View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Engineering Division
7/3/2018 9:13:08 AM |
See the attached traffic control plan for the Condition of Approval. | 7/3/2018 9:13:08 AM |
View |
PCD Engineering Division
4/3/2018 1:55:31 PM |
The attached documents are not reviewed. These are the traffic impact study and traffic control plans associated with the original approved site development plan (PPR1424). Per the email sent on January 16, 2018 (attached) in order to amend the traffic control plan an updated traffic memorandum and updated traffic control exhibit are required. The traffic memorandum will evaluate the as-built traffic condition and provide recommendations. |
4/3/2018 1:55:31 PM |