View: Project Documents
Agency | Comment | ||
---|---|---|---|
Colorado Geological Survey
2/10/2020 2:46:38 PM |
Colorado Geological Survey reviewed the overall Carriage Meadows Subdivision in 2006. RMG's Preliminary Subsurface Soil Investigation, Proposed Carriage Meadows Subdivision, Marksheffel Rd & Fontaine Blvd (August 4, 2006) contains a valid preliminary characterization of subsurface conditions based on the results of 12 test borings (six borings by RMG, and six by Kumar). The lot layout and density shown in RMG's 2006 report are fairly similar to that currently proposed. Loose, low blow count, relatively dry soils have been encountered within the Carriage Meadows/Lorson Ranch area. Lot-specific geotechnical investigation, testing, characterization and analysis will be needed to specify subgrade preparation requirements (including, if necessary, overexcavation, which should occur on a block- or filing-wide basis, not at the scale of individual lots), and for use in design of individual foundations, floor systems, subsurface drainage, pavements, etc. CGS recognizes that modifications may be needed based on grading and foundation excavation observations. |
2/10/2020 2:46:38 PM | |
PCD Engineering Division
1/30/2020 3:06:58 PM |
Revised sheets have been approved. | 1/30/2020 3:06:58 PM | |
PCD Project Manager
1/28/2020 4:28:38 PM |
CD sheets revised and approved January 2020 | 1/28/2020 4:28:38 PM | |
EPC County Attorney's Office
1/27/2020 2:12:48 PM |
Spoke to PCD Engineering. Nothing needed from OCA at this time. Please let me know if that changes. | 1/27/2020 2:12:48 PM | |
PCD Project Manager
1/23/2020 4:54:30 PM |
Please have your surveyor record the affidavit and provide us with a recorded copy. | 1/23/2020 4:54:30 PM | |
PCD Engineering Division
1/23/2020 4:41:56 PM |
Please submit the revised CD sheets in EDARP for approval. | 1/23/2020 4:41:56 PM | |
PCD Engineering Division
11/15/2018 12:32:32 PM |
No Engineering comments. Provide signed CDs. | 11/15/2018 12:32:32 PM | |
PCD Engineering Division
4/25/2018 7:48:48 PM |
Ready for signature. | 4/25/2018 7:48:48 PM | |
PCD Project Manager
4/24/2018 7:19:54 AM |
This item is scheduled for May 1 PC and May 22 BOCC | 4/24/2018 7:19:54 AM | |
PCD Project Manager
4/24/2018 7:19:27 AM |
Please update FAE and other engineering docs to be approved with signatures | 4/24/2018 7:19:27 AM | |
View |
EPC Parks Department
4/3/2018 12:42:20 PM |
See attached comments. | 4/3/2018 12:42:20 PM |
View |
PCD Project Manager
3/28/2018 3:48:54 PM |
Plat Redlines. Legal and acreage on tract table was not corrected. Please correct and reload. | 3/28/2018 3:48:54 PM |
Pikes Peak Regional Building Department
3/27/2018 8:38:51 AM |
Regarding a request for approval of a final plat for Carriage Meadows North Filing No. 1, Enumerations has the following comments: 1. Per our last set of comments, Enumerations has requested verification that for the street named Cider Mill, that the suffix Place is acceptable to Justin Annan at El Paso/Teller 911 but has not received that confirmation. Enumerations cannot approve the mylar for this plat without this confirmation. 2. Enumerations has been provided with a copy of this plat for addressing and we have established an addressing plan for this subdivision. The developer should contact Enumerations with contact information on who to provide these addresses to so that they can be placed on the mylar prior to mylar review. 3. Enumerations will review the mylar prior to recording for addressing, title block, floodplain statement and road names. A $10 per lot/tract Enumerations fee will be due at the time of mylar review. 4. Provide a copy of the final recorded plat for our records. Enumerations will not approve any plans submitted for this development without a copy of the final recorded plat in our records. Floodplain has no comment or objection to this submittal. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
3/27/2018 8:38:51 AM | |
View |
EPC Health Department
3/26/2018 7:43:47 PM |
3/26/2018 7:43:47 PM | |
View |
PCD Project Manager
3/22/2018 4:11:46 PM |
Grading and Erosion Control Red lines. Same comment on SWMP | 3/22/2018 4:11:46 PM |
View |
PCD Project Manager
3/22/2018 3:59:50 PM |
FAE V_3 red lines | 3/22/2018 3:59:50 PM |
View |
PCD Engineering Division
3/22/2018 3:37:08 PM |
See comment letter and redlines. | 3/22/2018 3:37:08 PM |
View |
EPC County Attorney's Office
3/16/2018 12:05:32 PM |
3/16/2018 12:05:32 PM | |
View |
Colorado Division of Water Resources
3/8/2018 2:16:31 PM |
This office previously provided comments regarding this subdivision referral on 12/19/2017. There appears to be no change in the referral materials that would impact the previous comments. Therefore, please refer to the the previous comment letter dated 12/19/2017. | 3/8/2018 2:16:31 PM |
View |
Fountain Mutual Irrigation Company
3/5/2018 7:41:36 AM |
Hi Kari: Please see attached letter to applicant and engineer dated February 19, 2018 referencing Conditional Approval by FMIC for both Carriage Meadows S & N Filings No. 1. | 3/5/2018 7:41:36 AM |
View |
PCD Project Manager
2/28/2018 7:38:53 AM |
MDT letter V_2 | 2/28/2018 7:38:53 AM |
View |
PCD Project Manager
2/28/2018 7:32:58 AM |
SDI red lines | 2/28/2018 7:32:58 AM |
View |
PCD Project Manager
2/28/2018 7:32:34 AM |
O & M V_2 red lines | 2/28/2018 7:32:34 AM |
View |
PCD Project Manager
2/28/2018 7:32:01 AM |
MS4 worksheet red lines | 2/28/2018 7:32:01 AM |
View |
PCD Project Manager
2/28/2018 7:31:07 AM |
Grading & Erosion Control Plan V_2 red lines | 2/28/2018 7:31:07 AM |
View |
PCD Project Manager
2/28/2018 7:30:33 AM |
Drainage report V_2b red lines | 2/28/2018 7:30:33 AM |
View |
PCD Project Manager
2/28/2018 7:30:00 AM |
CDs V_2b red lines | 2/28/2018 7:30:00 AM |
View |
PCD Project Manager
2/28/2018 7:29:16 AM |
LOI V_2 red lines | 2/28/2018 7:29:16 AM |
View |
PCD Project Manager
2/28/2018 7:28:56 AM |
Drainage report V_2 red lines | 2/28/2018 7:28:56 AM |
View |
PCD Project Manager
2/28/2018 7:28:29 AM |
Landscape plan V_2 red lines | 2/28/2018 7:28:29 AM |
View |
PCD Project Manager
2/28/2018 7:28:02 AM |
Plat V_2 red lines | 2/28/2018 7:28:02 AM |
View |
PCD Project Manager
2/28/2018 7:27:35 AM |
WQ Buffer Detention Agreement red lines review 2 | 2/28/2018 7:27:35 AM |
View |
PCD Engineering Division
2/27/2018 10:51:14 PM |
See comment letter and redlines. | 2/27/2018 10:51:14 PM |
Pikes Peak Regional Building Department
2/20/2018 8:17:15 AM |
Regarding a request for approval of a final plat for Carriage Meadows North Filing No. 1, Enumerations has the following comments: 1. The street name shown on the plat as Cider Mill Place was approved as Cider Mill Drive. Verify with Justin Annan (jannan@elpasoteller911.org) that the change in suffix is acceptable. The other road names are OK. 2. Enumerations has already been provided with a copy of the plat for addressing. None of the tracts indicate a need for an address. Please confirm that none will be needed. Once addresses have been established, place on the mylar in the appropriate location. 3. Prior to recording, Enumerations will review the mylar for addressing, title block, street names and floodplain statement. A fee of $10 per lot/tract addressed, payable to Pikes Peak Regional Building Department will be due at the time of mylar review. 4. Provide a copy of the final recorded plat to Enumerations. Approval of any plans submitted for this development will be pending receipt in our office of a copy of the final recorded plat. Floodplain has no comment or objection to this submittal. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
2/20/2018 8:17:15 AM | |
View |
US Postal Service
1/23/2018 12:29:51 PM |
There are four locations for this development that was submitted. I have relocated one location and worked with the developer to move the location from Galpin Dr. to Rubicon Dr. I have attached the updated locations and CBUs needed for this development. | 1/23/2018 12:29:51 PM |
View |
EPC Health Department
1/8/2018 11:17:35 AM |
1/8/2018 11:17:35 AM | |
View |
PCD Project Manager
1/4/2018 5:32:54 PM |
MTD letter review 1 | 1/4/2018 5:32:54 PM |
View |
PCD Engineering Division
1/4/2018 5:24:20 PM |
See comment letter and redlines. | 1/4/2018 5:24:20 PM |
View |
PCD Project Manager
1/4/2018 5:24:03 PM |
Drainage Report V-1 red lines | 1/4/2018 5:24:03 PM |
View |
PCD Project Manager
1/4/2018 5:23:07 PM |
ESQCP V-1 red lines | 1/4/2018 5:23:07 PM |
View |
PCD Project Manager
1/4/2018 5:22:36 PM |
FAE V-1 red lines | 1/4/2018 5:22:36 PM |
View |
PCD Project Manager
1/4/2018 5:22:13 PM |
Grading and Erosion Control Plan V-1 red lines | 1/4/2018 5:22:13 PM |
View |
PCD Project Manager
1/4/2018 5:21:32 PM |
LOI V-1 red lines | 1/4/2018 5:21:32 PM |
View |
PCD Project Manager
1/4/2018 5:20:55 PM |
SWMP Redlines V-1 | 1/4/2018 5:20:55 PM |
View |
PCD Project Manager
1/4/2018 5:20:26 PM |
Title Commitment Red lines | 1/4/2018 5:20:26 PM |
View |
PCD Project Manager
1/4/2018 5:19:57 PM |
CD V-1 red lines | 1/4/2018 5:19:57 PM |
View |
PCD Project Manager
1/4/2018 5:19:00 PM |
landscape plan red lines V-1 | 1/4/2018 5:19:00 PM |
View |
PCD Project Manager
1/4/2018 5:18:34 PM |
Plat red lines V-1 | 1/4/2018 5:18:34 PM |
View |
PCD Engineering Division
1/3/2018 10:49:40 AM |
1/3/2018 10:49:40 AM | |
Fountain
1/2/2018 3:31:51 PM |
No comments. | 1/2/2018 3:31:51 PM | |
Pikes Peak Regional Building Department
12/29/2017 9:56:04 AM |
Regarding a request for approval of a final plat for Carriage Meadows North Filing No. 1, Enumerations has the following comments: 1. Per Regional Building Code, section RBC312.8 addresses must appear on plats. Submit a 100 scale copy of the plat to our office for addressing. Place an (xxxx) on all lots and tracts which will require an address, in the location the address will be needed. Once addressing is completed, the addresses will be returned so that they may be placed on the mylar prior to recording. 2. Prior to recording, Enumerations will review the mylar for addressing, title block, street names and floodplain statement. A fee of $10 per lot/tract addressed, payable to Pikes Peak Regional Building Department will be due at the time of mylar review. 3. Provide a copy of the final recorded plat to Enumerations. Approval of any plans submitted for this development will be pending receipt in our office of a copy of the final recorded plat. 4. All road names have been previously approved, except that the street labeled as Cider Mill Place was approved as Cider Mill Drive. Verify with Justin Annan (jannan@elpasoteller911.org) that changing the street suffix is acceptable. 5. Since the northern boundary of this development borders on Banning Lewis Ranch property which contains floodplain area we are assuming that Cider Mill will not continue to the north. Please verify if this is the case. If this street is to continue to the north, please provide a plan for this extension so that this street can be properly addressed. Floodplain has the following comments: 1. This development is bordered on the north and east sides by floodplain area. Show the floodplain boundaries and base flood elevations on the plat. Contact Floodplain Administrator Keith Curtis (keith@pprbd.org, 719-327-2898) with questions or concerns. BRENT JOHNSON Enumerations Plans Examiner (719) 327-2888 www.pprbd.org |
12/29/2017 9:56:04 AM | |
View |
Colorado Division of Water Resources
12/28/2017 10:58:30 AM |
12/28/2017 10:58:30 AM | |
View |
EPC Parks Department
12/27/2017 11:41:56 AM |
PAB Endorsed Comments 12-13-2017 | 12/27/2017 11:41:56 AM |
View |
Mountain View Electric Association, Inc.
12/20/2017 3:36:04 PM |
12/20/2017 3:36:04 PM | |
View |
EPC Environmental Services
12/14/2017 8:50:44 AM |
12/14/2017 8:50:44 AM |