Project Details

Search


File Number
EGP192
Project Name
Grazing Yak Early Grading Permit
Description
The project proposes to construct a 35 megawatt solar farm facility on 270 acres of private land located southwest of the Town of Calhan, Colorado. Electricity generated by the project will interconnect into the Golden West Wind project substation via a 1-mile underground collection line, delivering power to Colorado Springs Utilities via an existing 29-mile generation tie line to the Jackson Fuller Substation. Location South of Washington Road, approximately 0.5 mile west of the intersection of Washington Road and Currier Road, Calhan, CO 80808
Parcels
1200000040 1200000040 1200000056 1200000056 1200000276 1200000276 1200000339 1200000339 1200000387 1200000387 1200000388 1200000388
Applicant
Core Consultants Inc.
Consultant Tina Brazil ( brazil@corecivil.com )
(215) 280-2370
Consultant Tina Brazil ( brazil@corecivil.com )
(215) 280-2370
EA Number
EA17223
File Prefix
EGP - Early Grading Permit
Year
2019
Project Manager
Kari Parsons
Status
Closed
Created
2/27/2019 7:48:36 AM

View: Review Comments


Approved Documents (5)

Link Document
View Erosion and Stormwater Quality Control Permit (ESQCP)
View Grading & Erosion Control Plan (8.5 x 11)
View Storm Water Management Plan (SWMP)
View Drainage Report - Final
View Financial Assurance Forms


Additional Documents (1)

Link Document Comment
View Pre-con applicants checklist to bring.


Review Documents (10)

Link Document Date
View Letter of Intent 4/25/2019 12:44:12 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 4/30/2019 3:10:38 PM
View MS4 Post Construction Form 4/25/2019 12:44:16 PM
View Grading & Erosion Control Plan (24 x 36) 7/1/2019 8:37:27 AM
View Storm Water Management Plan (SWMP) 4/25/2019 12:44:14 PM
View Drainage Letter 7/1/2019 8:37:25 AM
View DWR Non-Jurisdictional Water Impoundment Structure Application 4/25/2019 12:44:19 PM
View Financial Assurance Forms 7/1/2019 8:37:26 AM
View MS4 Form 6/9/2019 8:49:20 PM
View SDI spreadsheet 6/9/2019 8:49:21 PM



Events (27)

Date Comment
7/1/2019 3:09:21 PM Project Closed
7/1/2019 3:09:21 PM Project Approved: 7/1/2019
7/1/2019 8:39:01 AM Submission Triaged
7/1/2019 8:38:12 AM Submission received from Applicant
7/1/2019 7:23:23 AM Submission request sent to Applicant
6/26/2019 9:38:02 AM Request for Review Comments returned by PCD Engineering Division
6/10/2019 7:31:46 AM Request for Review Comments email sent for Project Grazing Yak Early Grading Permit for review by Kari Parsons on behalf of PCD Project Manager
6/10/2019 7:31:44 AM Request for Review Comments email sent for Project Grazing Yak Early Grading Permit for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
6/10/2019 7:31:23 AM Submission Triaged
6/9/2019 8:50:00 PM Submission received from Applicant
5/28/2019 12:53:24 PM Request for Review Comments returned by PCD Engineering Division
5/28/2019 12:38:25 PM Submission request sent to Applicant
5/28/2019 12:37:14 PM Request for Review Comments returned by PCD Project Manager
5/1/2019 5:27:56 PM Request for Review Comments email sent for Project Grazing Yak Early Grading Permit for review by Kari Parsons on behalf of PCD Project Manager
5/1/2019 5:27:52 PM Request for Review Comments email sent for Project Grazing Yak Early Grading Permit for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/1/2019 5:25:55 PM Fees paid: 5/1/2019 (Receipt: 1001407)
5/1/2019 4:44:59 PM Payment Request sent: 5/1/2019
5/1/2019 4:44:54 PM File # Assigned: EGP192
5/1/2019 3:09:07 PM Submission Triaged
4/30/2019 3:11:53 PM Submission received from Applicant
4/26/2019 9:07:27 AM Submission request sent to Applicant
4/26/2019 9:07:22 AM Submission Triaged
4/25/2019 12:45:09 PM Submission received from Applicant
2/27/2019 7:52:40 AM Submission request sent to Applicant
2/27/2019 7:48:41 AM Project Manager Assigned: Kari Parsons
2/27/2019 7:48:41 AM EA Assigned: EA17223
2/27/2019 7:48:40 AM Project Created