Project Details

Search


File Number
PPR1816
Project Name
Les Schwab Tire Center, Site Development Plan
Description
Site Development Plan to allow vehicle repair in the CR zoning district
Location
Lots 3-4, Meridian Crossing Filing No. 1
Parcels
5312106009 5312106009 5312106010 5312106010
Applicant
Galloway & Company, Inc.
Project Manager Aaron McLean ( AARONMCLEAN@GALLOWAYUS.COM )
(303) 770-8884 x2216
Project Manager Aaron McLean ( AARONMCLEAN@GALLOWAYUS.COM )
(303) 770-8884 x2216
EA Number
EA182
File Prefix
PPR - Plot Plan Review
Year
2018
Project Manager
Nina Ruiz
Status
Closed
Created
1/25/2018 8:08:21 AM

View: Review Comments



Additional Documents (1)

Link Document Comment
View Email Communications Client letting project Expire.


Review Documents (20)

Link Document Date
View Application/Petition Form 4/9/2018 1:09:38 PM
View Legal Description (MS WORD Version required) 4/9/2018 1:19:22 PM
View Letter of Intent 3/1/2019 3:33:01 PM
View Title Commitment (Current within 30 days of submittal) 4/9/2018 1:09:46 PM
View Vicinity/Location Map 4/9/2018 1:09:47 PM
View Applicant Comment Response Letter 3/1/2019 3:31:19 PM
View Deviation Request 4/9/2018 1:19:24 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 6/11/2018 5:15:11 PM
View Grading & Erosion Control Plan (24 x 36) 7/11/2020 3:09:44 PM
View Landscape Plan drawings (24" x 36") 3/1/2019 3:31:16 PM
View Sign Plan 4/9/2018 1:09:45 PM
View Site Development Plan (24" x 36") 7/11/2020 3:09:45 PM
View Storm Water Management Plan (SWMP) 8/7/2019 3:09:00 PM
View Drainage Report - Final 8/7/2019 3:08:59 PM
View Soils & Geology Report 4/3/2019 1:04:08 PM
View Elevation Plans (24" x 36") 6/11/2018 5:15:06 PM
View Financial Assurance Forms 7/11/2020 3:09:43 PM
View Floor Plans (24" x 36") 4/9/2018 1:09:41 PM
View Lighting Plan (24" x 36") 4/9/2018 1:09:44 PM
View Traffic Memo 8/14/2018 9:57:14 AM



Events (92)

Date Comment
11/10/2020 4:58:46 PM Project Closed
11/10/2020 4:58:46 PM Project Cancelled: 11/10/2020
10/20/2020 1:42:21 PM Submission request sent to Applicant
8/5/2020 6:17:37 AM Submission request sent to Applicant
8/4/2020 4:59:06 PM Request for Review Comments returned by PCD Engineering Division
7/30/2020 5:26:29 PM Request for Review Comments returned by PCD Project Manager
7/13/2020 5:34:11 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
7/13/2020 5:34:10 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
7/13/2020 5:33:36 AM Submission Triaged
7/11/2020 3:09:52 PM Submission received from Applicant
7/8/2020 12:45:07 PM Project Manager Assigned: Nina Ruiz
7/1/2020 11:50:30 AM Submission request sent to Applicant
8/29/2019 11:33:25 AM Submission request sent to Applicant
8/29/2019 11:32:15 AM Request for Review Comments returned by PCD Project Manager
8/28/2019 7:14:03 PM Request for Review Comments returned by PCD Engineering Division
8/14/2019 1:56:36 PM Submission Triaged
8/14/2019 1:21:37 PM Submission received from Applicant
8/12/2019 8:04:26 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Gabe Sevigny on behalf of PCD Project Manager
8/12/2019 8:04:24 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
8/12/2019 8:00:21 AM Submission request sent to Applicant
8/12/2019 7:59:38 AM Submission Triaged
8/8/2019 8:10:47 AM Submission received from Applicant
4/11/2019 3:34:57 PM Request for Review Comments returned by Falcon Fire Protection District
4/5/2019 12:29:25 PM Submission request sent to Applicant
4/5/2019 12:26:37 PM Request for Review Comments returned by PCD Project Manager
4/5/2019 12:22:52 PM Request for Review Comments email resent for Project Les Schwab Tire Center, Site Development Plan for review by Gabe Sevigny on behalf of PCD Project Manager
4/5/2019 9:12:03 AM Submission request sent to Applicant
4/5/2019 9:08:07 AM Request for Review Comments returned by PCD Project Manager
4/3/2019 3:01:26 PM Request for Review Comments returned by PCD Engineering Division
4/3/2019 1:16:53 PM Submission Triaged
4/3/2019 1:04:18 PM Submission received from Applicant
4/3/2019 12:13:24 PM Submission request sent to Applicant
3/18/2019 10:36:44 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Josh Miller on behalf of Falcon Highlands Metro
3/18/2019 10:36:28 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
3/18/2019 10:36:24 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Gabe Sevigny on behalf of PCD Project Manager
3/18/2019 10:36:15 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/4/2019 2:43:17 PM Submission Triaged
3/1/2019 3:33:05 PM Submission received from Applicant
9/6/2018 11:43:19 AM Submission request sent to Applicant
9/6/2018 11:41:30 AM Request for Review Comments returned by PCD Project Manager
9/5/2018 6:18:23 PM Request for Review Comments returned by PCD Engineering Division
8/15/2018 3:10:58 PM Request for Review Comments returned by EPC County Attorney's Office
8/14/2018 11:38:07 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Lori Seago on behalf of EPC County Attorney's Office
8/14/2018 11:30:36 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Josh Miller on behalf of Falcon Highlands Metro
8/14/2018 11:30:35 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
8/14/2018 11:30:34 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
8/14/2018 11:30:33 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Gabe Sevigny on behalf of PCD Project Manager
8/14/2018 11:30:31 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
8/14/2018 10:12:40 AM Submission Triaged
8/14/2018 9:59:31 AM Submission received from Applicant
8/14/2018 8:30:17 AM Submission request sent to Applicant
7/12/2018 11:58:10 AM Submission request sent to Applicant
7/12/2018 11:54:36 AM Request for Review Comments returned by PCD Project Manager
7/10/2018 4:36:26 PM Request for Review Comments returned by PCD Engineering Division
6/15/2018 11:14:44 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Gabe Sevigny on behalf of PCD Project Manager
6/15/2018 11:14:43 AM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
6/15/2018 10:53:18 AM Submission Triaged
6/15/2018 10:20:34 AM Submission received from Applicant
5/28/2018 9:39:18 AM Request for Review Comments returned by Falcon Fire Protection District
5/14/2018 8:59:39 AM Submission request sent to Applicant
5/14/2018 8:55:15 AM Request for Review Comments returned by PCD Project Manager
5/14/2018 8:54:14 AM Request for Review Comments returned by PCD Project Manager
5/14/2018 8:53:19 AM Request for Review Comments email resent for Project Les Schwab Tire Center, Site Development Plan for review by Gabe Sevigny on behalf of PCD Project Manager
5/7/2018 8:02:46 AM Submission request sent to Applicant
5/7/2018 7:59:38 AM Request for Review Comments returned by PCD Project Manager
5/7/2018 7:58:38 AM Request for Review Comments returned by PCD Project Manager
5/4/2018 1:30:05 PM Request for Review Comments returned by PCD Engineering Division
5/3/2018 8:52:32 AM Request for Review Comments returned by Pikes Peak Regional Building Department
4/17/2018 10:09:17 PM Request for Review Comments returned by EPC Health Department
4/17/2018 12:29:49 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
4/12/2018 12:58:50 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
4/12/2018 12:58:49 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Cynthia M. Beyer on behalf of Falcon Highlands Metro
4/12/2018 12:58:48 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
4/12/2018 12:58:47 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
4/12/2018 12:58:45 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
4/12/2018 12:58:44 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
4/12/2018 12:58:42 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by on behalf of EPC Health Department
4/12/2018 12:58:41 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Gabe Sevigny on behalf of PCD Project Manager
4/12/2018 12:58:40 PM Request for Review Comments email sent for Project Les Schwab Tire Center, Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
4/12/2018 12:55:27 PM Fees paid: 4/12/2018 (Receipt: 1000605)
4/12/2018 12:12:59 PM Payment Request sent: 4/12/2018
4/12/2018 11:35:48 AM Submission Triaged
4/12/2018 10:17:40 AM Submission received from Applicant
4/11/2018 10:26:48 AM Project Manager Assigned: Gabe Sevigny
4/11/2018 10:23:23 AM File # Assigned: PPR1816
4/11/2018 10:23:16 AM Submission request sent to Applicant
4/11/2018 10:22:11 AM Submission Triaged
4/9/2018 1:19:31 PM Submission received from Applicant
1/25/2018 8:12:17 AM Submission request sent to Applicant
1/25/2018 8:08:29 AM Project Manager Assigned: Nina Ruiz
1/25/2018 8:08:29 AM EA Assigned: EA182
1/25/2018 8:08:29 AM Project Created