Project Review Comments

Back to List


Project Name
The Beach at Woodmoor Final Plat
Description
Final plat to create 35 single family residential lots on approximately 12.38 acres
Location
The property is located on either side of Lake Woodmoor Drive, east of the intersection of Lake Woodmoor Drive and Lower Lake Road, one-half mile east of Woodmoor Drive
Parcels
7114100038 7114100038 7114107015 7114107015
Applicant
N.E.S.
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073
EA Number
EA-16-106
File Number
SF17015
Project Manager
Nina Ruiz
Status
Closed
Created
5/8/2017 8:06:19 AM

View: Project Documents



Review Comments (36)

Link Agency Comment
PCD Engineering Division
5/17/2018 9:52:04 AM
Engineering documents have been approved. 5/17/2018 9:52:04 AM
View PCD Engineering Division
3/19/2018 11:31:55 AM
Review 5: The cross section for the roadway ditch flow analysis at the detention outfall does not reflect the existing condition. Revise accordingly. Depending on the results additional improvements may be required. 3/19/2018 11:31:55 AM
View EPC County Attorney's Office
3/8/2018 12:29:43 PM
3/8/2018 12:29:43 PM
PCD Engineering Division
3/1/2018 8:34:26 AM
Review 4: Comments resolved on the construction plans. However, the drainage report comments does not appear to have been addressed. Depending on the results from addressing the review 3 drainage report comments, there may be revisions to the construction plans which will need to be reviewed. 3/1/2018 8:34:26 AM
Woodmoor Water and Sanitation District
2/26/2018 4:28:11 PM
See comments returned for plans on 2/26/18. No added comments. 2/26/2018 4:28:11 PM
View PCD Engineering Division
2/5/2018 3:22:00 PM
Attached are review 3 redline comments to the construction plans. 2/5/2018 3:22:00 PM
View PCD Engineering Division
2/5/2018 1:03:44 PM
Attached are review 3 redline comments to the drainage report. 2/5/2018 1:03:44 PM
PCD Engineering Division
2/5/2018 1:06:03 PM
Review 3
1. Deviation request is pending with the County Engineer.

2. One of the comments in the construction drawings is to submit a document verifying that the adjacent owner has given permission to conduct offsite grading in their property (the school property). This is required prior to approval of the construction drawings.

Comments resolved on the following documents:
SWMP
Plat
2/5/2018 1:06:03 PM
View Lewis Palmer 38
1/4/2018 9:43:19 AM
1/4/2018 9:43:19 AM
PCD Engineering Division
11/28/2017 3:46:55 PM
Per the Drainage Criteria Manual Chapter 11 Section 11.3.3, a geotechnical analysis and report prepared by a Colorado Professional Enginer with recommendations for the foundation preparation and embankment construction shall be submitted to the County with the complete design analysis for all permanent detention facilities. Incorporate the recommendations within the construction plans. 11/28/2017 3:46:55 PM
PCD Engineering Division
11/28/2017 2:59:26 PM
Submit the following documents:
- ESQCP
- Private Detention Pond Maintenance Agreement.

Coordinate with the Project Manager to create a document item for these items.
11/28/2017 2:59:26 PM
PCD Engineering Division
11/28/2017 10:52:03 AM
The County will require a copy of the submitted "Non-Jurisdictional Water Impoundment Structure" form prior to pre-construction meeting.

Link to the form http://water.state.co.us/DWRIPub/Documents/ds_impound.pdf
11/28/2017 10:52:03 AM
PCD Engineering Division
11/28/2017 10:48:16 AM
Redline comments on the following pdfs will be uploaded by the project manager:
- Plat
- Drainage Report
- Construction Plans
11/28/2017 10:48:16 AM
View Woodmoor Water and Sanitation District
11/22/2017 4:28:28 PM
See attached review documents. 11/22/2017 4:28:28 PM
View Woodmoor Water and Sanitation District
11/22/2017 4:27:46 PM
See attached review documents. 11/22/2017 4:27:46 PM
View Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
10/11/2017 5:07:22 PM
10/11/2017 5:07:22 PM
View PCD Project Manager
6/29/2017 5:25:07 PM
TRAFFIC IMPACT STUDY 6/29/2017 5:25:07 PM
View PCD Project Manager
6/29/2017 5:23:33 PM
SWMP 6/29/2017 5:23:33 PM
View PCD Project Manager
6/29/2017 5:20:46 PM
FINAINCIAL ASSURANCE 6/29/2017 5:20:46 PM
View PCD Project Manager
6/29/2017 4:01:24 PM
CONSTRUCTION DRAWINGS 6/29/2017 4:01:24 PM
View PCD Project Manager
6/29/2017 4:00:04 PM
PRELIMINARY/FINAL DRAINAGE REPORT 6/29/2017 4:00:04 PM
View PCD Project Manager
6/29/2017 3:43:06 PM
FINAL PLAT 6/29/2017 3:43:06 PM
View PCD Project Manager
6/29/2017 3:40:32 PM
LETTER OF INTENT 6/29/2017 3:40:32 PM
View PCD Project Manager
6/29/2017 3:32:17 PM
Please review all comments from the MDT comment review letter and redlines to documents attached to the request for resubmittal. 6/29/2017 3:32:17 PM
View Colorado Division of Water Resources
6/22/2017 11:59:52 AM
6/22/2017 11:59:52 AM
View Tri-Lakes-Monument Fire Protection District
6/22/2017 8:54:17 AM
The current project meets requirements for road access for Tri Lakes Monument Fire. All other aspects of the project shall conform with normal code requirements. 6/22/2017 8:54:17 AM
View Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
6/22/2017 5:11:58 AM
6/22/2017 5:11:58 AM
View EPC Health Department
6/21/2017 10:00:38 PM
6/21/2017 10:00:38 PM
Pikes Peak Regional Building Department
6/20/2017 2:31:49 PM
Enumerations:
Final plat pages are very difficult to read online, but once printed no issue reading the information.

Standard Final Plat comments:
1. Enumerations/Floodplain will review the mylar prior to plat for address placement, street naming, title block and floodplain statement.
2. $10.00 per lot and tract fee will be due at the time of the review of the mylar. If an address is not needed on a tract then no fee applies. Check should be made out to Regional Building Department. Paid directly to the Enumerations department.
3. A copy of the final recorded plat is required prior to plan submittal.



Floodplain:
Follow Floodplain code: RBC 313.18.25 All 100 Year Floodplain is required to be located into a tract. Please contact Keith, Floodplain Administrator keith@pprbd.org or 327-2898
6/20/2017 2:31:49 PM
911 Authority - El Paso/Teller County
6/19/2017 8:42:49 AM
No action for 911
All street names previously approved
Justin
6/19/2017 8:42:49 AM
View EPC Parks Department
6/16/2017 9:20:42 AM
El Paso County Community Services/Parks Final Comments 6/16/2017 9:20:42 AM
View Woodmoor Water and Sanitation District
6/15/2017 10:43:08 AM
See attached document for WWSD comments. 6/15/2017 10:43:08 AM
PCD Engineering Division
6/7/2017 10:45:18 AM
Engineering redline comments on the following pdf documents will be uploaded by the project managers: Construction Drawings, Final Drainage Report, Final Plat, Financial Assurance Estimates, Grading and Erosion Control, Letter of Intent, SWMP and Traffic Impact Study. 6/7/2017 10:45:18 AM
View PCD Engineering Division
6/7/2017 10:17:58 AM
See the attached checklist for missing items. Return the checklist identifying the page in the SWMP where the missing items are addressed. 6/7/2017 10:17:58 AM
View PCD Engineering Division
6/5/2017 1:47:56 PM
Include the following documents with the next resubmittal:
1. UDFCD SDI Worksheet for each permanent ponds.
2. EPC MS4 Post Construction Form
6/5/2017 1:47:56 PM
EPC County Attorney's Office
5/31/2017 1:49:07 PM
Water review will be drafted upon receipt of SEO letter.
Edi Anderson
5/31/2017 1:49:07 PM