019 8:58:26 AM |
Black Forest Trails Association
2/21/2019 11:38:43 PM |
On the Final Plat there are two oversized drainage easements overlying the trail easement on the north side of Sanctuary Pine Drive. There is a 40' Public Drainage Easement on the SW corner of Lot 11 and a Drainage Easement on Lot 9. When we initially discussed the placement of the trail on either the north or south side of Sanctuary Pine, comments were made that the north side would likely be more suitable. Are these drainage easements on the north side going to impair the ability of a trail to be placed and used within the designated 10' easement? | 2/21/2019 11:38:43 PM | |
PCD Project Manager
1/3/2019 7:43:34 AM |
Please see uploaded redlines and revise documents. You can provide signatures on engineering documents for signature and approval if comments are addressed. | 1/3/2019 7:43:34 AM | |
View |
PCD Project Manager
1/3/2019 7:42:35 AM |
CDs redlines 2 | 1/3/2019 7:42:35 AM |
View |
PCD Project Manager
1/3/2019 7:41:30 AM |
Drainage report 2 redlines | 1/3/2019 7:41:30 AM |
View |
PCD Project Manager
1/3/2019 7:40:20 AM |
MS4 Redlines | 1/3/2019 7:40:20 AM |
View |
PCD Project Manager
1/3/2019 7:39:32 AM |
LOI redlines 2 | 1/3/2019 7:39:32 AM |
View |
PCD Project Manager
1/3/2019 7:35:49 AM |
Plat Redlines 2 | 1/3/2019 7:35:49 AM |
View |
PCD Engineering Division
1/2/2019 5:09:08 PM |
(SWMP redlines) | 1/2/2019 5:09:08 PM |
View |
PCD Engineering Division
1/2/2019 5:08:31 PM |
(FAE redlines) | 1/2/2019 5:08:31 PM |
View |
PCD Engineering Division
1/2/2019 5:07:57 PM |
See comment letter and redlines. | 1/2/2019 5:07:57 PM |
Black Forest Trails Association
12/31/2018 11:55:43 PM |
The trails will be a valuable asset to the residents of Redtail Ranch and to the connectivity of the Black Forest community. Well done! Please continue to forward any further updates to us. |
12/31/2018 11:55:43 PM | |
Black Forest Land Use Committee
12/27/2018 4:27:11 PM |
The Black Forest Land Use Committee recommends approval of this final plat. | 12/27/2018 4:27:11 PM | |
View |
EPC Parks Department
12/21/2018 4:10:28 PM |
El Paso County Community Services / Parks Final Comments, Review #2 (PAB Endorsed 09/12/2018) | 12/21/2018 4:10:28 PM |
View |
Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
12/20/2018 9:10:21 PM |
12/20/2018 9:10:21 PM | |
Pikes Peak Regional Building Department
12/20/2018 2:50:32 PM |
Enumerations/Floodplain has the following comments: 1. Change the floodplain statement. See DP comments. |
12/20/2018 2:50:32 PM | |
911 Authority - El Paso/Teller County
12/11/2018 10:18:56 AM |
Street names previously approved No action for 911 Thank you Justin |
12/11/2018 10:18:56 AM | |
View |
PCD Project Manager
9/4/2018 12:32:51 PM |
MDT Review 1 Letter | 9/4/2018 12:32:51 PM |
View |
PCD Project Manager
9/4/2018 12:30:52 PM |
SWMP Redlines Review 1 | 9/4/2018 12:30:52 PM |
View |
PCD Project Manager
9/4/2018 12:30:25 PM |
Plat Redlines Review 1 | 9/4/2018 12:30:25 PM |
View |
PCD Project Manager
9/4/2018 12:29:57 PM |
Letter of Intent Redlines Review 1 | 9/4/2018 12:29:57 PM |
View |
PCD Project Manager
9/4/2018 12:28:12 PM |
Construction Drawing Redlines Review 1 | 9/4/2018 12:28:12 PM |
View |
PCD Engineering Division
9/4/2018 12:07:10 PM |
See comment letter and redlines. | 9/4/2018 12:07:10 PM |
Black Forest Land Use Committee
8/30/2018 9:42:14 AM |
The Black Forest Land Use Committee commends the applicant for following the Black Forest Preservation Plan in keeping a 5-acre average for density in the timbered area. The committee objects to the requirement for the 90-foot preservation ROW required of the applicant. Vollmer Road is a minor arterial and should stay that way. An increase from the 60-foot ROW to 180 feet is a requirement that the Highway Advisory Committee has not discussed or vetted and the 2060 MTCP requirement for an "upgrade" to this road in the future must not require such a large ROW preservation. With all the other properties along Vollmer (as well as many other minor arterials in the Black Forest) that would be severely impacted by Vollmer becoming a 4-lane road, the likelyhood of such an upgrade is highly improbable. A total ROW of 60-80 feet should be the maximum. The Land Use Committee fully supports the inputs and suggestions submitted by the Black Forest Trails Association. |
8/30/2018 9:42:14 AM | |
Pikes Peak Regional Building Department
8/29/2018 3:31:47 PM |
Enumerations has the following comments: 1. Sanctuary in the Pines Fil No 1 was projected years ago for the property to the east across Vollmer Road; which this subdivision may have reserved the street name Sanctuary Pine Drive. Is this for the same development? If the current location of existing Sanctuary Pine Drive is not a logical continuation, then a new street name will need to be chosen and approved. An email from El Paso/Teller County E-911 Authority is required, for this purpose. 2. Standard Final plat comments: ENUMERATIONS/FLOODPLAIN WILL REVIEW THE MYLAR PRIOR TO PLAT FOR ADDRESS PLACEMENT, ROAD NAMING, TITLE BLOCK, & FLOODPLAIN STATEMENT. $10.00 PER LOT & TRACT FEE WILL BE DUE AT THE TIME OF THE REVIEW OF THE MYLAR. IF AN ADDRESS IS NOT NEEDED ON A TRACT THEN NO FEE APPLIES. CHECK SHOULD BE MADE OUT TO PIKES PEAK REGIONAL BUILDING DEPARTMENT. PAID DIRECTLY TO ENUMERATIONS DEPARTMENT. A COPY OF THE FINAL RECORDED PLAT IS REQUIRED PRIOR TO PLAN SUBMITTAL FOR RESIDENTAL. A COPY OF THE FINAL RECORDED PLAT IS REQUIRED PRIOR TO APPROVAL IN ENUMERATIONS DEPARTMENT ON ANY COMMERCIAL PLANS SUBMITTAL. Floodplain has the following comment: The effect map date is March 17, 1997 not the 16th. |
8/29/2018 3:31:47 PM | |
View |
EPC Parks Department
8/29/2018 10:12:02 AM |
El Paso County Community Services/Parks Preliminary Comments | 8/29/2018 10:12:02 AM |
View |
Black Forest Trails Association
8/28/2018 3:54:48 PM |
8/28/2018 3:54:48 PM | |
View |
Black Forest Trails Association
8/28/2018 3:18:46 PM |
8/28/2018 3:18:46 PM | |
Black Forest Fire Protection District
8/28/2018 9:11:40 AM |
BFFRPD has reviewed the Preliminary Plan, Final Plat, Fire Protection Plan and all additional documents. BFFRPD agrees with current design of roadways, and cul-de-sacs for access and egress. BFFRPD would ask developer to consider providing permanent connectivity, via dedicated fire only access road (gated and marked) from the proposed new Ward Lane cul-de-sac to the dead-end Linwood Ln. Additionally BFFRPD would like consideration of a fire only access road in the 15' easement along the northern edge of Lot 1. BFFRPD would then work with adjacent property owners to the west to secure the necessary easements to create a continuous fire only access road from the end of the existing Ward Lane cul-de-sac to the Meadow Glen Lane cul-de-sac. The intention of the two proposed fire only access roads is to provide faster response times to the proposed development and provide additional access/egress options for the safety of the public during emergency events. Our proposal is in alignment with Firewise recommendations, and our Community Wildfire Protection Plan (Pg. 72, Table 2, "Access/Egress Improvements", "Create/improve dead end turn arounds"). | 8/28/2018 9:11:40 AM | |
View |
Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
8/26/2018 5:35:49 PM |
8/26/2018 5:35:49 PM | |
View |
Mountain View Electric Association, Inc.
8/22/2018 12:42:38 PM |
8/22/2018 12:42:38 PM | |
View |
911 Authority - El Paso/Teller County
8/20/2018 9:12:03 AM |
See attached | 8/20/2018 9:12:03 AM |