11/17/2026 11:47:30 AM
|
Project Closed
|
|
11/17/2026 11:47:30 AM
|
Project Approved: 11/17/2026
|
|
11/17/2026 9:17:30 AM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
11/13/2026 7:54:53 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
11/13/2026 7:54:53 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
11/13/2026 7:52:32 PM
|
Submission Triaged
|
|
11/12/2026 4:02:07 PM
|
Submission received from Applicant
|
|
11/12/2026 11:21:27 AM
|
Submission request sent to Applicant
|
|
11/12/2026 11:21:04 AM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
11/10/2026 2:56:27 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
11/4/2026 2:52:43 PM
|
Request for Review Comments returned by EPC DPW Asset Management
|
|
10/20/2026 5:21:21 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
10/20/2026 5:21:20 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
10/20/2026 5:21:19 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
10/20/2026 5:21:18 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
10/20/2026 5:21:17 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
10/20/2026 5:21:16 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
10/20/2026 5:21:15 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
10/20/2026 5:21:14 PM
|
Request for Review Comments email sent for Project Flying Horse North Filing No. 6 for review by on behalf of EPC DPW Asset Management
|
|
10/20/2026 5:19:30 PM
|
Submission Triaged
|
|
10/20/2026 4:27:15 PM
|
Submission received from Applicant
|
|
10/5/2026 2:15:08 PM
|
Submission request sent to Applicant
|
|
10/5/2026 2:12:47 PM
|
Project Manager Assigned: Stormwater Glenn Reese
|
|
9/21/2026 7:40:47 AM
|
Submission request sent to Applicant
|
|
9/21/2026 7:38:31 AM
|
Set Applicant to Flying Horse Development, LLC
|
|
9/21/2026 7:37:51 AM
|
No Fees
|
|
9/21/2026 7:37:51 AM
|
File # Assigned: ASB2626
|
|
9/21/2026 7:37:51 AM
|
Project Manager Assigned: Bret Dilts
|
|
9/21/2026 7:37:51 AM
|
Project Created. Parent Project: Flying Horse North Filing No. 6 (SF2529)
|