4/4/2025 3:30:24 PM
|
Project Closed
|
4/4/2025 3:30:24 PM
|
Project Approved: 4/4/2025
|
2/13/2025 1:36:40 PM
|
Request for Approval returned by PCD Project Manager
|
2/13/2025 1:34:35 PM
|
Request for Approval sent for Project 4171 PINEHURST CIR for review by Justin Kilgore on behalf of PCD Project Manager
|
2/11/2025 7:48:12 AM
|
Child Access Permit (driveway) project (AP25110)
|
2/11/2025 7:46:49 AM
|
Child Access Permit (driveway) project Approved (AP25109)
|
1/30/2025 1:34:04 PM
|
Request for Approval returned by PCD Project Manager
|
1/30/2025 1:31:58 PM
|
Request for Approval sent for Project 4171 PINEHURST CIR for review by Justin Kilgore on behalf of PCD Project Manager
|
1/30/2025 1:31:45 PM
|
Child BESQCP (drainage permit) project Approved (ESR25101)
|
1/30/2025 1:18:10 PM
|
Fees will be collected by Building Department
|
1/30/2025 1:18:10 PM
|
File # Assigned: SFD25111
|
1/30/2025 1:18:09 PM
|
Project Manager Assigned: Tara Younger
|
1/30/2025 1:18:09 PM
|
Project Created
|