Project Review Comments

Back to List


Project Name
Paint Brush Hills Filing No. 13E
Description
Phased plat for 102 single-family lots
Location
Parcel is located north Londonderry Drive west of Towner
Parcels
5226101007 5226101007
Applicant
Classic Engineering & Consulting
Marc Whorton ( mwhorton@classicconsulting.net )
(719) 785-2802
Marc Whorton ( mwhorton@classicconsulting.net )
(719) 785-2802
EA Number
17-149
File Number
SF189
Project Manager
Kari Parsons
Status
Closed
Created
1/3/2018 3:13:01 PM

View: Project Documents



Review Comments (42)

Link Agency Comment
View EPC Parks Department
4/16/2019 2:35:14 PM
El Paso County Community Services / Parks. Due to missed deadline, please refer to the original recommendations, as endorsed by the Park Advisory Board on September 12, 2018 (see attachments). 4/16/2019 2:35:14 PM
View EPC County Attorney's Office
4/5/2019 11:25:31 AM
4/5/2019 11:25:31 AM
PCD Engineering Division
3/11/2019 11:16:53 AM
No comments. Engineering documents were approved on 10/29/2018. 3/11/2019 11:16:53 AM
EPC County Attorney's Office
3/1/2019 10:55:50 AM
With respect to SIA and Detention Maintenance Agreement, same comments as October 1. 3/1/2019 10:55:50 AM
View Colorado Division of Water Resources
2/28/2019 6:42:52 AM
2/28/2019 6:42:52 AM
PCD Project Manager
10/29/2018 10:14:27 AM
This plat application is awaiting a finding of sufficiency from the State Engineers Office and the County Attorney. 10/29/2018 10:14:27 AM
View EPC Health Department
10/26/2018 3:05:51 PM
10/26/2018 3:05:51 PM
PCD Engineering Division
10/29/2018 9:07:23 AM
Review 3: Engineering comments are resolved. 10/29/2018 9:07:23 AM
View Colorado Division of Water Resources
10/16/2018 2:51:52 PM
10/16/2018 2:51:52 PM
PCD Project Manager
10/15/2018 1:22:07 PM
Please call Gilbert or Daniel if you have questions on engineering documents. The GEC plan will need to be submitted as requested. 10/15/2018 1:22:07 PM
View PCD Project Manager
10/15/2018 1:19:05 PM
TIS V_2 Redlines 10/15/2018 1:19:05 PM
View PCD Project Manager
10/15/2018 1:18:10 PM
Plat V_2 Redlines 10/15/2018 1:18:10 PM
View PCD Project Manager
10/15/2018 1:17:40 PM
FAE V_2 Redlines 10/15/2018 1:17:40 PM
View PCD Project Manager
10/15/2018 1:17:19 PM
Drainage Redlines Version 2 10/15/2018 1:17:19 PM
View PCD Project Manager
10/15/2018 1:16:56 PM
CD Redlines Version 2 10/15/2018 1:16:56 PM
PCD Engineering Division
10/15/2018 9:43:45 AM
Review 2 comments on the following documents will be uploaded by the Project Manager:
-Drainage Report
-Construction Drawings
-Financial Assurance
-Plat
-Traffic Impact Study

* Unresolved. The uploaded GEC was for the pre-development grading. Submit a Grading and Erosion Control Plan that's specific to the proposed improvements for this filing. Can be a part of the Construction Drawings.

Comments resolved on the following documents:
-O&M
-SDI Worksheet
-SWMP
-ESQCP
10/15/2018 9:43:45 AM
EPC County Attorney's Office
10/1/2018 12:46:21 PM
Please submit Detention Maintenance Agreement in Word for ease of editing. Please confirm that detention pond will not be maintained by HOA or Metro District, but by developer. 10/1/2018 12:46:21 PM
View EPC County Attorney's Office
10/1/2018 12:43:20 PM
Comments to SIA attached. Please submit all future drafts in Word for ease of editing. 10/1/2018 12:43:20 PM
View Parks Advisory Board
10/1/2018 9:52:18 AM
El Paso County Community Services/Parks Final Comments (PAB Endorsed 09/12/2018) 10/1/2018 9:52:18 AM
View Parks Advisory Board
9/19/2018 11:16:29 AM
El Paso County Community Services/Parks Final Comments (PAB Endorsed 09/12/2018) 9/19/2018 11:16:29 AM
View EPC Health Department
9/17/2018 7:28:36 PM
9/17/2018 7:28:36 PM
View EPC Parks Department
8/28/2018 3:05:18 PM
El Paso County Community Services/Parks Preliminary Comments 8/28/2018 3:05:18 PM
View PCD Project Manager
8/27/2018 10:31:19 AM
MDT Review 1 Letter 8/27/2018 10:31:19 AM
View PCD Project Manager
8/27/2018 10:30:07 AM
SDI 8/27/2018 10:30:07 AM
View PCD Project Manager
8/27/2018 10:29:49 AM
Traffic Study (TIS) Redlines Review 1 8/27/2018 10:29:49 AM
View PCD Project Manager
8/27/2018 10:28:15 AM
Plat Redlines Review 1 8/27/2018 10:28:15 AM
View PCD Project Manager
8/27/2018 10:27:15 AM
LOI Redlines Review 1 8/27/2018 10:27:15 AM
View PCD Project Manager
8/27/2018 10:26:58 AM
FAE Redlines Review 1 8/27/2018 10:26:58 AM
View PCD Project Manager
8/27/2018 10:25:43 AM
Drainage Report Redlines Review 1 8/27/2018 10:25:43 AM
View PCD Project Manager
8/27/2018 10:25:15 AM
CD Redlines Review 1 8/27/2018 10:25:15 AM
View PCD Project Manager
8/27/2018 10:24:58 AM
BMP O M Plan Redlines Review 1 8/27/2018 10:24:58 AM
View PCD Project Manager
8/27/2018 10:24:28 AM
Application Redlines Review 1 8/27/2018 10:24:28 AM
View Falcon Fire Protection District
8/22/2018 3:23:46 PM
8/22/2018 3:23:46 PM
View PCD Engineering Division
8/27/2018 9:08:27 AM
Review 1 comments on the following documents will be uploaded by the project manager:
- Traffic Study
- Drainage Report
- Operations and Maintenance
- Construction Drawings
- Financial Assurance
- Plat

* Submit the following documents:
- EPC MS4 Post Construction Form (attached)
- Pond Maintenance Agreement.

* Add "PCD File No. SF-18-009" in the front page of the following documents:
- SDI Worksheet
- SWMP
- ESQCP

* The uploaded GEC was for the pre-development grading. Submit a Grading and Erosion Control Plan that's specific to the proposed improvements for this filing. Can be a part of the Construction Drawings.
8/27/2018 9:08:27 AM
Pikes Peak Regional Building Department
8/21/2018 11:08:34 AM
Enumerations has the following comments:

1. Addressing was assigned for this subdivision in 2006, configuration did not change except for on DEVONCOVE DRIVE. MS Civil has been contacted regarding the error.
2. Regional Building, Enumerations department did not start charging addressing fees until January 2008, therefore all lot and tract fees will be due.
3. Standard Plat comments apply.

Floodplain has no comment.
8/21/2018 11:08:34 AM
View Colorado Parks and Wildlife
8/20/2018 1:36:13 PM
8/20/2018 1:36:13 PM
View Colorado Division of Water Resources
8/20/2018 11:21:38 AM
8/20/2018 11:21:38 AM
View EPC County Attorney's Office
8/14/2018 4:22:26 PM
Changes to SIA are attached. Please provide a Detention Maintenance Agreement if needed. 8/14/2018 4:22:26 PM
View 911 Authority - El Paso/Teller County
8/6/2018 11:48:10 AM
See Attached 8/6/2018 11:48:10 AM
View EPC Environmental Services
8/3/2018 2:57:09 PM
8/3/2018 2:57:09 PM
View Mountain View Electric Association, Inc.
8/2/2018 4:13:46 PM
8/2/2018 4:13:46 PM
Colorado State Forest Service
7/31/2018 10:46:33 AM
The primary wildland fuel type for this proposal is grassland with scattered trees having a low wildfire hazard potential. No special fire mitigation plans or other actions are necessary for final approval by the Colorado State Forest Service. 7/31/2018 10:46:33 AM